Method Statement: Installation of Carbon Steel Chilled Water Piping with Welded Joints – Method Statement
Method Statement: Installation of Carbon Steel Chilled Water Piping with Welded Joints method statement and inspection test plan example.

Method Statement: Installation of Carbon Steel Chilled Water Piping with Welded Joints – Method Statement

AI-assisted method statement with matching ITP, PDF download, and Excel export.

Published 14 Jul 2026 Rev. 00 380 views 231 downloads
About this method statement: This method statement details the installation of carbon steel chilled water piping using welded joints. It covers WPS/WPQ control, cutting, beveling, fit-up, multi-pass welding, NDT, and hydrotesting with clear acceptance criteria.

More than a static template

Unlike a downloadable Word or PDF template, this method statement is an AI-assisted editable starting point connected directly to a matching Inspection and Test Plan. Every section is structured, project-adaptable, and ready to export.

  • AI-assisted drafting — Customize every section with AI for your specific project scope.
  • Linked ITP — A matching inspection and test plan is generated alongside the method statement.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review, verify, and adjust all content against your project requirements before use.

Static template vs. Quollnet workflow

FeatureStatic templateQuollnet
Project-specific contentManual fill-in requiredAI-assisted customization
Linked ITPSeparate document, no linkMatching ITP included
Export formatsUsually PDF onlyPDF and Excel
Structured sectionsFree-form layout13 standardized sections
Saved to your accountLocal file onlyCloud-saved, reusable
Content accuracyYou verify everythingAI-assisted, you still verify
CostOften free but time-intensiveFree to customize and download

What you can customize

When you save this method statement to your account, every section becomes editable. The following 13 sections are included:

  • Scope — Defines the activity and its boundaries.
  • References — Standards, specifications, and drawings.
  • Responsibilities — Roles and accountabilities.
  • Resources — Labour, plant, and equipment summary.
  • Materials — Materials and compliance requirements.
  • Equipment — Tools and equipment details.
  • Prerequisites — Hold points and pre-conditions.
  • Method sequence — Step-by-step construction sequence.
  • Safety controls — HSE risk controls and PPE.
  • Environmental controls — Environmental mitigation measures.
  • QA/QC — Quality inspection and test requirements.
  • ITP — Inspection and Test Plan table (has its own page).
  • Attachments — Referenced drawings and documentation.

Why this method statement is used

This method statement is used to define and communicate the approved procedure for carrying out method statement: installation of carbon steel chilled water piping with welded joints on site. It ensures the work is planned in advance, the correct resources and controls are in place, and all personnel understand responsibilities, sequence, quality requirements, and safety controls before work begins. It aligns site execution with the documented scope and acceptance expectations.

Who uses this method statement

This method statement is used by contractors, site supervisors, project engineers, QA/QC engineers, HSE officers, consultants, and client representatives. It serves as a shared reference for planning, execution, supervision, inspection, and approval of the activity on site.

When it is prepared and submitted

The method statement is prepared before the work activity starts and submitted as part of the pre-construction documentation package for review and approval.

Who reviews or approves it

The method statement is usually submitted to the client representative, consultant, resident engineer, or project management consultant for review and approval before the work commences.

Important approval note

This method statement is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all content must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

For example: if your specification requires a departure from a referenced standard, that departure must be documented and approved separately — this method statement will not capture that automatically. Always verify against your applicable drawings, specifications, and regulatory requirements.

Method statement content

Scope

Overview

This method statement covers the complete installation of carbon steel chilled water (CHW) piping using welded butt joints and required fittings in plant rooms and services corridors. The scope includes material verification, pipe cutting, beveling, fit-up, welding (root and multi-pass), slag removal, weld inspection/NDT, hydrostatic testing, painting/touch-up at weld areas, and documentation.

Included Works

  • Verification of IFC isometrics, line list, P&IDs, WPS/PQR, and welder qualifications.
  • Handling, storage, and identification of pipes, fittings, and welding consumables.
  • Pipe cutting and end preparation to ASME B16.25 or ISO equivalent.
  • Alignment, fit-up, tack welding, and preheat/interpass control per approved WPS.
  • Root pass inspection, multi-pass welding, interpass cleaning, and cap finishing.
  • NDT coordination (VT 100%; RT/UT/MT extent per project specifications).
  • Hydrostatic pressure testing, drying/draining, and reinstatement.
  • Coating/painting touch-up at welded areas and final marking.
  • As-built documentation, weld maps, and test records.

Exclusions

  • Thermal insulation and jacketing.
  • Chemical cleaning/flushing and water treatment beyond hydrostatic test water quality control (unless noted in project specs).
  • Valve internals setting and actuator calibration.

Typical Limits

  • Piping size: DN25–DN600 [Verify per project].
  • Material: Carbon steel (e.g., ASTM A53/A106 Gr B or EN 10216/10255) [Verify per project].
  • Design code: ASME B31.9 (Building Services Piping) or ASME B31.3 (if specified) [Verify per project].

References

Document TypeReference / NumberRevisionNotes
Code ASME B31.9 / ASME B31.3 Latest
Code ASME Section IX or ISO 15614-1 (WPS), ISO 9606-1 (Welder) [Verify per project] Latest
Standard ASME B16.25 Latest
Standard ASTM A53/A106; ASME B16.9 (fittings); ASME B16.5 (flanges) or EN/BS equivalents [Verify per project] Latest
Standard ASME Section V or ISO 17635/17637(VT)/17638(MT)/17640(UT)/17636(RT) [Verify per project] Latest
Standard ASME B31.9/B31.3 acceptance criteria or ISO 5817 Level C [Verify per project] Latest
Standard ISO 8501-1 (surface prep), ISO 12944 (protective paint) [Verify per project] Latest
Code ASME B31.9 (test pressure typically 1.5 × design) [Verify per project] Latest

Responsibilities

RoleResponsibilityName / Party
PM Project Manager Contractor
CM Construction Manager Contractor
Engineer Site Engineer Contractor
Welding Engineer Welding Engineer Contractor
QA/QC QA/QC Contractor
HSE HSE Contractor
NDT NDT Subcontractor Approved Lab
Supervisor Piping Supervisor Contractor

Resources

Resource TypeDescriptionQuantityRemarks
Manpower ASME IX or ISO 9606-1 certified for relevant positions (1G–6G) 4–8 Maintain continuity logs
Manpower Experience with CS piping fit-up and alignment 4–8
Manpower Certified rigging and signaling 2–4
Manpower Level II minimum for MT/UT/RT As needed

Materials

MaterialSpecification / GradeQuantityRemarks
Carbon Steel Size: DN25–DN600; Sch 40/80 [Verify] As per BOQ ASTM A53/A106 Gr B or EN 10216/10255 [Verify]
CS ASME B16.9 As per BOQ
CS ASME B16.5, Class 150/300 [Verify] As per BOQ
E7018, E6010, ER70S-2/6 AWS A5.1/A5.18 As required Low hydrogen control required
Argon 99.99% purity [Verify] As required
Epoxy/alkyd system ISO 12944 compatible [Verify] As required
Compressed fiber/EPDM; ASTM A193/A194 bolts [Verify] As required

Equipment

EquipmentCapacity / TypeQuantityInspection Required
Welding Power Source Up to 300 A 4–8 Yes
Rod Oven 120–400°C 1 store + 2 portable Yes
Cold Cutter/Beveler DN25–DN600 As required Yes
Clamps & Gauges As required Yes
1–3 t chain blocks Up to 3 t As required Yes
Measuring tools Sets Yes
NDT instruments As required Yes
Hydro pump & gauges Up to required test P 1 set/test pack Yes

Prerequisites

  • Approved method statement, risk assessment, and ITP.
  • IFC isometrics, P&IDs, support drawings, and weld maps available on site.
  • Approved material submittals (pipes, fittings, consumables) and MTCs.
  • Approved WPS/PQR; welder qualifications (WPQ) valid for position/thickness/material group; continuity log updated.
  • Calibrations valid for welding machines, gauges, UT/MT/RT equipment, pressure gauges.
  • PTW issued for hot works, lifting, confined space (if any), and radiography [Verify per project HSE plan and local regulations].
  • Work area cleared, scaffold/MEWP inspected, lifting plan approved where applicable.
  • Temporary supports/hangers planned to avoid weld distortion and overloading.
  • NDT subcontractor availability and hold/witness points agreed with Consultant.
  • Hydrotest test packs prepared: line list, test boundaries, blinds, vents, test medium, acceptance criteria.
  • Fire watch and firefighting equipment available for all hot works.

Method Sequence

StepActivityDescriptionResponsibilityInspection / Hold Point
1 Material Receipt & Verification Receive and inspect pipes/fittings/consumables. Check MTCs, heat numbers, size/schedule, damages, coating condition. Segregate by line class. QA/QC, Storekeeper Visual; document check
2 WPS/WPQ Verification Confirm approved WPS/PQR covers material, thickness, position, process (GTAW/SMAW). Verify welder qualifications current and within scope. Welding Engineer, QA/QC Document check
3 Cutting & End Preparation Measure and mark as per spool/iso. Use cold cutting. Bevel ends to ASME B16.25: 37.5° ±2.5°; root face 1.6 mm ±0.8 mm; root gap at fit-up 3.0 mm ±1.0 mm [Verify per WPS]. Deburr and clean to bare metal 25 mm from edge. Pipe Fitter Dimensional check
4 Fit-Up & Alignment Set with internal/external clamps. Verify root gap and hi-lo using gauge. Use spacers/dogs if required. Tack weld using qualified process/filler; grind tacks if they remain in weld. Install temporary supports to maintain alignment. Pipe Fitter, Welder Visual/dimensional
5 Preheat & Interpass Control Preheat per WPS using temp sticks/IR thermometer. Typical preheat: 50–100°C depending on thickness/CE [Verify per WPS]. Maintain interpass ≤250°C [Verify per WPS]. Shield joint from drafts. Welder, Welding Eng. Measurement
6 Root Pass Welding Execute root using GTAW (ER70S-2/6) or SMAW (E6010 where permitted). Control heat input/travel as per WPS. Clean and grind root as needed to sound metal. Welder In-process
7 Root Pass VT (and MT if specified) After cleaning, perform VT of root (internal via borescope if accessible). MT may be required for accessible external surfaces per ITP. QA/QC, NDT VT/MT
8 Hot Pass, Fill & Cap Deposit hot pass and subsequent layers (SMAW E7018 or GTAW) with interpass cleaning. Use stringer or weave per WPS. Finish cap slightly convex 1–3 mm reinforcement. Welder In-process
9 Interpass Cleaning & Slag Removal Remove slag and spatter thoroughly between passes using chipping and wire brush. Clean with solvent only if approved and fully evaporated. Welder Visual
10 Final Visual & Dimensional Inspection VT after cap: check profile, reinforcement, undercut, arc strikes, dimensional compliance to isos/spools, support locations and clearances. QA/QC, Site Eng. VT/dimensional
11 NDT (RT/UT/MT as per ITP) Carry out NDT extent per project (e.g., 10% RT/UT of butt welds minimum, more for critical lines) [Verify]. Coordinate radiography safety zones or UT access. NDT Technician, QA/QC RT/UT/MT
12 Repair (if required) Mark/plan repair, remove defect by grinding/gouging, re-weld per WPS. Re-inspect same method and extent as original or as ITP requires. Welder, QA/QC VT + NDT
13 Hydrostatic Pressure Test Prepare test pack; install blinds; fill with clean water (with inhibitor if specified); vent air; pressurize to 1.5 × design pressure [Verify]; hold 30–60 min [Verify]; examine for leaks/pressure drop. QA/QC, Site Eng. Witness
14 Draining, Drying & Reinstatement Depressurize, drain to approved point, blow out with clean dry air where required, remove blinds, reinstall components, restore vents/drains. Site Eng., Supervisor Visual
15 Coating/Paint Touch-Up at Welds Prepare surface (St 2/3), apply primer and topcoat per TDS to specified DFT. Mark line number, flow, and identification. Painting Supervisor DFT checks
16 Documentation & Handover Compile weld map, material traceability, NDT, hydrotest, repairs, painting, and as-built marked isometrics; submit dossier. QA/QC Review

Safety Controls

For each significant hazard, the following items are defined: hazard, likely consequence, engineering/procedural control, required PPE, collective preventive measure, and inspection/permit/supervision requirement.

1) Hot works (welding, grinding)
- Consequence: Burns, fire, eye injury.
- Controls: Hot work PTW; remove combustibles 10 m; non-sparking mats; fire blankets; dedicated fire watch with extinguisher and charged hose.
- PPE: FR coveralls, welding helmet with correct shade, leather gloves/apron, safety boots, safety glasses, ear protection.
- Collective measures: Welding screens to protect others; spark containment.
- Inspection/Permit/Supervision: PTW; daily fire watch log; HSE inspection before start and after shift.

2) Fumes and gases (welding smoke, argon)
- Consequence: Respiratory irritation, asphyxiation in poorly ventilated/confined spaces.
- Controls: Local exhaust ventilation; avoid shielding gas accumulation; continuous gas monitoring in confined spaces.
- PPE: Respiratory protection P2/P3 if ventilation inadequate; standard PPE as above.
- Collective measures: Mechanical ventilation/air movers.
- Inspection/Permit/Supervision: Confined space permit; atmospheric testing records; HSE oversight.

3) Radiography (if RT used)
- Consequence: Radiation exposure.
- Controls: Prefer UT where feasible. If RT required, restrict area with barriers 25 m or as calculated; warning lights/signage; licensed radiography team.
- PPE: Dosimeters for RT crew; standard PPE for others outside exclusion zone.
- Collective measures: Controlled access and spotter.
- Inspection/Permit/Supervision: RT permit; survey meter readings; RPO supervision; records retained.

4) Lifting and handling of pipes/spools
- Consequence: Crush injuries, dropped loads.
- Controls: Approved lifting plan, certified gear, tag lines, exclusion zones.
- PPE: Helmet with chin strap, gloves, boots, hi-vis.
- Collective measures: Banksman control; barricades.
- Inspection/Permit/Supervision: Pre-lift checklist; gear certificates; competent rigger/banksman.

5) Grinding/cutting operations
- Consequence: Flying particles, noise, hand injuries.
- Controls: Guards in place; correct discs; two-handed operation; sparks directed away.
- PPE: Face shield over safety glasses, gloves, hearing protection.
- Collective measures: Grinding booths/screens.
- Inspection/Permit/Supervision: Tool pre-use checks; HSE spot checks.

6) Pressure testing
- Consequence: Component rupture, fluid injection injury.
- Controls: Test boundaries barricaded; pressurize gradually; stand clear; use calibrated gauges; relief valve fitted to pump.
- PPE: Face shield, gloves, boots.
- Collective measures: Exclusion zone; signage.
- Inspection/Permit/Supervision: Test permit; QA/QC witness; Supervisor present.

7) Electrical hazards (welding sets)
- Consequence: Shock, arc flash.
- Controls: PAT-tested equipment; dry leads; intact insulation; isolation when servicing; 30 mA RCD.
- PPE: Dry gloves, FR clothing, dielectric boots where needed.
- Collective measures: Cable management to avoid water/traffic.
- Inspection/Permit/Supervision: Electrical inspection log; competent electrician.

8) Working at height (pipe racks/MEWPs)
- Consequence: Falls.
- Controls: Scaffolds tagged “green”; MEWP harness/anchor; 3-point contact; tools tethered.
- PPE: Full body harness with lanyard; helmet with chin strap.
- Collective measures: Guardrails; toe boards.
- Inspection/Permit/Supervision: Scaffold inspection tags; MEWP inspection; PTW if required.

9) Heat stress and burns
- Consequence: Dehydration, heat-related illness.
- Controls: Work-rest cycles; hydration; shade; handle hot workpieces with tongs.
- PPE: Heat-resistant gloves, FR clothing.
- Collective measures: Cooling fans; shaded rest area.
- Inspection/Permit/Supervision: HSE monitoring; first aid availability.

10) Noise and illumination
- Consequence: Hearing loss; poor visibility leading to incidents.
- Controls: Hearing protection zones; task lighting ≥200 lux at weld area.
- PPE: Earplugs/earmuffs; safety glasses.
- Collective measures: Light towers; signage.
- Inspection/Permit/Supervision: Noise survey (if required); lighting checks.

Note: Where exact controls depend on local law or project HSE plan, verify per project HSE plan and local regulations.

Environmental Controls

  • Welding fumes and dust: Use LEV; select low-fume electrodes; avoid excessive grinding. Maintain air quality below occupational limits [Verify per local regs].
  • Electrode stubs and slag: Collect in designated metal bins; dispose as non-hazardous waste unless contaminated; record quantities.
  • Solvent use and paint touch-up: Use low-VOC where possible; prevent spills; secondary containment for cans; follow SDS; segregate hazardous waste.
  • Hydrotest water: Use clean water; add corrosion inhibitor only if specified; discharge to approved drainage after turbidity/pH check and filtration as needed [Verify per permit].
  • NDT chemicals (MT): Use aerosol catch mats; prevent overspray; collect wipes as hazardous waste.
  • Noise and light spill: Use acoustic screens and welding curtains; limit work hours per permit.
  • Energy and gas cylinders: Close valves when not in use; store upright, segregate full/empty; leak test with approved solution.
  • Housekeeping: Keep walkways clear; immediate cleanup of spatter and metal offcuts to prevent contamination of drains.
  • Spill response: Spill kits at workface; train crew; report and document incidents.
  • Environmental monitoring: Maintain waste transfer notes, water discharge logs, and monthly environmental checklist.

QA / QC

General

  • Applicable codes: ASME B31.9 (or B31.3 if specified), ASME Section IX/ISO 15614-1/ISO 9606-1 for welding qualifications, ASME Section V/ISO 17635 series for NDT [Verify per project].
  • Hold/witness points as per ITP; no work to proceed past hold points without approval signatures.

Welding Controls

  • WPS/PQR: Use only Client-approved WPSs; parameters recorded on weld logs (current, voltage, travel speed or heat input range) [Per WPS].
  • Preheat/interpass: Measure using temp sticks or IR thermometer; typical preheat 50–100°C; interpass ≤250°C unless WPS states otherwise [Verify].
  • Joint prep: Bevel angle 37.5° ±2.5°, root face ~1.6 mm ±0.8 mm, root gap 3.0 mm ±1.0 mm unless WPS differs.
  • Consumables: Low hydrogen control for E7018: baking as per manufacturer; holding oven 120–150°C; issue in heated quivers; record batch/heat and welder ID.
  • Welder continuity: Update monthly; suspension after lapse per ASME IX/Project requirement.
  • Arc strikes: Prohibited on base metal outside groove; if present, grind and MT check.

Inspection & NDT

  • VT: 100% of welds per ISO 17637 immediately after cleaning each critical stage (root and final).
  • NDT extent: Typical baseline 10% RT or UT of full penetration butt welds; 100% for critical joints/tie-ins as specified; MT on surface where required [Verify per ITP/spec].
  • Acceptance criteria: ASME B31.9/B31.3 or ISO 5817 Level C for imperfections [Verify per project].
  • Repairs: Same WPS; record defect type/location; NDT re-test same method and extent.

Pressure Testing

  • Test pressure: 1.5 × design pressure, hold 30–60 minutes [Verify per project]; two calibrated gauges in 1.5–4 × test pressure range; gauge agreement within 5%.
  • Acceptance: No leakage/pressure drop; joints dry and tight; document vent/drain points and reinstatement.

Records

  • Weld map and numbering; welder IDs; heat numbers per spool; material receiving inspection; fit-up and VT reports; NDT reports and films; repair logs; hydrotest pack (gauges certs, permits, sketches); coating/DFT logs; calibration certificates; as-built isometrics; NCRs and close-outs.

Attachments

  • Approved WPS/PQR and register.
  • Welder qualifications (WPQ) and continuity logs.
  • IFC isometrics, P&IDs, line list, and weld map.
  • Material approvals (MAS), MTCs, consumable COCs.
  • Calibration certificates (welding sets, gauges, NDT equipment, DFT meters).
  • ITP and signed ITRs at each stage.
  • NDT procedures and reports (VT/MT/UT/RT) including films and interpretations.
  • Hydrostatic test packs (sketches, gauge certs, permits, reports).
  • Coating system TDS/SDS and DFT reports.
  • NCRs, corrective actions, concessions (if any).
  • As-built drawings and final turnover dossier.

This content is a read-only public reference. Download or customize to get an editable version.

ITP preview

The first inspection activities from the linked ITP for Method Statement: Installation of Carbon Steel Chilled Water Piping with Welded Joints:

ActivityInspection / TestAcceptance CriteriaResponsibilityRecord
Material receipt and identificationVerify grade, size, MTCs, heat numbersCorrect material per approved submittals; traceable; free from damageQA/QC, ConsultantMaterial receiving report, MTCs
WPS/PQR/WPQ verificationDocument reviewApproved and valid for process, position, thickness, materialWelding Eng., QA/QC, ConsultantApproved WPS/PQR/WPQ copies
Joint preparation and fit-upBevel angle/land; root gap; hi-lo checkAs per WPS/ASME B16.25; hi-lo ≤10% WT (max 1.5 mm); root gap 3±1 mmQA/QC, ConsultantFit-up report with photos

Showing 3 of 10 inspection activities. View full ITP →

Related Inspection and Test Plan

An Inspection and Test Plan (ITP) is available for Method Statement: Installation of Carbon Steel Chilled Water Piping with Welded Joints. The ITP defines the inspection activities, acceptance criteria, hold and witness points, responsible parties, and records required to verify the work described in this method statement.

View the Method Statement: Installation of Carbon Steel Chilled Water Piping with Welded Joints ITP →

Frequently asked questions

Typically ASME B31.9 applies to building services piping. Some projects specify ASME B31.3. Verify against project specifications.

A common benchmark is 10% RT or UT for butt welds, with increased extent for critical joints or if defects are found. Verify per ITP and project specs.

Preheat is set by the approved WPS based on material thickness and carbon equivalent. Typical values are 50–100°C with interpass ≤250°C. Verify per WPS.

For SMAW fill/cap on carbon steel, E7018 low hydrogen electrodes are typically required with controlled storage and issuance to prevent hydrogen cracking.

A typical benchmark is 1.5 times the design pressure with a 30–60 minute hold. Exact value and duration must be verified per project and code.