Install Contiguous Pile Wall: Cage and Concreting
Definition: Install contiguous pile wall—cage and concreting checklist guides site engineers through verifying cage cover, centralizers, tremie placement, and pile continuity during bored contiguous wall construction.
- Verify cage cover, centralizers, and tremie embedment before concreting.
- Reduce defects and delays by standardizing acceptance criteria and evidence.
- Interactive, commentable checklist with export and QR code verification.
- Ensure pile continuity and clean displacement in slurry-supported bores.
Install contiguous pile wall—cage and concreting is a focused checklist for bored pile wall construction that helps site engineers confirm reinforcement cage cover, centralizers, tremie placement, and continuity of adjacent piles. It aligns day-to-day work with the method statement for contiguous bored piles, reinforcement cage installation, and tremie concreting under slurry or groundwater. The scope begins after drilling is complete and boreholes are ready for cages, and it ends once concrete is placed, heads are verified, and as-built data is captured. By standardizing measurable acceptance criteria—cover tolerances, tremie embedment, sediment limits, and volume reconciliation—teams avoid segregation, trapped debris, and inconsistent pile alignment. The checklist emphasizes polymer centralizers, continuous supply, embedment of the tremie pipe, and clean slurry displacement to deliver structurally reliable, durable piles ready for trimming and capping beam works. Use it live in the field: tick items, attach photos and readings, add comments, and export PDF/Excel via QR.
- Control concrete quality and reinforcement positioning by verifying cage geometry, centralizer spacing, and minimum cover before any lift. Quantified checks on sediment, slurry, tremie diameter, and embedment reduce segregation and void risk, resulting in durable, continuous piles ready for trimming and capping beam integration.
- Reduce rework by confirming continuous concrete head, uninterrupted supply, and verified rise using weighted tapes. Acceptance windows for slump, embedment, and placed volumes keep operations predictable. Transparent logs of batch tickets, timestamps, and test specimens support inspections and approval without delaying follow-on works.
- Improve traceability with consistent records: bar heat numbers, coupler torque, slurry results, and as-built surveys for position and cut-off. Interactive online checklist with tick, comment, and export features secured by QR code. Supervisors see real-time compliance, corrective actions, and close-out status across multiple piles and shifts.
- Assure pile continuity at wall scale by enforcing pour sequencing, monitoring overlap limits, and reconciling theoretical versus placed volume. Clean displacement of slurry and controlled trimming of contaminated tops protect integrity at the construction joint, reducing infiltration risk and ensuring predictable performance of the contiguous wall.
Pre-Concreting Checks
Reinforcement Cage
Centralizers and Cover
Tremie Setup and Placement
Concreting Operations
Continuity and Records
Reinforcement cage cover and centralizers: achieving uniform clearance
Uniform cover around the reinforcement cage controls durability and structural reliability of contiguous bored piles. Polymer wheel centralizers and spacers should be fixed at 1.5–2.0 m vertical spacing, with additional units near the toe and joints. Dry-fitting the cage through a guide ring verifies that the nominal cover—commonly 60 mm ±10 mm with an absolute minimum of 50 mm—is achieved before lifting. Use calipers to confirm bar sizes, tape measures to check spiral pitch within tolerance, and a calibrated torque wrench for couplers. Temporary stiffeners prevent ovalization during handling, keeping out-of-round within 10 mm. Document heat numbers and spacer batches to maintain traceability. On site, a quick four-quadrant cover check with a gauge or measured offsets provides immediate acceptance evidence, and photographs validate spacer distribution. These practices reduce the chance of steel touching the bore wall, preventing corrosion initiation and maintaining the designed load path from concrete to reinforcement.
- Place centralizers near the toe and at 1.5–2.0 m spacing.
- Target 60 mm cover, never less than 50 mm anywhere.
- Dry-fit cages through a guide ring before lifting.
- Keep out-of-round within 10 mm during handling.
- Record bar heats, spacer batches, and torque values.
Tremie concreting essentials: first charge, embedment, and continuity
Successful tremie placement depends on a sealed first charge, adequate embedment, and uninterrupted supply. Assemble tremie sections with clean gaskets and prove joints with a brief 0.2 MPa water test. Select an internal diameter at least three times the largest aggregate and no less than 150 mm to limit friction and blockages. Position the tip 150–300 mm above the pile base and launch with a plug or go-devil to prevent washout. Maintain at least 3 m of tremie embedment below the rising concrete head, monitoring with a weighted tape and a simple head calculation. Keep truck intervals under five minutes to avoid cold joints, track batch tickets, and record slump at discharge. Watch returns: clearer displaced slurry and uniform head rise indicate sound displacement. If contamination appears at the top, plan for trimming 0.5–1.0 m after set.
- Water-test tremie joints at 0.2 MPa for 5 minutes.
- Use ID ≥ 150 mm and ≥ 3× aggregate size.
- Maintain ≥ 3 m tremie embedment at all times.
- Keep truck gaps ≤ 5 minutes to prevent cold joints.
- Monitor head rise with a weighted tape.
Wall continuity and quality records: proving performance pile by pile
Contiguous wall performance depends on consistent pile continuity and verifiable records. Follow the approved pour sequence to minimize gaps or misalignment between adjacent piles. Survey as-built positions to within ±25 mm and confirm cut-off within ±10 mm to ensure proper capping beam engagement. Reconcile placed volume against theoretical to detect overbreak or necking; investigate deviations greater than 10%. Maintain a complete evidence file: slurry tests, sediment checks, torque logs, heat numbers, tremie embedment charts, timestamps, and photos. Tag each pile with ID and pour details for traceability, and obtain same-day approvals to keep works flowing. If top contamination is suspected, plan controlled trimming before constructing the capping beam. These measures create a defensible QA trail and help avoid later remediation costs.
- Follow the approved pour sequence for continuity.
- Survey position ±25 mm and cut-off ±10 mm.
- Reconcile actual versus theoretical volume each pile.
- Tag piles with ID and pour date immediately.
- Secure same-day digital approvals and uploads.
How to Use This Interactive Cage and Concreting Checklist
- Preparation: assemble tremie pipes and gaskets, centralizers, cover gauges, weighted tape, Marsh funnel, mud balance, sand kit, calipers, torque wrench, guide ring, survey kit, concrete testing gear, and PPE.
- Preparation: confirm access, pump location, concrete delivery schedule, lighting, communications, approved method statement, and permits. Brief crew on sequence, acceptance limits, and evidence to capture.
- Using the Interactive Checklist: open the checklist, select project and pile ID, start interactive mode, and assign a responsible owner for each section.
- Using the Interactive Checklist: tick items as completed, attach photos, enter readings (slump, density, embedment), scan batch tickets, and link instrument reports.
- Using the Interactive Checklist: record nonconformances with comments, assign corrective actions and deadlines, and @mention stakeholders for rapid resolution.
- Export: generate a QR-authenticated PDF/Excel report with all evidence, timestamps, signatures-in-progress, and shareable links for supervisors and inspectors.
- Sign-Off: capture digital signatures from superintendent, inspector, and contractor; lock the record; distribute and archive per approved project specifications and authority requirements.
Call to Action
- Start Checklist Tick off tasks, leave comments on items or the whole form, and export your completed report to PDF or Excel—with a built-in QR code for authenticity.
- Download Excel - Contiguous Pile Wall—Cage and Concreting
- Download PDF - Contiguous Pile Wall—Cage and Concreting
- View Image - Contiguous Pile Wall—Cage and Concreting