CFA Piling Method Statement — Auger Drilling, Continuous Concrete Placement & Cage Installation inspection and test plan example.

Inspection and Test Plan for CFA Piling Method Statement — Auger Drilling, Continuous Concrete Placement & Cage Installation

AI-assisted inspection and test plan connected to a method statement, with PDF and Excel export.

Published 18 May 2026 Rev. 00 622 views 303 downloads
About this ITP: This ITP defines the inspections and tests required for CFA piling including plant calibration, continuous monitoring during drilling and extraction, reinforcement insertion checks and fresh concrete sampling frequency. It ensures contractual hold points are observed and records retained.

More than a static template

Unlike a downloadable Word or PDF template, this ITP is an AI-assisted editable starting point directly connected to its method statement. Every inspection activity, hold point, and acceptance criterion is structured and ready to adapt to your project.

  • AI-assisted customization — Tailor inspection activities and acceptance criteria to your specific project scope.
  • Linked method statement — This ITP is connected to the corresponding method statement describing the work sequence.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review and verify all content against your project specifications and standards before use.

What you can customize

When you save this ITP to your account, every inspection row becomes editable. You can add, remove, or modify:

  • Inspection activity — Description of what is being inspected.
  • Inspection type — Hold point (H), Witness point (W), Review (R), or Monitor (M).
  • Responsibility — Contractor, subcontractor, engineer, or client.
  • Frequency — How often the inspection occurs.
  • Acceptance criteria — Referenced standard or specification requirement.
  • Records — Forms, test reports, or checklists required as evidence.

Why this ITP is used

To formalise inspection and acceptance criteria for each critical stage of CFA piling and ensure traceable records for compliance with design and contractual requirements.

Who uses this inspection and test plan

Piling contractors, site QA/QC personnel, Engineers, independent testing laboratories and Client representatives use this ITP to verify piling works.

When this ITP is prepared and submitted

Used during mobilisation and continuously during piling operations; prior to first pile and at each defined hold point and sampling event throughout the piling programme.

Who receives or approves this ITP

The ITP is usually submitted to the client representative, consultant, resident engineer, or project management consultant for review and approval before the related work activity starts.

Inspection scope

Covers plant calibration, pile set-out, drilling parameters logging, concrete pumping pressure & flow monitoring, reinforcement placement and fresh concrete sampling and testing.

Typical hold, witness, and review points

Pre-mobilisation review, calibration of instrumentation, first pile trial, verification of continuous placement parameters, reinforcement insertion, fresh concrete sampling and post-pile survey.

Typical inspection records

Automated monitoring logs, batch tickets, calibration certificates, slump & temperature logs, cube test certificates, survey reports and completed ITP sign-off sheets.

Important approval note

This ITP is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all inspection activities, hold points, and acceptance criteria must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

Always verify acceptance criteria against your applicable drawings, specifications, and regulatory requirements. Hold points must be confirmed with the relevant authority before work proceeds past that point.

Inspection and test plan

Activity Inspection / Test Acceptance Criteria Responsibility Record
Pre-mobilisation review Check method statement, RAMS, plant certificates and ITP distributed All documents approved and personnel briefed Piling Manager Document register, toolbox talk attendance sheet
Plant & instrumentation calibration Calibration certificates checked for rig torque sensor, pressure transducer and flow meter Calibration valid and logged Plant Engineer / QA Calibration certificates, commissioning checklist
Set-out verification Confirm pile centre coordinates and mark on ground prior to drilling Position within ±50 mm of design Surveyor Set-out check sheet, survey printout
Drilling parameters monitoring Continuous logging of depth, rpm, torque and penetration rate; verify no unexpected spikes Logged data complete; no exceedance of preset alarm limits; if exceedance then Engineer notified Piling Supervisor Automated drill log (exported file)
Concrete pumping & pressure control Continuous pressure & flow logging; verify pump pressure within acceptable range and continuous flow during extraction No interruptions, pressure within documented band; pump stoppages investigated and reported Pump Operator / QA Pump log, automated pressure/flow data
Reinforcement cage insertion & vibration Dimensional and cover checks; monitor for segregation during vibration; visual inspection Cage positioned centrally, cover per drawing, no visible segregation Piling Supervisor / Installer Cage insertion checklist, photo record
Fresh concrete sampling Take slump, temperature and cube samples immediately on arrival/during pour; frequency: every pour or every 6 m3 (whichever more frequent); minimum 3 cubes per sample (150 mm) Slump within ±25 mm of target; temperature within contract limits; cubes tested at 7 & 28 days meet criteria QA / Testing Technician Batch tickets, slump & temperature logs, cube test certificates
Pile head cut-off & final survey Verify cut-off level and verticality; check top of pile and record dimensions Cut-off within +/-10 mm and pile within positional/verticality tolerances Surveyor / Piling Supervisor As-built survey report, cut-off record

This table is a read-only public reference. Download the PDF or Excel version, or customize this ITP to edit it for your project.

Frequently asked questions

Sample fresh concrete for each pour or at least every 6 m3 placed, whichever is more frequent. Each sample set should include slump, temperature and a minimum of three 150 mm cube specimens.

Key hold points include plant/instrument calibration, completion of first pile/trial, verification of continuous concrete placement parameters and reinforcement insertion checks prior to proceeding with production piles.

Related method statement

This Inspection and Test Plan is associated with the CFA Piling Method Statement — Auger Drilling, Continuous Concrete Placement & Cage Installation method statement, which describes the step-by-step construction sequence, resources, materials, equipment, safety controls, and environmental controls for this activity.

View the CFA Piling Method Statement — Auger Drilling, Continuous Concrete Placement & Cage Installation method statement →

Continue with related inspection, method statement, article, and checklist resources.

Related resources