User avatar G
Guest

Site Instructions Construction Legal And Forms

Learn what site instructions (Engineer’s, Architect’s, PM’s Instructions, ASI, Work/Field Orders) mean legally in FIDIC, JCT, NEC & AIA, with free forms.

Site Instructions Construction Legal And Forms
Site Instructions Construction Legal And Forms

Site Instructions in Construction: Legal Meaning, Risks, and Templates


What is a Site Instruction?

A site instruction — also known as an Engineer’s Instruction (FIDIC), Architect’s Instruction (JCT), Project Manager’s Instruction (NEC), Architect’s Supplemental Instruction (ASI) (AIA), or Work Order/Field Order (Government works) — is a formal written directive issued during the execution of a construction project by the Engineer, Architect, or Project Manager to the contractor.

It directs how certain aspects of the work should be carried out and is contractually binding, meaning the contractor must comply — but it can also trigger entitlement to additional time or cost under the contract.

Many engineers and architects focus on the technical side and underestimate the legal impact of their communications. They sometimes believe that unless they issue the official instruction form, the message is informal. In reality, any written directive that tells the contractor what to do may be legally treated as an instruction, even if it appears in:

💡 Legal Tip: If you write it, it might be an instruction. Treat every technical directive as potentially binding.


Legal Definitions by Contract Type

FIDIC

Under the FIDIC Red Book, Clause 3.3 (Instructions of the Engineer) empowers the Engineer to issue instructions necessary for execution.
If the instruction constitutes a variation, it must be processed under Clause 13 (Variations and Adjustments).
The contractor must comply immediately but may submit a notice of claim under Clause 20 if the instruction impacts time or cost.

💡 Legal Tip: In FIDIC, compliance is mandatory — claims are handled afterwards.


JCT

In JCT contracts, the Architect’s/Contract Administrator’s Instruction (AI/CAI) can change the work, materials, or sequence. Variations resulting from instructions entitle the contractor to adjustments in time and/or money.


NEC

In NEC contracts, the Project Manager’s Instruction (PMI) changes the Works Information and is treated as a Compensation Event. This requires prompt assessment and agreement on price and program changes.


AIA

The American Institute of Architects (AIA) differentiates between:

  • Architect’s Supplemental Instruction (ASI) — for minor changes with no impact on cost or time.

  • Construction Change Directive (CCD) — for changes that affect cost or time, even if the adjustment is not yet agreed.

💡 Legal Tip: Under AIA, ASIs are inherently “conditional” — any cost/time impact should be processed as a CCD or Change Order.


Government Works Contracts

Public works contracts often authorize Work Orders or Field Orders from the Engineer or Contracting Officer. If these change the scope, they must be processed as a formal contract modification (US GAO).


When is Something Legally Considered an Instruction?

Even without the official form, a directive is likely an instruction if it tells the contractor what to do. Examples:

  • Shop drawing comments — “Increase wall thickness to 250 mm.”

  • Submittal comments — “Use approved brand X cement.”

  • MoM action items — “Contractor to install safety net by Friday.”

  • Emails — “Proceed with excavation in Zone B.”

  • Inspection reports/NCRs — “Remove and replace defective slab.”

Contractors often log these to support variation claims.


Common Triggers for Site Instructions

Site instructions may arise from:

  • Contractor’s site clarification or RFI.

  • Non-conformance reports requiring remedial action.

  • Safety concerns needing immediate measures.

  • Design coordination issues between trades.

  • Unforeseen site conditions (e.g., buried utilities).

  • Owner convenience — changes in design/scope for preference rather than necessity.

  • Nominated subcontractors — instructing the contractor to appoint a specified subcontractor.

  • Alternative proposals from the contractor.

💡 Legal Tip: Even “owner convenience” changes are instructions — and may trigger variation entitlements.


Conditional Instructions

A conditional instruction might say:

“Proceed only if this causes no additional cost or delay — otherwise disregard.”

While this appears in practice, especially under AIA ASIs, it’s problematic in other contracts.

Risks

  • Ambiguity over who decides if there’s impact.

  • Possible delays if the contractor hesitates.

  • Under some contracts (like FIDIC), it contradicts the “must comply” principle.

FIDIC Reality

Under FIDIC Clause 3.3, the contractor must comply with instructions immediately, regardless of impact.
If they believe it affects time or cost, they submit notice under Clause 20 and claim afterwards.
A “conditional” wording doesn’t remove the contractor’s right to claim — it can just cause confusion.

Better approach:

  • Use the variation proposal process (Clause 13.3) to assess impact first.

  • Or issue the instruction and handle claims through the contract’s claims procedure.


The Contractor’s Perspective – Why Informal Instructions Are Gold

From the contractor’s viewpoint, every instruction is potential claim material.
Engineers and architects sometimes overlook the contractual force of informal directions — but a redline on a drawing or a note in MoM can support a claim for extra time or additional payment.


Best Practices for Issuing and Tracking Site Instructions

  1. Reference the contract clause for every instruction.

  2. Number and log all instructions — even if issued via MoM, drawing comment, or email.

  3. Confirm verbal directions in writing within 24 hours.

  4. Link instructions to variations/change orders where relevant.

  5. Maintain a unified instruction register covering all mediums.

💡 Legal Tip: A complete instruction log protects both the Employer and Contractor in disputes.


Free Site Instruction Form Templates

Download ready-to-use forms:

Each includes:

  • Contract clause reference

  • Reason for instruction

  • Cost/time impact

  • Signature & acknowledgment fields


References & Further Reading

Elie Saad's photo
Elie Saad
Aug 10, 2025
0
0
126
37

Frequently Asked Questions about Site Instructions Construction Legal And Forms


FAQ

Q: What is a site instruction vs change order?

A: A site instruction (also known as Engineer’s Instruction, Architect’s Instruction, PMI, ASI, or Work/Field Order) is a binding directive to carry out work but doesn’t automatically change contract time or cost—whereas a change order explicitly amends the contract sum or schedule, as explained in our Managing Variation Orders guide.

FAQ

Q: Is a comment on shop drawing a site instruction?

A: Yes—comments like “increase wall thickness to 250 mm” can legally be considered a site instruction, even if not issued on a formal form. See our article on informal site instructions for examples of shop drawings, submittal comments, and meeting minutes being used as contract directives.

FAQ

Q: What is a conditional site instruction?

A: A conditional instruction states work must proceed “only if no delay or cost occurs.” Under FIDIC contracts, this doesn’t override contractor rights—compliance is mandatory, with claims handled afterwards via the notice procedures in Clause 20.

FAQ

Q: How do I track site instruction templates and forms?

A: Use a site instruction register that logs all directives—from official forms to meeting minutes, emails, submittal comments, and ASIs/CCDs in AIA contracts—so nothing slips through and you maintain legal visibility. Download free site instruction templates for FIDIC and AIA contracts.

FAQ

Q: When is an ASI vs CCD used in AIA contracts?

A: An Architect’s Supplemental Instruction (ASI) is for minor changes without impact on cost/time. A Construction Change Directive (CCD) is used when changes affect contract sum or timeline, pending agreement on adjustments. More details are available from the American Institute of Architects official resources.

Related Checklists


Site Mobilization and Safety Setup Inspection Checklist
✅ 13 items
Site mobilization and safety setup are critical phases in construction projects, ensuring that the site is ready for work and that all safety measures are in place to protect workers and visitors. This process involves setting up temporary facilities, securing the site, and ensuring compliance with safety regulations. Proper inspection of these elements helps avoid potential hazards and project delays. Users can interact with this checklist by ticking off items, leaving comments, and exporting the completed report as a PDF or Excel file, secured with a unique QR code for authenticity.
Site Survey and Layout Benchmark Inspection Checklist
✅ 15 items
The site survey and layout benchmark inspection is a crucial preparatory phase in construction projects. It involves verifying the accuracy of the site's initial survey and the placement of layout benchmarks before any physical work begins. This step ensures that the project aligns with design specifications and prevents costly errors and delays. This checklist provides a comprehensive guide to inspecting various aspects of site surveys and benchmarks, helping professionals ensure quality and compliance. Users can interact with this checklist online, ticking off items, adding comments, and exporting the report as a PDF or Excel file, complete with QR code authentication for traceability.
Site Fencing, Hoardings and Signage Inspection Checklist
✅ 15 items
Inspecting site fencing, hoardings, and signage is crucial for ensuring safety, compliance, and effective project management on construction sites. This checklist covers the essential aspects of inspecting these installations, including material integrity, placement accuracy, and visibility. Proper inspection helps prevent unauthorized access, ensures public safety, and maintains a professional appearance. Our interactive checklist allows users to tick items, leave comments, and export completed reports as PDF or Excel, with a unique QR code for validation.
Carpentry and Joinery Installation Inspection Checklist
✅ 15 items
This Carpentry and Joinery Installation Inspection Checklist is designed to guide construction professionals in assessing the quality and accuracy of carpentry and joinery work on site. Whether you are a site manager, a quality assurance inspector, or a skilled tradesperson, this checklist provides a structured approach to ensuring installations meet industry standards and client specifications. It covers essential aspects such as materials, workmanship, safety, and compliance, helping you to identify and address potential issues before they escalate. Proper inspections not only enhance the durability and safety of the structures but also ensure customer satisfaction and project success.
Comprehensive Demobilization Inspection Checklist
✅ 15 items
Demobilization of site facilities and temporary services involves systematically dismantling and removing all non-permanent structures and services used during a construction project. This phase includes ensuring the safe and orderly removal of equipment, temporary buildings, utilities, and services without disrupting the site's integrity or the surrounding environment. It is crucial to perform detailed inspections to ensure all temporary installations are completely removed and the site is restored to its original or agreed state, avoiding potential safety hazards and environmental impacts. This interactive checklist allows users to methodically tick off tasks, add comments, and export the completed inspection report as a PDF or Excel file secured with a unique QR code.

Related Articles


Fidic Site Instruction Form Download Usage
⏳ 3 min read
Fidic Site Instruction Form – Free Download And Usage Tips
Download our free FIDIC Site Instruction form. Learn how to use it in any FIDIC edition, track variations, and protect against disputes with proper records.
Aia Architects Supplemental Instruction Form
⏳ 2 min read
Aia Architect’s Supplemental Instruction (asi) – Free Form And Usage Tips
Download our free AIA Architect’s Supplemental Instruction (ASI) form. Learn how to use it for minor changes with no cost/time impact, per AIA contracts.
Aia Construction Change Directive Form
⏳ 2 min read
Aia Construction Change Directive (ccd) – Free Form And Usage Tips
Download our free AIA Construction Change Directive (CCD) form. Learn how to use it for changes affecting cost/time when terms aren’t yet agreed.
Site Housekeeping Checklist Download
⏳ 4 min read
Free Site Housekeeping Checklist – Download In Excel, Word, & Pdf
Ensure a safe and organized construction site with our comprehensive Site Housekeeping Checklist. Download for free in Excel, Word, or PDF formats to streamline debris removal, maintain clear walkways, and uphold safety standards.
Managing Variation Orders Construction Projects
⏳ 6 min read
Comprehensive Guide To Managing Variation Orders In Construction Projects
Learn effective strategies for managing variation orders in construction projects. Access free, no-registration-required templates to streamline your change order processes and maintain project efficiency.