Collapsed As Built image
Collapsed As Built
Apr 19, 2025
⏳ Estimated reading time: 3 min
Discover how Collapsed As-Built (But-For) analysis helps evaluate delays in completed construction projects. Learn when to use it, how it works, and how it supports forensic delay claims.
Collapsed As-Built (But-For) Analysis | Construction Delay Method

Collapsed As-Built (But-For) Analysis in Construction Projects

Introduction

Collapsed As-Built, often referred to as But-For Analysis, is a retrospective delay analysis method used to assess how a project would have progressed but for specific delay events. By removing delays from the actual as-built schedule, this method models a hypothetical scenario to determine whether the delay truly impacted the project’s completion date.

It is widely used in formal claims, arbitration, and forensic delay assessments, especially when a detailed as-built schedule and robust records are available.


1. What Is Collapsed As-Built Analysis?

In this method, analysts take the final as-built schedule and remove one or more delay events (typically owner-related or excusable delays). The goal is to simulate what the finish date would have been if those delays hadn't occurred.

This "collapsed" schedule shows the adjusted project timeline, offering a basis to measure actual vs. theoretical impact.


2. How the Analysis Works

Step 1:

Start with the completed as-built schedule, including all activities and actual dates.

Step 2:

Identify and remove delay-related activities (e.g., design approval hold, variation order) from the schedule.

Step 3:

Recalculate the schedule using Critical Path Method (CPM) tools (e.g., Primavera P6, MS Project).

Step 4:

Compare the recalculated finish date with the actual finish date to determine delay impact.


3. Mini Case Example

A project finishes on Day 320. Analysts remove three owner-driven delay events totaling 30 days.
The revised schedule shows a finish on Day 280.
Delay attributable to owner = 320 - 280 = 40 days.

This outcome supports a potential Extension of Time (EOT) or claim for excusable delay.


4. When to Use This Method

  • After project completion

  • When comprehensive as-built data is available

  • In forensic dispute analysis or arbitration

  • To evaluate entitlement in complex delay scenarios


5. Pros and Cons

Aspect Pros Cons
Precision Based on actual execution Relies on accurate as-built data
Legal Weight Common in court/arbitration May be challenged as hypothetical
Transparency Clearly isolates impact of selected delays Doesn’t reflect mitigation or concurrent delays unless modeled separately

6. Contractual & Legal Context

Collapsed As-Built is widely accepted in formal disputes when supported by:

  • Auditable as-built schedules

  • Daily logs and correspondence

  • Industry protocols like AACEI RP 29R-03 or SCL Protocol

However, it is often scrutinized for:

  • Over-simplification of real project dynamics

  • Omission of float consumption or acceleration efforts

  • Potential for bias if key delays are selectively removed


7. Best Practices

  • Document all delay events and mitigation efforts contemporaneously.

  • Maintain detailed as-built schedules and daily progress records.

  • Use CPM tools with full logic tie visibility.

  • Remove delays incrementally to measure individual impacts.

  • Validate findings with contractual clauses (e.g., FIDIC 8.4, NEC time risk allowances).


8. Support Your Delay Claims with Expert Tools

Use the Collapsed As-Built method more effectively with these free, professional tools designed for retrospective delay analysis and claim preparation:



Conclusion

Collapsed As-Built analysis offers a powerful tool to test the what-if scenario of delay removal in completed projects. It is especially useful in arbitration or litigation settings where clarity on causation is critical. However, the accuracy and fairness of this method depend entirely on the integrity of the as-built data and transparency in fragnet removal. When used responsibly, it can be a compelling method to support or defend delay-related claims.

A
Anonymous
None
5 1
Apr 19, 2025
👁️ 47 👉 47

Frequently Asked Questions about Collapsed As Built


FAQ

Q: What is Collapsed As-Built (But-For) analysis?

A: It's a retrospective method that removes delay events from the as-built schedule to simulate what the project completion date would have been but for those delays. This helps determine how much time a specific event actually added to the project duration.

FAQ

Q: How is delay measured in this method?

A: Delay = Actual Completion Date − Collapsed Completion Date Example: If the actual finish was on Day 360 and the collapsed schedule (without owner delays) shows Day 310: Delay = 360 − 310 = 50 days, which may support an EOT or compensation claim.

FAQ

Q: When should Collapsed As-Built be used?

A: This method is best used after project completion, especially in disputes or forensic delay assessments where as-built data is fully available.

FAQ

Q: Is this method accepted in court or arbitration?

A: Yes — it’s commonly accepted in legal proceedings when supported by clear documentation. However, it may be scrutinized for its hypothetical nature, especially if key logic changes or concurrent delays are ignored.

FAQ

Q: What do FIDIC and NEC contracts say about this method?

A: While not naming it explicitly, FIDIC Clause 20 and Clause 8.4 support the idea of evaluating entitlement retrospectively when prospective methods are no longer feasible. NEC Compensation Events can also support its use, provided the delay cause-effect logic is well demonstrated.

FAQ

Q: How does Collapsed As-Built handle concurrent delays?

A: It doesn’t inherently resolve concurrency. Analysts must identify overlapping delays from different parties and apply concurrency principles to apportion responsibility. Otherwise, the method may overstate one party’s entitlement.

FAQ

Q: What is required to ensure this method holds up under legal scrutiny?

A: You’ll need a fully auditable as-built schedule, consistent daily records, and documentation that supports both the delay events and their removal. Referencing standards like the SCL Protocol or AACEI RP 29R-03 adds credibility to your approach.

Related Articles


Time Impact Analysis
⏳ 2 min read
Time Impact Analysis (tia) | Construction Delay Method
Master Time Impact Analysis (TIA), the leading prospective method for assessing construction delays. Understand its use, contract requirements, and best practices.
Impacted As Planned
⏳ 3 min read
Impacted As-planned Analysis | Construction Delay Method
Understand how Impacted As-Planned (IAP) analysis is used to model construction delays based on baseline schedules. Learn how to perform IAP, when to use it, and how it compares to TIA and other delay methods.
Windows Analysis
⏳ 3 min read
Windows Analysis | Construction Delay Evaluation Method
Learn how Windows Analysis blends prospective and retrospective methods to accurately evaluate construction delays. Explore window selection, critical path shifts, and legal considerations.
As Planned Vs As Built
⏳ 3 min read
As-planned Vs. As-built Analysis | Construction Delay Method
Learn how As-Planned vs. As-Built analysis is used to evaluate construction delays. Understand the steps, advantages, challenges, and when to apply it for EOT claims or dispute resolution.
Delay Analysis Construction
⏳ 4 min read
Delay Analysis In Construction | Methods, Tools & Legal Guide
Learn about the top delay analysis methods in construction, legal implications, and download our free Delay Analysis Method Selector Tool to choose the best method for your project based on complexity, data, and contract conditions.
Powerd by Quollnet.com