On site, a $1/m² margin hit on 2,500 m² is real — who's covering extra wastage if tiles drop to $5/m²?
Contracts & Claims
Construction contracts, claims management, variation notices, contractual risk, and consultant correspondence.
23 articles on Contracts & Claims
I once started a project without a proper handover. The chaos that followed taught me the hard way about the risks mentioned here.
Jihad ahmad, I hear you! It’s like jumping into a pool without checking if there’s water. A proper handover really does save a lot of headaches later on.
It's interesting how advance payments are often misunderstood as a price lock mechanism. Have any contractors experienced issues with this misconception? It seems crucial to clarify these terms in contracts to avoid future disputes.
The article highlights the importance of timely notices, but it might be beneficial to include examples of common disputes arising from missed notices. Have you encountered a situation where a lack of notice led to a significant issue on a project?
It's interesting how the article emphasizes the role of notices in preventing disputes. Has anyone experienced a situation where a well-documented notice helped resolve a potential conflict? Sharing such examples could enhance understanding of their practical impact.
Managing VOs sounds like a juggling act. I once had a project where a simple design tweak turned into a month-long delay. Keeping a detailed log really helps avoid those surprises!
It's funny how a simple email or a note can turn into a legally binding instruction. Makes you think twice about what you write! I guess every little comment could be a potential claim waiting to happen.
Using the Site Instruction Form sounds practical, but I wonder how often contractors actually comply immediately.
I guess the real challenge is getting everyone on the same page after the instruction is issued.
Using a CCD feels a bit like giving a kid a cookie before dinner—necessary but tricky! It's good to have a clear record to avoid future tantrums over costs.
Filling out a CCD is like assembling IKEA furniture—follow the steps, keep the instructions handy, and hope you don’t end up with extra pieces later on!
It's funny how something as simple as an ASI can save a project from spiraling out of control. I once had to clarify a paint color, and it turned into a whole debate! Keeping it minor is key,
The distinction between contractual and statutory warranty periods is crucial. It would be helpful to explore how different jurisdictions handle latent defects and the implications for contractors and employers. Has anyone experienced challenges with these distinctions in practice?
It’s interesting how different jurisdictions handle liability periods. How do contractors typically manage the risk of latent defects in regions with longer statutory periods?
The differences in liability periods highlight the need for clear contract terms. How do contractors ensure compliance with both FIDIC and local laws, especially when statutory periods exceed contractual ones?
The article raises important points about advance payments. It would be interesting to explore how different jurisdictions handle these issues. Are there examples of successful reforms in other regions that could serve as models for the construction industry?
Zahra Esfahani: That's a valuable point. It would also be worthwhile to examine how the proposed reforms, like non-refundable advance payments, might impact contractor relationships with employers. Could these changes lead to more collaborative project environments?
The article highlights significant issues with advance payments. It would be insightful to discuss how different industries outside construction manage similar financial risks. Are there best practices we could adopt to enhance contractor protections?
It's funny how a 10-day delay can feel like a lifetime on a project. Keeping those baselines updated is key!
Hiroshi Takahashi: True! It’s wild how a small delay can snowball. I once saw a project stall over a week just because of a late delivery. Keeping those baselines updated really does save headaches later on!
It's funny how many projects skip the kick-off meeting. It's like trying to bake a cake without checking the recipe first. You end up with a mess!
It's interesting how the article highlights the importance of accurate delay categorization. I once worked on a project where we had a mix of excusable and non-excusable delays, and it really complicated the claims process. Keeping detailed records was a lifesaver
Lena Miller: I can relate to that! It’s like trying to untangle a bunch of wires—excusable and non-excusable delays just make everything messier. Keeping tabs on everything really helps.
As someone who's dealt with construction delays, I can say the as-planned vs. as-built method really helps in pinpointing where things went sideways. It's like a reality check for projects!
Navigating RFIs can feel like a game of telephone. One wrong word and it’s a whole new ballgame! Keeping it clear and concise is key.
I once submitted an EOT claim without a proper delay log, and it turned into a real headache. This checklist seems like a lifesaver to avoid that mess again. Definitely downloading it!
On site provisional sums for façade packages often stall follow trades; how do you budget floats for authority approvals?