G
Guest

Method Statement: Installation of Final Sanitary Ware Fixtures (WCs, Wash Basins, Bidets, Showers, Urinals) inspection and test plan example.

Inspection and Test Plan for Method Statement: Installation of Final Sanitary Ware Fixtures (WCs, Wash Basins, Bidets, Showers, Urinals)

AI-assisted inspection and test plan connected to a method statement, with PDF and Excel export.

Published 22 Jul 2026 Rev. 00 1 views
About this ITP: This ITP sets inspection stages and acceptance criteria for installing sanitary fixtures, from materials verification to final functional testing with hold/witness points.

More than a static template

Unlike a downloadable Word or PDF template, this ITP is an AI-assisted editable starting point directly connected to its method statement. Every inspection activity, hold point, and acceptance criterion is structured and ready to adapt to your project.

  • AI-assisted customization — Tailor inspection activities and acceptance criteria to your specific project scope.
  • Linked method statement — This ITP is connected to the corresponding method statement describing the work sequence.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review and verify all content against your project specifications and standards before use.

What you can customize

When you save this ITP to your account, every inspection row becomes editable. You can add, remove, or modify:

  • Inspection activity — Description of what is being inspected.
  • Inspection type — Hold point (H), Witness point (W), Review (R), or Monitor (M).
  • Responsibility — Contractor, subcontractor, engineer, or client.
  • Frequency — How often the inspection occurs.
  • Acceptance criteria — Referenced standard or specification requirement.
  • Records — Forms, test reports, or checklists required as evidence.

Why this ITP is used

To ensure each fixture is installed to specification, safe, watertight, and functional before handover.

Who uses this inspection and test plan

QA/QC inspectors, site engineers, plumbing foremen, and the Consultant/Employer’s Representative.

When this ITP is prepared and submitted

Applied from material receipt through installation and final testing prior to area handover.

Who receives or approves this ITP

Consultant/Engineer for review and approval.

Inspection scope

Materials, set-out, anchors/brackets, fixture mounting, connections, sealing, and functional testing.

Typical hold, witness, and review points

Hold: anchor/bracket installation before mounting. Witness: final functional and leak tests.

Typical inspection records

MIRs, IRs, checklists, torque logs, photos, test sheets, as-built markups.

Important approval note

This ITP is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all inspection activities, hold points, and acceptance criteria must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

Always verify acceptance criteria against your applicable drawings, specifications, and regulatory requirements. Hold points must be confirmed with the relevant authority before work proceeds past that point.

Inspection and test plan

Activity Inspection / Test Acceptance Criteria Responsibility Record
Material receipt and verification Check models, finishes, certifications (WRAS/KIWA/NSF), damages Conforms to approved submittal; no damage QA/QC + Storekeeper MIR, delivery notes, photos
Area readiness and permits Verify finishes, waterproofing sign-off, isolation, permits Area safe and ready; permits valid Foreman + HSE Pre-start checklist, PTW
Set-out verification Heights, clearances, centerlines vs drawings Heights ±5 mm; centerline ±3 mm Engineer + QA/QC Survey record/as-built
Anchor hole drilling and substrate check (HOLD) Confirm scan results, hole diameter/depth/edge distance Per ETA/manufacturer; dust-free holes QA/QC + Engineer IR (Hold) with photos
Bracket/carrier/frame installation Level/plumb, torque on fixings Level/plumb ±2 mm; torque per TDS QA/QC + Foreman In-process checklist
Fixture mounting (basins, WCs, bidets, urinals) Alignment, stability, seating, gasket placement Stable; no rocking; alignment within tolerances QA/QC + Foreman IR with photos
Connection of isolation valves and flexible hoses Thread engagement, torque, no kinks, bend radius ≥3 thread turns; torque per TDS; radius per manufacturer QA/QC + Plumber Torque log, checklist
Trap and waste installation Washer seating, trap seal depth, waste fall Seal ≥50 mm; slope 1:40–1:60 QA/QC + Plumber Checklist
Silicone jointing Joint width/continuity; adhesion; curing Uniform bead 5–10 mm; no voids; cure per TDS QA/QC + Finisher Photos
Functional and leak testing (WITNESS) 10-min leak observation; flow/flush tests; thermostatic setpoint No leaks; flow within spec; WC passes flush; mixer setpoint per spec QA/QC + Consultant IR (Witness), test sheets
Final protection and handover Protection installed; signage; area clean Protection intact; zero snags outstanding Foreman + QA/QC Handover checklist

This table is a read-only public reference. Download the PDF or Excel version, or customize this ITP to edit it for your project.

Frequently asked questions

100% inspection and testing of installed fixtures due to the high risk of concealed leaks and finish damage.

Yes, record actual torque values for critical fasteners and compression fittings where specified by the manufacturer.

Raise an NCR, correct the defect (e.g., replace fixture, re-seal joint), and perform re-inspection and re-testing before acceptance.

Related method statement

This Inspection and Test Plan is associated with the Method Statement: Installation of Final Sanitary Ware Fixtures (WCs, Wash Basins, Bidets, Showers, Urinals) method statement, which describes the step-by-step construction sequence, resources, materials, equipment, safety controls, and environmental controls for this activity.

View the Method Statement: Installation of Final Sanitary Ware Fixtures (WCs, Wash Basins, Bidets, Showers, Urinals) method statement →

Related resources