G
Guest

Method Statement: Installation and Commissioning of Jockey Pump with Piping, Valves, and Pressure Switch Calibration – Method Statement
Method Statement: Installation and Commissioning of Jockey Pump with Piping, Valves, and Pressure Switch Calibration method statement and inspection test plan example.

Method Statement: Installation and Commissioning of Jockey Pump with Piping, Valves, and Pressure Switch Calibration – Method Statement

AI-assisted method statement with matching ITP, PDF download, and Excel export.

Published 03 Jun 2026 Rev. 00 22 views 1 downloads
About this method statement: This method details how to install and commission a fire protection jockey pump, including piping, UL/FM valves, hydrostatic testing, and pressure switch calibration. It defines a HOLD point at calibration and includes HSE, QA/QC, and ITP requirements.

More than a static template

Unlike a downloadable Word or PDF template, this method statement is an AI-assisted editable starting point connected directly to a matching Inspection and Test Plan. Every section is structured, project-adaptable, and ready to export.

  • AI-assisted drafting — Customize every section with AI for your specific project scope.
  • Linked ITP — A matching inspection and test plan is generated alongside the method statement.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review, verify, and adjust all content against your project requirements before use.

Static template vs. Quollnet workflow

FeatureStatic templateQuollnet
Project-specific contentManual fill-in requiredAI-assisted customization
Linked ITPSeparate document, no linkMatching ITP included
Export formatsUsually PDF onlyPDF and Excel
Structured sectionsFree-form layout13 standardized sections
Saved to your accountLocal file onlyCloud-saved, reusable
Content accuracyYou verify everythingAI-assisted, you still verify
CostOften free but time-intensiveFree to customize and download

What you can customize

When you save this method statement to your account, every section becomes editable. The following 13 sections are included:

  • Scope — Defines the activity and its boundaries.
  • References — Standards, specifications, and drawings.
  • Responsibilities — Roles and accountabilities.
  • Resources — Labour, plant, and equipment summary.
  • Materials — Materials and compliance requirements.
  • Equipment — Tools and equipment details.
  • Prerequisites — Hold points and pre-conditions.
  • Method sequence — Step-by-step construction sequence.
  • Safety controls — HSE risk controls and PPE.
  • Environmental controls — Environmental mitigation measures.
  • QA/QC — Quality inspection and test requirements.
  • ITP — Inspection and Test Plan table (has its own page).
  • Attachments — Referenced drawings and documentation.

Why this method statement is used

This method statement is used to define and communicate the approved procedure for carrying out method statement: installation and commissioning of jockey pump with piping, valves, and pressure switch calibration on site. It ensures the work is planned in advance, the correct resources and controls are in place, and all personnel understand responsibilities, sequence, quality requirements, and safety controls before work begins. It aligns site execution with the documented scope and acceptance expectations.

Who uses this method statement

This method statement is used by contractors, site supervisors, project engineers, QA/QC engineers, HSE officers, consultants, and client representatives. It serves as a shared reference for planning, execution, supervision, inspection, and approval of the activity on site.

When it is prepared and submitted

The method statement is prepared before the work activity starts and submitted as part of the pre-construction documentation package for review and approval.

Who reviews or approves it

The method statement is usually submitted to the client representative, consultant, resident engineer, or project management consultant for review and approval before the work commences.

Important approval note

This method statement is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all content must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

For example: if your specification requires a departure from a referenced standard, that departure must be documented and approved separately — this method statement will not capture that automatically. Always verify against your applicable drawings, specifications, and regulatory requirements.

Method statement content

Scope

Work Summary

  • Installation of jockey (pressure maintenance) pump set on housekeeping pad/baseplate including anchors and non-shrink grouting.
  • Installation of suction and discharge piping spools, flexible connectors (if specified), check valve on discharge, isolation valves (OS&Y/butterfly) on suction and discharge, pressure gauges, pressure switch, and drains/vents.
  • Electrical installation: termination to jockey pump controller/MCC, earthing/bonding, rotation check, functional interlocks per approved single-line diagrams.
  • Hydrostatic pressure testing and flushing of connected sections as required by standards and project documents.
  • Calibration of pressure switch cut-in/cut-out (HOLD POINT) with calibrated test gauge/manifold.
  • Functional testing to verify auto start/stop, cut-in/cut-out pressures, absence of short cycling, and leak-free system.
  • Documentation: inspection records, calibration sheets, test certificates, as-built redlines, O&M manuals for handover.

Exclusions/Interfaces

  • Main fire pump installation/commissioning is by others but interface and setpoints must be coordinated to ensure jockey pump settings are above the main pump start and below relief limits [Verify per project specifications].
  • BMS integration and remote monitoring points are covered by the controls contractor; terminations and I/O checks at the jockey pump controller interface form part of coordination.

Constraints and Considerations

  • Maintain clearances required by manufacturer for maintenance access.
  • Do not impose piping strain on the pump nozzles; align and support prior to final bolt-up.
  • Pressure switch calibration is a formal HOLD point and must be witnessed by QA/QC and Client/Consultant as per ITP.

References

Document TypeReference / NumberRevisionNotes
Standard NFPA 20 (latest adopted edition)
Standard NFPA 13 (latest adopted edition)
Standard NFPA 25 (latest adopted edition)
Standard BS EN 12845 Use where project specifies EN route; harmonize with NFPA if required [Verify per project specifications].
Standard ASME B31.9
Standard MSS SP-58 / SP-69
Standard ASTM C1107
Standard NFPA 70 (NEC) / IEC 60364 Select per project jurisdiction [Verify per project specifications].
Standard EN 837-1 / ASME B40.100
Standard ISO/IEC 17025

Responsibilities

RoleResponsibilityName / Party
PM Approve method/ITP, ensure procurement and manpower. Contractor
CM/MEP Supervise installation; verify interface readiness. Contractor
QA/QC Arrange hold/witness points; verify test instruments' calibration. Contractor
HSE Ensure HSE compliance and toolbox talks. Contractor
Supervisor Brief crew; verify method adherence. Contractor
Electrician Execute works per NEC/IEC; complete test sheets. Contractor
Vendor Rep Witness and sign off settings. Supplier
Consultant Review and approve settings and test outcomes. Client/Consultant

Resources

Resource TypeDescriptionQuantityRemarks
Labor Install piping, valves, supports. 2–4
Labor Pump setting, alignment, grouting, coupling. 2–3
Labor Cabling, terminations, testing, rotation check. 2–3
Staff Permits, monitoring, toolbox talks. 1
Staff Inspections and ITP documentation. 1

Materials

MaterialSpecification / GradeQuantityRemarks
Pump 1 set
Valve 1
Valve 2–3
Pipe/Fittings As per BOQ
Flexible connector As required
Grout As required
Anchors As required
Instrumentation Per design

Equipment

EquipmentCapacity / TypeQuantityInspection Required
Chain block ≥1 t 1 Yes
Level 1 Yes
Alignment tool 1 Yes
Torque wrench 1–2 Yes
Test pump/manifold Up to 20 bar / 300 psi 1 Yes
Test instruments Set Yes

Prerequisites

  • Approved shop drawings, vendor datasheets, material approvals, method statement, and ITP.
  • Permits: Hot Work (if welding), Electrical LOTO, Pressure Testing, Confined Space (if applicable) [Verify per project HSE plan and local regulations].
  • Housekeeping pad/base cast to correct elevation and dimensions; surface prepared and cured; anchors positioned per drawings or sleeves cast for post-installation.
  • Calibrated instruments available: pressure gauges (class ≤1.0), alignment tools, torque wrench, electrical testers; calibration certificates valid (≤12 months) [Verify per project specifications].
  • Utilities available: electrical supply, water for flushing/testing, drains identified for controlled discharge.
  • Upstream/downstream system isolation confirmed; LOTO applied; system depressurized before any tie-in.
  • Materials inspected and accepted; certificates and listings (UL/FM) verified.
  • Access, lighting, housekeeping, and lifting arrangements prepared; lifting plan approved where required.
  • Vendor/Manufacturer representative notified for commissioning support if required by warranty.
  • Pre-commissioning checklists printed and briefed to the team.

Method Sequence

StepActivityDescriptionResponsibilityInspection / Hold Point
1 Receiving and Storage Inspect jockey pump and accessories on delivery for damage, nameplate data, and UL/FM listings. Store indoors on skids, protected from moisture and dust. Storekeeper / QA/QC Material inspection
2 Base Preparation Verify housekeeping pad levelness and dimensions. Position anchor bolts or drill and fix post-installed anchors as detailed. Dry fit base/frame and shim to achieve level within ±1 mm/m [Verify per project specifications]. MEP Supervisor Base check
3 Pump Positioning and Temporary Alignment Lift pump/base with certified lifting gear; position on pad. Shim as required. For base-mounted sets, perform rough alignment of pump and motor; do not finalize until after grouting. MEP Supervisor Lifting supervision
4 Grouting of Base Formwork/edge dams as needed. Mix and place non-shrink grout under baseplate continuously; avoid voids. Cure as per manufacturer. Do not torque anchors until grout reaches required strength (e.g., ≥70% in 24–48 h) [Verify]. MEP Supervisor Grout inspection
5 Final Alignment and Anchor Tightening After grout cure, perform final pump/motor alignment using dial or laser per manufacturer tolerance (e.g., offset and angular misalignment within 0.05 mm TIR for small sets) [Verify]. Tighten anchor bolts to specified torque using calibrated torque wrench. Mechanical Technician Alignment check
6 Suction/Discharge Piping Installation Install spools, flexible connectors (if specified), isolation valves (suction/discharge), and discharge check valve. Support piping independently before final nozzle connection (nozzle loads within OEM limits). Bolt-up with correct gasket and torque pattern. Pipefitter In-process inspection
7 Instrumentation Installation Install pressure gauge(s) at discharge header and near pressure switch manifold. Install pressure switch with isolation valve, test tee, and bleed valve for calibration. Provide drain/vent points as detailed. Pipefitter/Technician Instrument check
8 Electrical Termination and Earthing Install cables/conduits as per approved single-line and wiring diagrams. Terminate at jockey pump controller/MCC. Provide earthing/bonding. Verify overload/short-circuit protection and control logic per drawings. Authorized Electrician Electrical pre-check
9 Hydrostatic Testing (Local Sections) Isolate and test new/modified piping sections. Pressurize to 200 psi (13.8 bar) or 50 psi (3.4 bar) above maximum system working pressure, whichever is greater, for 2 hours [Verify]. Monitor with calibrated gauge. MEP Supervisor / QA/QC Witness test
10 Flushing and Cleaning Flush piping at required velocity per NFPA 13/BS EN 12845; discharge to approved drains with strainers. Ensure system free from debris before coupling to pump. MEP Supervisor Witness flush
11 Pre-Start Mechanical/Electrical Checks Verify all fasteners torqued, guards in place, valves set (suction open, discharge open), vents primed, coupling guard fitted. Electrically verify LOTO status cleared, correct fuses/overloads, emergency stop functional. Supervisor/Electrician Checklist review
12 Pressure Switch Calibration (HOLD POINT) Isolate switch via test manifold. Using calibrated master gauge, adjust cut-in and cut-out setpoints: typical cut-in ≈ 10 psi (0.7 bar) below normal system pressure but ≥5 psi (0.35 bar) above main fire pump start; cut-out ≈ 10 psi (0.7 bar) above normal system pressure [Verify per project specifications]. Lock settings and apply tamper seal; label setpoints. QA/QC + Vendor Rep HOLD POINT – Client/Consultant witness
13 Initial Bump Test and Rotation Check Jog motor to confirm correct rotation with coupling disengaged (if applicable). Correct phase if needed. Refit coupling/guard after confirmation. Authorized Electrician Witness
14 Functional Testing – Auto Start/Stop With system pressurized to normal, slowly bleed pressure to trigger cut-in; observe auto start. Restore pressure to trigger cut-out; observe stop. Repeat thrice. Record pressures and times. QA/QC + Supervisor Witness test
15 Handover Documentation Compile and submit records: material approvals, calibration sheets, hydrotest/flushing, alignment/torque, electrical tests, pressure switch certificate, functional test, as-builts, O&M manuals. QA/QC Engineer Document review

Health, Safety, and Environment (HSE) – Safety Controls

Task-Specific Hazards and Controls

1) Hazard: Pressurized water release during testing or calibration
- Likely consequence: Injection injury, slips, equipment damage
- Engineering/procedural control: Install test manifold with isolation and bleed; depressurize before disconnecting; use rated hoses and fittings; set relief valve on test pump; barricade area and post signage
- Required PPE: Safety goggles/face shield, cut-resistant gloves, safety boots, long sleeves
- Collective preventive measure: Pressure testing permit; controlled discharge to drain; spill trays
- Inspection/permit/supervision: QA/QC to verify gauges and relief; Supervisor to enforce permit and LOTO; Consultant witness at hold point

2) Hazard: Electrical shock/arc during terminations and bump tests
- Likely consequence: Severe injury, burns, fatality
- Engineering/procedural control: LOTO for isolation; verify absence of voltage; use insulated tools; correct circuit protection; arc-flash boundaries [Verify per project HSE plan and local regulations]
- Required PPE: Electrically rated gloves, arc-rated face shield, arc-rated clothing, safety boots
- Collective preventive measure: Electrically competent persons only; barriers and signage; emergency stop tested
- Inspection/permit/supervision: Electrical work permit; Supervisor and HSE oversight; tool/tester calibration check

3) Hazard: Lifting and handling of pump/base and valves
- Likely consequence: Crush injuries, dropped loads
- Engineering/procedural control: Certified lifting gear and points; pre-lift meeting; taglines; keep clear of suspended loads
- Required PPE: Helmet with chin strap, gloves, safety boots, high-visibility vest
- Collective preventive measure: Exclusion zone; banksman/signaller control
- Inspection/permit/supervision: Lifting plan and inspection certificates; appointed person supervision

4) Hazard: Hot works (welding/brazing) if required for spools
- Likely consequence: Fire, fumes, burns
- Engineering/procedural control: Hot work permit; fire watch; fire blankets; ventilation; gas cylinder securing; gas leak checks
- Required PPE: Welding helmet, heat-resistant gloves, flame-resistant clothing, safety boots
- Collective preventive measure: Fire extinguishers and charged hose nearby; remove combustibles
- Inspection/permit/supervision: Hot work permit; fire watch for minimum 30 minutes post-work [Verify per project]

5) Hazard: Rotating equipment and pinch points at coupling
- Likely consequence: Lacerations, entanglement
- Engineering/procedural control: Guards installed before operation; no loose clothing; bump test with coupling uncoupled if required
- Required PPE: Safety glasses, gloves, fitted clothing
- Collective preventive measure: Interlocked/machine guarding where available; restricted access
- Inspection/permit/supervision: Pre-start checklist sign-off by Supervisor

6) Hazard: Chemical exposure from grout and cleaning agents
- Likely consequence: Skin/eye irritation, respiratory issues
- Engineering/procedural control: Follow SDS; wet curing methods; avoid dry mixing dust
- Required PPE: Chemical-resistant gloves, goggles, dust mask (P2/P3) as needed
- Collective preventive measure: Local ventilation; washing station
- Inspection/permit/supervision: SDS available on site; HSE inspections

7) Hazard: Confined or congested pump room work
- Likely consequence: Poor egress, heat stress, collision with plant
- Engineering/procedural control: Maintain clear escape routes; limit crew size; hydration plan; ventilation
- Required PPE: Helmet, gloves, boots
- Collective preventive measure: Housekeeping and floor marking; task zoning
- Inspection/permit/supervision: Supervisor walkdown; HSE monitoring of heat index

8) Hazard: Noise and vibration during functional tests
- Likely consequence: Hearing damage, hand-arm vibration
- Engineering/procedural control: Limit test duration; maintain equipment condition; distance where possible
- Required PPE: Hearing protection (earplugs/muffs)
- Collective preventive measure: Noise signage; scheduling to minimize exposure
- Inspection/permit/supervision: HSE to verify noise controls

9) Hazard: Inadvertent main fire pump start due to incorrect setpoints
- Likely consequence: Overpressure, system activation
- Engineering/procedural control: Coordinate setpoints; confirm main pump controller start pressure is below jockey cut-in by defined margin; isolate main pump during setting if permissible
- Required PPE: Standard PPE
- Collective preventive measure: Commissioning plan with interlocks and checks
- Inspection/permit/supervision: QA/QC and Consultant witness at calibration HOLD point

[All controls to be aligned with project HSE plan and local regulations.]

Environmental Controls

  • Water discharge from flushing/testing: Route to approved drains with temporary hoses and strainers; prevent erosion and flooding; record discharge volumes if required by permit.
  • Slurry and sediment: Capture debris with filter bags/strainers; dispose of solids as non-hazardous waste per local regulations.
  • Chemical handling (grout/cleaners): Store in bunded area; avoid washout to drains; manage grout bags and contaminated PPE as construction waste.
  • Noise: Schedule tests during permitted hours; use door closures; provide hearing protection and signage where levels exceed limits [Verify per local regulations].
  • Waste management: Segregate metal offcuts, packaging, and general waste; recycle where facilities exist; maintain waste transfer notes.
  • Energy use: Switch off lighting/tools when not in use; avoid idle running of test pumps.
  • Spill prevention: Drip trays under pump during oil/grease application; spill kits available; report and log any spill.
  • Indoor air quality: Provide ventilation during hot works or solvent use; maintain CO monitoring if combustion equipment is used [Verify per project HSE plan].

QA/QC

Inspection and Testing Requirements

  • Instruments: Pressure gauges, torque wrenches, electrical testers to have valid calibration certificates (≤12 months) [Verify].
  • Base Levelness: ±1 mm/m; record readings at four corners.
  • Alignment: Within OEM limits; record dial/laser readings and temperature at time of measurement.
  • Anchors: Torque to manufacturer values; record in torque sheet; chemical anchors pull-out tests if specified [Verify per project specifications].
  • Piping: Verify support spacing per MSS SP-58 and drawings; ensure correct gasket type and bolt torque pattern.
  • Hydrostatic Test: 200 psi (13.8 bar) or 50 psi above max working pressure (greater governs), hold 2 hours; no visible leakage or unacceptable pressure loss per NFPA 13/BS EN 12845 [Verify per project specifications].
  • Electrical: Insulation resistance ≥2 MΩ at 500 VDC (motor power) and ≥1 MΩ (control circuits) unless OEM specifies otherwise [Verify]. Rotation correct; overload settings per motor FLA.
  • Pressure Switch Calibration (HOLD): Cut-in/cut-out set to approved design values; tolerance ±2 psi (±0.14 bar). Apply tamper seal; label settings; record gauge serials and ambient conditions.
  • Functional Test: Three successive auto start/stop cycles; no short cycling; current within nameplate; no abnormal noise/vibration; no leaks.
  • Documentation: Maintain signed ITP checklists, calibration certificates, test reports, redlined drawings, and O&M manuals in the turnover dossier.

Acceptance

  • All witness/hold points satisfied and signed by Client/Consultant.
  • Deviations/NCRs closed with approved dispositions before handover.

Attachments

  • Approved shop drawings (mechanical and electrical) for jockey pump installation and piping details.
  • Manufacturer installation, operation, and maintenance (IOM) manuals.
  • Material submittals and approvals (pump, valves, instruments, grout, anchors).
  • Calibration certificates for gauges, torque wrenches, and electrical test instruments.
  • Risk Assessment / Job Hazard Analysis (JHA) for this activity.
  • Permits: Hot Work, Electrical LOTO, Pressure Testing, Confined Space (if applicable).
  • Checklists: Base/Anchor, Piping Installation, Electrical Pre-Commissioning, Pre-Start, Functional Testing.
  • ITP forms and sign-off sheets including HOLD/WITNESS point records.
  • As-built redline markups of piping and instrumentation locations.
  • Commissioning plan and start-up reports with vendor/consultant sign-offs.

This content is a read-only public reference. Download or customize to get an editable version.

ITP preview

The first inspection activities from the linked ITP for Method Statement: Installation and Commissioning of Jockey Pump with Piping, Valves, and Pressure Switch Calibration:

ActivityInspection / TestAcceptance CriteriaResponsibilityRecord
Materials receiving (pump, valves, instruments)Verification of approvals, listings (UL/FM), certificates, and conditionConforms to approved submittals; no damage; certificates availableQA/QC, Supplier RepMaterial Inspection Report
Base preparation and anchorsLevel survey; anchor type/position checkLevelness ±1 mm/m; anchors per drawings/specsQA/QC, MEP SupervisorBase/Anchor Checklist
GroutingGrout material compliance; placement and curing checkASTM C1107 compliant; cure per manufacturerQA/QCGrout Inspection Report

Showing 3 of 10 inspection activities. View full ITP →

Related Inspection and Test Plan

An Inspection and Test Plan (ITP) is available for Method Statement: Installation and Commissioning of Jockey Pump with Piping, Valves, and Pressure Switch Calibration. The ITP defines the inspection activities, acceptance criteria, hold and witness points, responsible parties, and records required to verify the work described in this method statement.

View the Method Statement: Installation and Commissioning of Jockey Pump with Piping, Valves, and Pressure Switch Calibration ITP →

Frequently asked questions

Commonly, cut-in is about 10 psi (0.7 bar) below normal system pressure but still above the main fire pump start pressure, and cut-out is about 10 psi (0.7 bar) above normal. Verify with project specifications and NFPA 20 guidance.

Install the UL/FM-listed check valve on the jockey pump discharge, oriented with flow direction away from the pump and accessible for maintenance.

Yes. Any new or modified fire protection piping sections must be hydrostatically tested per NFPA 13 or BS EN 12845. Protect the pump from test pressure using isolation and bypass as needed.

QA/QC and the Client/Consultant must witness the HOLD point; the vendor representative should attend if required by warranty or the project specifications.

Typically it should be isolated or its start setpoint verified to be below the jockey cut-in to prevent unintended starting. Follow the approved commissioning plan and permits.

Continue with related Quollnet resources connected to this method statement.

Related resources