Method Statement – Intumescent Paint Application to Structural Steelwork inspection and test plan example.

Inspection and Test Plan for Method Statement – Intumescent Paint Application to Structural Steelwork

AI-assisted inspection and test plan connected to a method statement, with PDF and Excel export.

Published 11 Jun 2026 Rev. 00 809 views 184 downloads 1 uses
About this ITP: Defines inspections for each stage of intumescent coating works, including Sa 2½ preparation, environmental controls, WFT/DFT checks, adhesion testing, and documentation.

More than a static template

Unlike a downloadable Word or PDF template, this ITP is an AI-assisted editable starting point directly connected to its method statement. Every inspection activity, hold point, and acceptance criterion is structured and ready to adapt to your project.

  • AI-assisted customization — Tailor inspection activities and acceptance criteria to your specific project scope.
  • Linked method statement — This ITP is connected to the corresponding method statement describing the work sequence.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review and verify all content against your project specifications and standards before use.

What you can customize

When you save this ITP to your account, every inspection row becomes editable. You can add, remove, or modify:

  • Inspection activity — Description of what is being inspected.
  • Inspection type — Hold point (H), Witness point (W), Review (R), or Monitor (M).
  • Responsibility — Contractor, subcontractor, engineer, or client.
  • Frequency — How often the inspection occurs.
  • Acceptance criteria — Referenced standard or specification requirement.
  • Records — Forms, test reports, or checklists required as evidence.

Why this ITP is used

To establish hold/witness points and objective acceptance criteria ensuring the coating achieves the required fire performance and durability.

Who uses this inspection and test plan

QA/QC inspectors, coating supervisors, third-party inspectors, and the Client/Engineer’s Representative.

When this ITP is prepared and submitted

Throughout the coating process from material receipt through final acceptance and handover.

Who receives or approves this ITP

Client/Engineer for approval prior to works.

Inspection scope

Material verification, substrate preparation, cleanliness/contamination tests, environmental monitoring, primer and intumescent application, thickness control, adhesion testing, topcoat application, and final documentation.

Typical hold, witness, and review points

Post-blast inspection (Hold), pre-intumescent application (Hold), total DFT mapping (Hold), adhesion testing (Witness), final acceptance (Hold).

Typical inspection records

CIRs, WFT/DFT logs, environmental logs, Bresle/dust/profile results, adhesion test reports, batch logs, calibration certificates, NCR/CARs, MDR.

Important approval note

This ITP is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all inspection activities, hold points, and acceptance criteria must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

Always verify acceptance criteria against your applicable drawings, specifications, and regulatory requirements. Hold points must be confirmed with the relevant authority before work proceeds past that point.

Inspection and test plan

Activity Inspection / Test Acceptance Criteria Responsibility Record
Material receipt and storage Verify PDS/SDS, batch numbers, shelf-life, storage temperatures Conforms to approved submittals; storage within PDS limits; no damaged containers QA/QC + Materials Controller Material Receipt & Storage Log
Surface degreasing (pre-blast) Visual and wipe test per SSPC-SP1 No oil/grease residues; clean, dry surface Coating Inspector Pre-blast Inspection Report
Abrasive blasting Visual vs ISO 8501-1; profile ISO 8503 Sa 2½; profile 40–75 µm Rz [Verify] Coating Inspector Post-blast Report; Profile Measurements
Dust testing ISO 8502-3 dust tape test Max Class 2 (quantity/size) [Verify] Coating Inspector Dust Test Record
Soluble salt testing ISO 8502-6/9 (Bresle), conductivity to mg/m² ≤20 mg/m² chloride (as NaCl) [Verify] Coating Inspector Bresle Test Record
Environmental conditions (pre-coating and during cure) Air/steel temp, RH, dew point Steel temp ≥3°C above dew point; RH ≤85%; within PDS limits Coating Inspector Environmental Log
Primer application WFT (ASTM D4414) and DFT (ISO 19840/ASTM D7091) Uniform primer DFT 50–75 µm [Verify]; visual free from defects Coating Inspector Primer WFT/DFT Log; CIR
Recoat window verification Time/ambient review; surface condition Within PDS recoat interval or surface properly prepared Painting Supervisor + QA/QC Recoat Verification Record
Stripe coats to details Visual coverage; WFT spot checks Continuous coverage on edges/welds/bolts; no misses Coating Inspector Stripe Coat Inspection Record
Intumescent basecoat application (each coat) WFT during spray; defects check Per-coat WFT within PDS limit; no runs/sags/cracks Painting Supervisor + Coating Inspector WFT Log; CIR
Curing between coats Time/ambient verification; surface condition Meets minimum recoat criteria per PDS; surface firm/non-tacky Coating Inspector Cure Verification Log
Total DFT mapping (final) DFT per ISO 19840/SSPC-PA 2 sampling plan Mean ≥ NDFT; no individual <80% NDFT unless permitted [Verify] Coating Inspector DFT Map & Acceptance Report
Adhesion testing (representative) ASTM D4541/ISO 4624 pull-off Average ≥1.5 MPa; no individual <1.0 MPa; acceptable failure mode [Verify] Coating Inspector / Third-Party (if specified) Adhesion Test Report
Topcoat/sealer application (if specified) WFT/DFT; compatibility check Within PDS DFT; applied within recoat window; uniform finish Coating Inspector Topcoat Inspection Record
Final acceptance and documentation Review of MDR, close-out of NCRs, housekeeping All records complete; coating free of defects; protection in place QA/QC Manager + Client Rep Final Acceptance Certificate; MDR

This table is a read-only public reference. Download the PDF or Excel version, or customize this ITP to edit it for your project.

Frequently asked questions

Follow ISO 19840 or SSPC-PA 2: define measurement areas per member or per 10 m², with multiple gauge readings per area and mapping of results.

Select representative, non-critical areas agreed with the Engineer to avoid structural or aesthetic impact; repair test spots after testing.

Related method statement

This Inspection and Test Plan is associated with the Method Statement – Intumescent Paint Application to Structural Steelwork method statement, which describes the step-by-step construction sequence, resources, materials, equipment, safety controls, and environmental controls for this activity.

View the Method Statement – Intumescent Paint Application to Structural Steelwork method statement →