Method Statement: Mobile Crane Positioning, Outrigger Mat Configuration, and Ground Bearing Verification inspection and test plan example.

Inspection and Test Plan for Method Statement: Mobile Crane Positioning, Outrigger Mat Configuration, and Ground Bearing Verification

AI-assisted inspection and test plan connected to a method statement, with PDF and Excel export.

Published 26 May 2026 Rev. 00 389 views 178 downloads
About this ITP: Defines inspections, tests, and records for mobile crane set-up: ground verification, mat sizing, levelling, function checks, preload, and test lift.

More than a static template

Unlike a downloadable Word or PDF template, this ITP is an AI-assisted editable starting point directly connected to its method statement. Every inspection activity, hold point, and acceptance criterion is structured and ready to adapt to your project.

  • AI-assisted customization — Tailor inspection activities and acceptance criteria to your specific project scope.
  • Linked method statement — This ITP is connected to the corresponding method statement describing the work sequence.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review and verify all content against your project specifications and standards before use.

What you can customize

When you save this ITP to your account, every inspection row becomes editable. You can add, remove, or modify:

  • Inspection activity — Description of what is being inspected.
  • Inspection type — Hold point (H), Witness point (W), Review (R), or Monitor (M).
  • Responsibility — Contractor, subcontractor, engineer, or client.
  • Frequency — How often the inspection occurs.
  • Acceptance criteria — Referenced standard or specification requirement.
  • Records — Forms, test reports, or checklists required as evidence.

Why this ITP is used

To control critical quality and safety points that prevent crane overturning and utility strikes through measurable inspections and tests.

Who uses this inspection and test plan

Appointed Person, Temporary Works Engineer, Geotechnical Engineer, Lifting Supervisor, Crane Operator, QA/QC, HSE.

When this ITP is prepared and submitted

Before crane arrival (planning), during set-up and levelling, prior to first lift (test), and during operations monitoring.

Who receives or approves this ITP

Client/Engineer/Principal Contractor [Verify]

Inspection scope

Design reviews, material inspections, platform testing, set-up inspection, levelling/function checks, preload/settlement monitoring, and test lift witness.

Typical hold, witness, and review points

Hold: Lift Plan/TWD approval; Set-up prior to preload; Test lift. Witness: Platform QA tests; Levelling/function checks.

Typical inspection records

Approved plans and calcs, permits, material certs, test reports, checklists, settlement logs, photos, close-out report.

Important approval note

This ITP is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all inspection activities, hold points, and acceptance criteria must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

Always verify acceptance criteria against your applicable drawings, specifications, and regulatory requirements. Hold points must be confirmed with the relevant authority before work proceeds past that point.

Inspection and test plan

Activity Inspection / Test Acceptance Criteria Responsibility Record
Lift Plan and calculations approval Design/Calc Review Approved Lift Plan; Mat/ground calc signed by AP/TWE AP; TWE Approved Plan; Calc Sheets
Utility detection and permit GPR/CAT survey Permit-to-Dig/Avoidance issued; services marked on ground Utility Coordinator; HSE Survey Report; Permit
Platform construction/verification Density/CBR/LWD 95% MDD; CBR/LWD per TWD; level and slope within limits [Verify] Geo Eng.; QA/QC QA Test Reports; Inspection Sheet
Mat material inspection Visual; cert check Correct grade/spec; fit for use; no damage beyond limits QA/QC Material Inspection Report; Certs
Mat installation and crane positioning Set-up inspection Mats positioned per plan; pad centring; no point packing; exclusion zones set Supervisor Set-up Checklist; Photos
Levelling and function tests Inclinometer; LMI/ATB tests Level within ±0.5°; LMI/ATB operational; wind alarm set Operator; Supervisor Function Test Sheet; Level Record
Staged preload/settlement check Settlement measure Immediate settlement ≤ 10 mm per leg; differential ≤ 10 mm; re-level if required [Verify] Supervisor; QA/QC Settlement Log
Initial test lift Partial load test Stable response; no progressive settlement; communications effective Supervisor; AP (Witness) Test Lift Record
Operations monitoring Routine checks Wind within limits; level maintained; exclusion zones enforced Operator; Supervisor Operator Log; Daily Checklist
Demobilisation and reinstatement Final inspection No residual hazards; ground reinstated; all records closed Supervisor; QA/QC Close-out Report; Photos

This table is a read-only public reference. Download the PDF or Excel version, or customize this ITP to edit it for your project.

Frequently asked questions

Compaction/density results, CBR/LWD data meeting TWD, level/slope survey records, and a signed platform inspection sheet.

The Appointed Person prepares or verifies the calculation, and the Temporary Works Engineer performs the check/approval as required by project procedures.

Before the first operational lift after set-up or relocation, and whenever significant configuration changes occur or after abnormal events such as high winds [Verify per plan].

Related method statement

This Inspection and Test Plan is associated with the Method Statement: Mobile Crane Positioning, Outrigger Mat Configuration, and Ground Bearing Verification method statement, which describes the step-by-step construction sequence, resources, materials, equipment, safety controls, and environmental controls for this activity.