Method Statement: Lead Dust Cleanup, Decontamination, HEPA Vacuuming, Wet Wiping, Encapsulation, Waste Disposal, and Post-Cleanup Lead Wipe Clearance inspection and test plan example.

Inspection and Test Plan for Method Statement: Lead Dust Cleanup, Decontamination, HEPA Vacuuming, Wet Wiping, Encapsulation, Waste Disposal, and Post-Cleanup Lead Wipe Clearance

AI-assisted inspection and test plan connected to a method statement, with PDF and Excel export.

Published 12 Nov 2026 Rev. 00 1 views
About this ITP: This ITP defines inspections and tests for lead dust cleanup, from containment and negative pressure to clearance wipe results and waste compliance.

More than a static template

Unlike a downloadable Word or PDF template, this ITP is an AI-assisted editable starting point directly connected to its method statement. Every inspection activity, hold point, and acceptance criterion is structured and ready to adapt to your project.

  • AI-assisted customization — Tailor inspection activities and acceptance criteria to your specific project scope.
  • Linked method statement — This ITP is connected to the corresponding method statement describing the work sequence.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review and verify all content against your project specifications and standards before use.

What you can customize

When you save this ITP to your account, every inspection row becomes editable. You can add, remove, or modify:

  • Inspection activity — Description of what is being inspected.
  • Inspection type — Hold point (H), Witness point (W), Review (R), or Monitor (M).
  • Responsibility — Contractor, subcontractor, engineer, or client.
  • Frequency — How often the inspection occurs.
  • Acceptance criteria — Referenced standard or specification requirement.
  • Records — Forms, test reports, or checklists required as evidence.

Why this ITP is used

To assure the cleanup and encapsulation works meet regulatory and project acceptance criteria and to provide traceable records for release.

Who uses this inspection and test plan

Contractor QA/QC and Supervisors, HSE, Independent Assessor, and the Client/Engineer’s Representative.

When this ITP is prepared and submitted

During execution from setup through final clearance and demobilization, including any re-clean/re-test cycles.

Who receives or approves this ITP

Client/Engineer Representative and, where required, regulatory authorities.

Inspection scope

Containment integrity, negative pressure maintenance, HEPA equipment readiness, cleaning passes, encapsulant DFT, waste controls, and clearance sampling outcomes.

Typical hold, witness, and review points

Containment sign-off; negative pressure establishment; encapsulant first-coat QC; independent clearance sampling; final walkthrough.

Typical inspection records

Containment checklist, pressure logs, cleaning logs, WFT/DFT readings, calibration certificates, COC forms, lab reports, waste manifests, photo records.

Important approval note

This ITP is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all inspection activities, hold points, and acceptance criteria must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

Always verify acceptance criteria against your applicable drawings, specifications, and regulatory requirements. Hold points must be confirmed with the relevant authority before work proceeds past that point.

Inspection and test plan

Activity Inspection / Test Acceptance Criteria Responsibility Record
Containment installation Visual inspection; smoke test if specified Continuous seals; protected penetrations; functional decon entry Lead Abatement Supervisor / QA Containment checklist, photos
Negative pressure establishment Manometer reading and data logging ≥ 0.02 in. w.g. (5 Pa) negative pressure; target ≥ 4–6 ACH [Verify] Supervisor / QA Pressure logs, calibration certs
Equipment readiness (HEPA vacs/NAMs) Pre-use inspection; certificate check HEPA/PAO/DOP cert within 12 months; intact seals/hoses; pre-filters installed QA / HSE Pre-use checklists, certs
First HEPA vacuuming In-process visual checks No visible settled dust; top-down complete Supervisor / QA Cleaning checklist
Wet wiping/mopping Visual/ATP if specified [Verify] Surfaces clean; solutions changed at prescribed frequency Supervisor / QA Cleaning logs
Second HEPA vacuuming Visual No visible dust or debris Supervisor / QA Checklist
Encapsulant application (if specified) WFT/DFT measurements; adhesion checks if specified DFT within manufacturer spec; uniform coverage; no holidays QA / Applicator WFT/DFT logs, photos
Interim visual inspection Visual with bright light No visible dust/debris QA / Client Rep (witness) Inspection report
Clearance wipe sampling ASTM E1728 wipe sampling; NLLAP lab analysis All results ≤ applicable clearance standards [Verify] Independent Assessor COC, lab reports, clearance certificate
Waste classification and packaging Label/closure checks; TCLP as required Correct labels; intact containers; compliant storage Environmental Manager Waste profiles, manifests
Demobilization & final area release Final walkthrough Clean area; no damage; documentation complete Supervisor / Client Rep Handover certificate

This table is a read-only public reference. Download the PDF or Excel version, or customize this ITP to edit it for your project.

Frequently asked questions

Only if containment integrity is verified and areas re-cleaned as needed. Document cause, corrective actions, and obtain approval from the Client/Engineer and Assessor.

Typically at least one floor and one interior sill per room, and one trough if present; adjust per HUD/EPA/contract requirements and sampling plan.

Related method statement

This Inspection and Test Plan is associated with the Method Statement: Lead Dust Cleanup, Decontamination, HEPA Vacuuming, Wet Wiping, Encapsulation, Waste Disposal, and Post-Cleanup Lead Wipe Clearance method statement, which describes the step-by-step construction sequence, resources, materials, equipment, safety controls, and environmental controls for this activity.

View the Method Statement: Lead Dust Cleanup, Decontamination, HEPA Vacuuming, Wet Wiping, Encapsulation, Waste Disposal, and Post-Cleanup Lead Wipe Clearance method statement →