G
Guest

Open NCRs at Taking-Over / DLP: What Happens at Handover and How to Escalate

Can taking-over happen with open NCRs? Learn when handover is allowed, when it must be blocked, how to document outstanding NCRs, and when to escalate to contractual notices (e.g., Notice to Correct) through common contract authorities.

Ncr At Handover
Ncr At Handover
English version

Open NCRs at Taking-Over / DLP

Summary

Open Non confromance report - NRC at taking-over are common, but they must be controlled. Taking-over can usually proceed only if the remaining NCRs do not prevent safe use of the works and do not block statutory approvals or system performance. The right practice is to (1) classify NCRs as “blocker” vs “non-blocker,” (2) attach an Outstanding NCR Schedule to the taking-over documentation, (3) apply commercial controls where relevant (withhold/deduction tied to a clear reference), and (4) escalate persistent or ignored NCRs into contractual notices under the authority defined in the contract (Engineer/CA/PM/Employer’s Rep).


1) What “taking-over” means (and why open NCRs matter)

Taking-over (handover) is the contractual milestone where the Employer/Client accepts the Works (or a Section) as complete enough to take possession and use. It typically triggers major consequences such as:

  • start of the Defects Liability Period (DLP) / defects regime,

  • changes in risk/possession and operational responsibility,

  • payment milestones (e.g., release of part retention, final account steps).

Open NCRs matter because they can affect safety, use, approvals, final valuation, and the project’s ability to close out cleanly.


2) Key definitions (keep these separate)

  • NCR (Non-Conformance Report): a QA/QC record raised when work/material/testing/documentation does not meet contract requirements.

  • Snag / punch list: typically minor completion/finishing items. Example Snag list

  • Defect: a nonconforming condition managed under the defects regime (often after taking-over).

  • Outstanding works: incomplete items remaining at handover.

In practice, many teams treat open NCRs at handover as “outstanding defects/outstanding works”—but you should only do this when the NCR is not a handover blocker.


3) Who has authority at taking-over (common structures)

Different contract families use different titles, but the practical control usually sits with one of:

  • Engineer / Consultant (FIDIC-style supervision/administration),

  • Contract Administrator (CA) (JCT-style),

  • Project Manager / Employer’s Representative (NEC-style PM),

  • plus Authorities Having Jurisdiction (AHJ) for occupancy/permits (where relevant).

Your project procedures should clearly state:

  • who can certify taking-over/substantial completion,

  • who can issue instructions (to correct),

  • who can issue contractual notices (default/cure/termination steps).


4) The decision rule: can we take over with open NCRs?

A) “Blocker NCRs” (taking-over should not be issued)

Treat an NCR as a blocker when it prevents safe or compliant use, for example:

  • safety / structural integrity concerns (or unverified critical repairs),

  • life-safety systems not proven (fire alarm cause & effect, smoke control, etc.),

  • statutory approvals/permits/commissioning requirements not met,

  • performance-critical tests incomplete or failed where operation would be unsafe.

B) “Non-blocker NCRs” (taking-over may proceed with controls)

Often acceptable when:

  • the NCR is minor and correctable post-handover,

  • a clear corrective action plan exists,

  • verification method and evidence are defined,

  • commercial controls are documented where relevant.

Practical principle: Handover can proceed with outstanding items that do not prevent intended use—if they are transparently listed, time-bound, and verifiable.


5) How to document open NCRs at taking-over (best practice)

5.1 Attach an annex: Outstanding NCR Schedule

At taking-over, create an annex listing all open NCRs, including:

  • NCR ID

  • location / element

  • brief nonconformance description (facts)

  • severity (minor/major/critical)

  • required action (repair/replace/retest/submittal)

  • responsible party

  • target closure date

  • verification method and evidence required

  • optional: IPC hold/deduction reference

  • optional: contractual notice reference/date (if escalated)

This mirrors the common industry practice of issuing a taking-over/substantial completion document with a list of outstanding defects/works attached.

5.2 Keep the NCR Log “light,” but traceable

Your NCR log/register should stay QA-focused and only record high-level commercial/contract admin references (e.g., IPC ref, amount held, notice ref/date). The detailed QS valuation and contractual follow-up should be in separate registers.


6) Commercial impacts at handover (withholding, holds, deductions)

Open NCRs often become commercial at handover through:

  • withheld valuation (work not certified/measured until compliant),

  • IPC deductions/holds linked to specific NCRs,

  • concession/acceptance with a credit (where the contract allows acceptance of a deviation with a value adjustment).

Field example (UAE – supplier/subcontractor compliance)

On Julphar Residence / Al Reem Island (Employer: RAK Properties; A/E: Arkconsult; Contractor: S.E.G. Emirates), a recurring real-world pattern occurred: some work met technical specs and was operational, but sourcing allegedly did not match the approved supplier/subcontractor list. The Engineer/Employer position presented was effectively: remove/replace or accept a deduction, and deductions were applied without clear supporting build-up provided to the contractor.

How to present this professionally in your article (without escalating dispute language):

  • “Some projects treat approved supplier/subcontractor compliance as a contractual requirement independent of technical performance.”

  • “Resolution may be replacement, or a concession paired with a commercial adjustment—ideally supported by a transparent valuation reference.”



7) When open NCRs should escalate to contractual notices

An NCR becomes a contractual risk when:

  • the contractor does not respond within required time,

  • corrective action is not implemented,

  • deadlines are repeatedly missed,

  • the issue is systemic/repeated,

  • the NCR blocks taking-over or safe use.

7.1 “Notice to Correct” (FIDIC-style example)

In FIDIC 1999-style wording, a Notice to Correct is used when the contractor fails to carry out an obligation, requiring remedy within a specified reasonable time. This is a recognized escalation step before stronger remedies.

7.2 Defects correction periods and completion logic (NEC-style example)

NEC guidance highlights that defects notified before completion have correction periods linked to completion, and that completion can be certified when defects do not prevent use (depending on the contract’s completion definition).

7.3 Substantial completion with outstanding items (AIA-style example)

AIA A201-style provisions commonly tie substantial completion to the Owner’s ability to occupy/use the work, and require correction of items that prevent such use before the certificate is issued.


8) Practical “do this at handover” checklist

  • Separate NCRs into blocker vs non-blocker.

  • If blocker: delay taking-over or do sectional/partial taking-over.

  • If non-blocker: issue taking-over with an Outstanding NCR Schedule annex.

  • Ensure each open NCR has: target date + verification method + evidence.

  • Track commercial impacts by reference (IPC ref/amount), not by re-doing QS valuation in QA logs.

  • If contractor ignores NCRs: escalate to the contract admin route (notice reference + date + cure timeline in the contract notices log).


References and Downlaods

GIZ – Taking-Over Certificate template (includes “List of defects/outstanding works” enclosure)

AIA – A201®–2017 General Conditions (Substantial Completion logic and correction of items preventing use)

FIDIC – “Restraints on the Execution of Works” (quotes FIDIC 1999 Sub-Clause 15.1 Notice to Correct)

Fenwick Elliott – Termination by the Employer under FIDIC (discussion of Sub-Clause 15.1 Notice to Correct and “reasonable time”):

International Construction Knowledge Hub – FIDIC 1999 Commentary on Clause 15 (Notice to Correct overview)
NEC – Defining and managing defects in ECC (defect correction period timing)
Sharpe Pritchard – Defects under NEC4 (completion/defects summary incl. defect correction period)


L
Lena Miller
Feb 12, 2026
0
0
29
13

Ncr At Handover

Frequently Asked Questions


FAQ

Q: Can taking-over happen with open NCRs?

A: Yes, if the open NCRs do not prevent safe and compliant use of the works, and they are formally listed in an annex with clear corrective actions, dates, and verification evidence requirements.

FAQ

Q: When must taking-over be refused because of NCRs?

A: When NCRs affect safety, statutory approvals, life-safety systems, or any performance requirement that prevents the Employer from using the works as intended.

FAQ

Q: Do open NCRs become defects under the DLP?

A: Often they are managed like outstanding defects after handover, but you should still document them explicitly at taking-over (with actions, dates, and verification) to avoid ambiguity.

FAQ

Q: Can the Employer apply deductions for nonconformance that still works and meets specs?

A: Some projects do, especially where the contract includes compliance requirements beyond performance (e.g., approved supplier/subcontractor lists). Best practice is to tie any deduction to a clear contractual/commercial reference and a documented valuation basis.

FAQ

Q: When should we escalate an NCR into a contractual notice?

A: When the contractor fails to act within required timeframes, the issue is repeated/systemic, or the NCR blocks taking-over/use. Under some contract families, “Notice to Correct” is a formal escalation step.

Related Checklists


Protect Open Pile Heads Checklist: Clean, Dry, Cap
✅ 25 items
Protect open pile heads is a critical control that keeps exposed pile tops clean, dry, and ready for capping. This checklist focuses on short-term pile head protection—often called pile head protection, temporary pile head cover, and pile cap preparation—between driving/trimming and permanent capping. You will cap, cover, and maintain dryness, while explicitly excluding long-term storage scenarios that demand separate, engineered solutions. By preventing rain ingress, soil splash, laitance loss, corrosion initiation, and oil or slurry contamination, you reduce remedial chipping, cutbacks, and schedule risk. The outcome is consistent, capping-ready pile heads with verifiable evidence of condition and protection. Use the structured steps to select materials, install caps and covers, manage cleanliness and dryness, and document compliance per approved project specifications and authority requirements. Start the interactive mode to tick tasks, add photos and comments, and export your records to PDF/Excel with a secure QR link for verification.
Compile pile dossier for handover: QA docs checklist
✅ 24 items
Compile pile dossier for handover is your structured process for organizing and validating all pile-related documentation prior to client acceptance. This piling documentation checklist focuses on the pile QA dossier, ensuring verifiable records for installation, testing, calibrations, and as-built deliverables while explicitly excluding general foundation records such as pile caps or ground beams. By curating only pile-specific evidence—installation logs, static and dynamic load test reports, integrity test summaries, instrument calibration certificates, and NCR closures—you reduce disputes, avoid rework, and accelerate taking-over. The outcome is a clean, traceable package that demonstrates compliance per approved project specifications and authority requirements, with consistent file naming, signatures, and revision control. Practical acceptance cues, SI-based tolerances, and geo-referenced evidence help teams close gaps quickly and defend quality under audit. Use this interactive checklist to assign actions, capture photo and file attachments, add comments, and track digital sign-offs. Start ticking items, comment where needed, and export the dossier as PDF/Excel with an embedded QR code.
Final Cleaning and Debris Removal Inspection Checklist
✅ 11 items
Final cleaning and debris removal are critical steps at the end of a construction project. This phase ensures the site is safe, aesthetically pleasing, and ready for use. Our checklist covers the key tasks and inspections needed to verify that all construction debris is removed, surfaces are cleaned, and any remaining issues are addressed. Completing these tasks not only enhances the appearance and safety of a site but also prevents future maintenance problems. Users can interact with this checklist online, mark tasks as complete, add comments, and export the finished report with a QR code for authenticity.
Remediate Pile Defects Checklist: Grout or Core Repair
✅ 26 items
Remediate pile defects with a disciplined, field-proven process focused on pressure grouting or core repair, verification, and closing nonconformance reports. This checklist guides supervisors, QC engineers, and contractors through practical pile repair steps without adding new tests, relying on the approved investigation and method statement. It helps decide between pressure grouting for internal voids or core repair for localized damage, manages materials and equipment, and controls grouting pressures, volumes, and curing. You will capture photo evidence, pressure/volume logs, batch certificates, and as-built sketches to demonstrate that defective piles are restored to intent per approved project specifications and authority requirements. The scope excludes new integrity or load testing; verification depends on process records, dimensional checks, and joint inspections. Outcomes include safe, durable repairs, traceable documentation, and timely NCR closure. Use this interactive checklist to tick off actions, add field comments, and export a QR-secured PDF/Excel package for review and archiving.
Control bentonite slurry: QA tests and actions checklist
✅ 21 items
Control bentonite slurry is critical to keeping excavations stable and ensuring clean, bondable concrete interfaces. This checklist focuses on bentonite slurry testing and slurry quality control using proven field methods: mud balance density, Marsh funnel viscosity, sand content kit, pH measurement, and filtrate loss on a filter press. It applies to bored piles, diaphragm walls, and similar foundations where slurry supports open excavation. By holding density, viscosity, solids, alkalinity, and filtrate within target ranges, you reduce risks of sidewall collapse, debris inclusions, excessive bleed, and weak zones in the completed element. The scope excludes polymers; only sodium bentonite hydration and non-polymer treatments (e.g., soda ash for pH adjustment) are considered. Outcomes include predictable excavation performance, lower cleaning time, and consistent concrete quality. Use this interactive list to track readings, flag nonconformities, record corrective actions, and attach evidence. Start in interactive mode, tick items, add comments, and export PDF/Excel with a QR-secured audit trail.

Related Articles


Site Handover Accessible Site Letter Checklist
⏳ 5 min read
Construction Site Handover: Legal Meaning, “accessible Site” Clause, Checklist & Free Letter Template
A practical guide to construction site handover: legal meaning, “Accessible Site” clause, risks of informal possession, a step-by-step checklist, and a free handover letter template.
Ncr Meaning Construction
⏳ 3 min read
Ncr Meaning In Construction (qa/qc Non-conformance Report Guide)
NCR meaning in construction: an NCR (Non-Conformance Report) is a QA/QC record issued when work or materials don’t meet project requirements. Learn when to issue an NCR, who issues it, and how it’s closed.
Ncr Log Template E46
⏳ 2 min read
Ncr Log Template (register & Ncr Tracker) – Excel/pdf Download
Download an NCR log template (NCR register) to track non-conformance reports by ID, date, status, location, references, actions, and closure. Includes an empty template and a filled example in Excel and PDF.
Defect Liability Period Dlp
⏳ 2 min read
What Is Construction Defect Liability Period - Dlp
This article explores the defects liability period in FIDIC contracts, comparing it to statutory periods in civil law countries. It discusses the contractor's obligations, retention money, and the potential for latent defects.
Ncr Form Template
⏳ 4 min read
Ncr Form Template (excel/pdf) – Non-conformance Report Format
Download a practical NCR form template used on construction projects. Includes key fields for QA/QC non-conformance description, specification references, corrective action, verification, and closure.