Inspection and Test Plan for Method Statement: Fireproofing Inspection and ITP for Composite Steel Deck Floor Systems (Soffit of Trapezoidal Galvanized Deck)
AI-assisted inspection and test plan connected to a method statement, with PDF and Excel export.
More than a static template
Unlike a downloadable Word or PDF template, this ITP is an AI-assisted editable starting point directly connected to its method statement. Every inspection activity, hold point, and acceptance criterion is structured and ready to adapt to your project.
- AI-assisted customization — Tailor inspection activities and acceptance criteria to your specific project scope.
- Linked method statement — This ITP is connected to the corresponding method statement describing the work sequence.
- Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
- Editable starting point, not a final document — Review and verify all content against your project specifications and standards before use.
What you can customize
When you save this ITP to your account, every inspection row becomes editable. You can add, remove, or modify:
- Inspection activity — Description of what is being inspected.
- Inspection type — Hold point (H), Witness point (W), Review (R), or Monitor (M).
- Responsibility — Contractor, subcontractor, engineer, or client.
- Frequency — How often the inspection occurs.
- Acceptance criteria — Referenced standard or specification requirement.
- Records — Forms, test reports, or checklists required as evidence.
Why this ITP is used
To verify that soffit fireproofing on composite steel deck achieves the specified fire-resistance rating with compliant thickness, adhesion, and continuity.
Who uses this inspection and test plan
Contractors, QA/QC inspectors, testing agencies, and consultants use this ITP to plan and verify inspections/tests.
When this ITP is prepared and submitted
From substrate readiness through post-application cure, testing, and final hold before ceilings/services are installed.
Who receives or approves this ITP
Consultant/Client for review and approval.
Inspection scope
Substrate cleanliness, environmental conditions, bonding agent application, SFRM application, thickness/density per ASTM E605, adhesion per ASTM E736, and final acceptance.
Typical hold, witness, and review points
HP-0 Mock-up approval; HP-1 Substrate readiness; HP-2 Thickness verification; HP-3 Adhesion acceptance; HP-4 Final inspection before concealment. Witness points throughout as identified.
Typical inspection records
Substrate acceptance, bonding logs, environmental logs, thickness/density/adhesion test reports, NCRs, repair logs, final acceptance certificate.
Important approval note
This ITP is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all inspection activities, hold points, and acceptance criteria must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.
Always verify acceptance criteria against your applicable drawings, specifications, and regulatory requirements. Hold points must be confirmed with the relevant authority before work proceeds past that point.
Inspection and test plan
| Activity | Inspection / Test | Acceptance Criteria | Responsibility | Record |
|---|---|---|---|---|
| Documentation and design verification | Review of approvals, UL/EN design, TDS/SDS | Approved submittals and matching design thickness/density requirements | Contractor QA/QC; Consultant (W) | Approved Submittals Register (W) |
| Substrate readiness (Hold Point HP-1) | Cleanliness and dryness check; deck fixings verification | Surface free of oil/dust/moisture; fixings per deck spec | PFP Superintendent; QA/QC; Consultant (W) | Substrate Acceptance Form (HP-1) |
| Environmental conditions | Temp/RH/dew point readings | Within TDS limits; substrate ≥3°C above dew point [Verify] | QA/QC | Environmental Log (W) |
| Mock-up approval (Hold Point HP-0) | Visual, trial thickness and adhesion sample | Profile/keying acceptable; trial tests satisfactory | Contractor; Consultant (W) | Mock-Up Approval (HP-0) |
| Bonding agent/primer application | WFT spot checks; visual coverage | Continuous coverage; WFT per TDS [Verify] | Applicator; QA/QC (W) | Bonding Agent Log (W) |
| In-process application checks | Nozzle angle, rebound control, first-pass keying in ribs | No shadowing; firm keying into flutes | PFP Superintendent; QA/QC (W) | In-Process Inspection Sheet (W) |
| Dry thickness measurement (ASTM E605) | Depth gauge readings by lot/area including crests/webs/valleys | Lot average ≥ specified; individual ≥ 80–90% or ≥ spec−3 mm [Verify] | QA/QC; Testing Agency (W) | Thickness Test Report (HP-2) |
| Density determination (ASTM E605) | Cores/scrapings per method | Within product/UL design density range [Verify] | Testing Agency; QA/QC (W) | Density Certificate (W) |
| Cohesion/Adhesion (ASTM E736) | Pull-off bond tests at representative locations | ≥ manufacturer/UL design minimum; typical 150–200 psf (≈7–10 kPa) [Verify] | Testing Agency; Consultant (W) | Adhesion Test Report (HP-3) |
| Defect repair and re-test | Visual and re-measure thickness/adhesion | Meets original acceptance criteria | Applicator; QA/QC | Repair & Re-Test Log |
| Final inspection before concealment (Hold Point HP-4) | Walkdown; records review; spot checks | All tests closed; continuity of rating; clean area | QA/QC; Consultant/Client (W) | Final Acceptance Certificate (HP-4) |
| Post-trade damage inspection (if services/ceilings installed) | Visual; spot thickness checks of impacted areas | No damage; any damage repaired and re-inspected | QA/QC; Applicator | Post-Trade Inspection Report |
This table is a read-only public reference. Download the PDF or Excel version, or customize this ITP to edit it for your project.
Frequently asked questions
Related method statement
This Inspection and Test Plan is associated with the Method Statement: Fireproofing Inspection and ITP for Composite Steel Deck Floor Systems (Soffit of Trapezoidal Galvanized Deck) method statement, which describes the step-by-step construction sequence, resources, materials, equipment, safety controls, and environmental controls for this activity.
View the Method Statement: Fireproofing Inspection and ITP for Composite Steel Deck Floor Systems (Soffit of Trapezoidal Galvanized Deck) method statement →Continue with related inspection, method statement, article, and checklist resources.