Demolition and Removal of Concrete Pavement, Kerbs and Footpaths inspection and test plan example.

Inspection and Test Plan for Demolition and Removal of Concrete Pavement, Kerbs and Footpaths

AI-assisted inspection and test plan connected to a method statement, with PDF and Excel export.

Published 27 Oct 2026 Rev. 00 3 views
About this ITP: This ITP defines hold/witness points and acceptance criteria for demolition, waste control, monitoring, and subgrade testing before subsequent works.

More than a static template

Unlike a downloadable Word or PDF template, this ITP is an AI-assisted editable starting point directly connected to its method statement. Every inspection activity, hold point, and acceptance criterion is structured and ready to adapt to your project.

  • AI-assisted customization — Tailor inspection activities and acceptance criteria to your specific project scope.
  • Linked method statement — This ITP is connected to the corresponding method statement describing the work sequence.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review and verify all content against your project specifications and standards before use.

What you can customize

When you save this ITP to your account, every inspection row becomes editable. You can add, remove, or modify:

  • Inspection activity — Description of what is being inspected.
  • Inspection type — Hold point (H), Witness point (W), Review (R), or Monitor (M).
  • Responsibility — Contractor, subcontractor, engineer, or client.
  • Frequency — How often the inspection occurs.
  • Acceptance criteria — Referenced standard or specification requirement.
  • Records — Forms, test reports, or checklists required as evidence.

Why this ITP is used

To assure demolition and subgrade conditions meet safety, environmental, and quality requirements before handover to subsequent construction.

Who uses this inspection and test plan

Contractor supervisors, Site Engineers, HSE, Independent Laboratory, and the Client/Engineer’s Representative.

When this ITP is prepared and submitted

From mobilization and TMP setup through demolition, waste load-out, and final subgrade testing and surveys.

Who receives or approves this ITP

Client/Engineer for approval prior to works.

Inspection scope

TMP compliance, utility clearance, plant checks, saw-cut accuracy, dust/noise/vibration control, demolition execution, waste management, subgrade proof-rolling and testing, and as-built surveys.

Typical hold, witness, and review points

Permit-to-Dig (Hold), operations near utilities (Hold), proof-roll (Witness), in-situ testing (Witness), as-built formation survey (Hold).

Typical inspection records

TMP checklists, permits, utility logs, plant inspections, monitoring data, test reports, survey files, waste tickets, daily diaries, NCRs and closeouts.

Important approval note

This ITP is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all inspection activities, hold points, and acceptance criteria must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

Always verify acceptance criteria against your applicable drawings, specifications, and regulatory requirements. Hold points must be confirmed with the relevant authority before work proceeds past that point.

Inspection and test plan

Activity Inspection / Test Acceptance Criteria Responsibility Record
TMP installation and opening to traffic Layout inspection vs approved TMP All devices installed per approved TMP; sightlines and access maintained; edge protection in place. Traffic Manager / Engineer (Witness) TMP inspection checklist, photos
Utility clearance and Permit-to-Dig Verification of utility mark-out and trial hole records Permit-to-Dig issued; utilities positively identified/marked; isolation/consents complete where required. Utility Coordinator / Engineer (Hold) Permit-to-Dig, trial hole logs, utility drawings
Pre-start plant and attachment inspection Daily plant checklist; coupler safety; breaker tool condition No leaks/defects; quick-coupler lock functional; guards fitted; certificates in date. Demolition Supervisor Daily plant checklists
Set-out and saw-cut verification Measurement vs design/mark-up Saw-cut lines within ±25 mm of design; full-depth isolation; slurry contained. Surveyor / Engineer (Witness) Set-out records, photos
Dust suppression in operation Visual check and flow/pressure check; dust monitoring if applicable No visible dust beyond boundary; exposure below OEL; runoff prevented. Supervisor / HSE (Witness) Dust log, monitoring results
Mechanical breaking operations Sequence/exclusion zone checks Exclusion enforced; no damage to adjacent assets; fragment size manageable; breaker used vertically. Demolition Supervisor / Engineer (Surveillance) Daily log, photos
Waste segregation and load-out Visual segregation; load security inspection Concrete separated from steel; covered loads; WTN/weighbridge tickets completed; licensed carrier. Supervisor / HSE (Surveillance) Waste records, WTN, tickets
Proof-roll of subgrade Observation of rutting/pumping No excessive deformation; soft spots identified and cordoned for treatment. Engineer (Witness) Proof-roll log, photos
In-situ testing (DCP; density/moisture; plate load if specified) ASTM/BS methods as applicable Meets specified CBR/strength and density/moisture criteria. [Verify values per spec] Independent Lab / Engineer (Witness) Lab test reports, location plan
As-built survey of formation GNSS/Total Station survey Formation levels within ±10 mm; line/grade/crossfall per design. [Verify] Surveyor / Engineer (Hold) As-built CAD/CSV, report
Final housekeeping and TMP handback/adjustment Walkthrough No debris; signage matches final condition; drains protected/cleared; safe for handover or next phase. Supervisor / Traffic Manager Final checklist, photos

This table is a read-only public reference. Download the PDF or Excel version, or customize this ITP to edit it for your project.

Frequently asked questions

Proof-rolling of 100% of exposed subgrade, DCP at agreed frequency (e.g., 1/250 m²), and density/moisture tests (e.g., 1/500 m²) unless superseded by project specifications.

The Engineer’s attendance is required at defined hold/witness points; works must not proceed past a hold point without written release.

Related method statement

This Inspection and Test Plan is associated with the Demolition and Removal of Concrete Pavement, Kerbs and Footpaths method statement, which describes the step-by-step construction sequence, resources, materials, equipment, safety controls, and environmental controls for this activity.

View the Demolition and Removal of Concrete Pavement, Kerbs and Footpaths method statement →