G
Guest

Method Statement: Installation of Underground uPVC/HDPE Gravity Drainage Networks – Method Statement
Method Statement: Installation of Underground uPVC/HDPE Gravity Drainage Networks method statement and inspection test plan example.

Method Statement: Installation of Underground uPVC/HDPE Gravity Drainage Networks – Method Statement

AI-assisted method statement with matching ITP, PDF download, and Excel export.

Published 17 Jul 2026 Rev. 00 1 views
About this method statement: This method statement details how to install underground uPVC/HDPE gravity drainage. It covers trenching, bedding, jointing, manhole connections, backfilling, and testing to international standards.

More than a static template

Unlike a downloadable Word or PDF template, this method statement is an AI-assisted editable starting point connected directly to a matching Inspection and Test Plan. Every section is structured, project-adaptable, and ready to export.

  • AI-assisted drafting — Customize every section with AI for your specific project scope.
  • Linked ITP — A matching inspection and test plan is generated alongside the method statement.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review, verify, and adjust all content against your project requirements before use.

Static template vs. Quollnet workflow

FeatureStatic templateQuollnet
Project-specific contentManual fill-in requiredAI-assisted customization
Linked ITPSeparate document, no linkMatching ITP included
Export formatsUsually PDF onlyPDF and Excel
Structured sectionsFree-form layout13 standardized sections
Saved to your accountLocal file onlyCloud-saved, reusable
Content accuracyYou verify everythingAI-assisted, you still verify
CostOften free but time-intensiveFree to customize and download

What you can customize

When you save this method statement to your account, every section becomes editable. The following 13 sections are included:

  • Scope — Defines the activity and its boundaries.
  • References — Standards, specifications, and drawings.
  • Responsibilities — Roles and accountabilities.
  • Resources — Labour, plant, and equipment summary.
  • Materials — Materials and compliance requirements.
  • Equipment — Tools and equipment details.
  • Prerequisites — Hold points and pre-conditions.
  • Method sequence — Step-by-step construction sequence.
  • Safety controls — HSE risk controls and PPE.
  • Environmental controls — Environmental mitigation measures.
  • QA/QC — Quality inspection and test requirements.
  • ITP — Inspection and Test Plan table (has its own page).
  • Attachments — Referenced drawings and documentation.

Why this method statement is used

This method statement is used to define and communicate the approved procedure for carrying out method statement: installation of underground upvc/hdpe gravity drainage networks on site. It ensures the work is planned in advance, the correct resources and controls are in place, and all personnel understand responsibilities, sequence, quality requirements, and safety controls before work begins. It aligns site execution with the documented scope and acceptance expectations.

Who uses this method statement

This method statement is used by contractors, site supervisors, project engineers, QA/QC engineers, HSE officers, consultants, and client representatives. It serves as a shared reference for planning, execution, supervision, inspection, and approval of the activity on site.

When it is prepared and submitted

The method statement is prepared before the work activity starts and submitted as part of the pre-construction documentation package for review and approval.

Who reviews or approves it

The method statement is usually submitted to the client representative, consultant, resident engineer, or project management consultant for review and approval before the work commences.

Important approval note

This method statement is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all content must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

For example: if your specification requires a departure from a referenced standard, that departure must be documented and approved separately — this method statement will not capture that automatically. Always verify against your applicable drawings, specifications, and regulatory requirements.

Method statement content

Scope

Purpose

This method statement details the complete procedure for installation of underground uPVC/HDPE gravity drainage pipelines, including survey and setting out, trench excavation and support, dewatering, bedding preparation, pipe laying and jointing (push-fit/solvent-weld for uPVC; butt/electrofusion for HDPE), connections to manholes and chambers, backfilling in layers, compaction and field density testing, leakage and deflection testing, CCTV survey, and reinstatement up to formation level.

Extent of Works

  • Pipe diameters: DN100–DN600 [Verify per project specifications]
  • Locations: off-carriageway and within carriageway/travelled ways
  • Depth of cover: typically ≥600 mm verge/landscaped areas; ≥900 mm under roads [Verify per project specifications]
  • Interfaces: tie-in to existing manholes, new precast manholes, catchpits, gullies, laterals, cleanouts/rodding eyes, and outfalls

Exclusions

  • Pressurised pipelines and rising mains
  • Structural design of temporary works/shoring (provided separately)
  • Permanent pavement reinstatement (covered by separate method, unless otherwise stated)

References

Document TypeReference / NumberRevisionNotes
Standard ASTM D2321
Standard BS EN 1401-1
Standard BS EN 12666-1
Standard ISO 21307 / ASTM F2620
Standard ISO 12176
Standard EN 1610
Standard BS EN 1917 / ASTM C478
Standard ASTM C923
Standard ASTM D698 / ASTM D1557
Standard ASTM D6938
Standard BS 6031 / EN 1997-1 Temporary works design to BS 5975 where applicable [Verify per project].
Guideline WRC MSCC (latest) / NASSCO PACP
Standard ASCE 38 / PAS 128 For pre-excavation utility surveys [Verify per project].

Responsibilities

RoleResponsibilityName / Party
PM Authorize MS/ITP, ensure competent personnel and permits Contractor
SE Check survey controls, verify line/level, request inspections Contractor
QA/QC Raise ITP hold/witness, review test results, NCR management Contractor
HSE Issue permits (PTW), enforce controls, toolbox talks Contractor
Surveyor Establish/control benchmarks, check invert levels and slopes Contractor
Foreman Ensure workmanship, plant coordination, safe systems of work Contractor
Technician Follow ISO 21307/ASTM F2620, maintain weld logs, equipment calibration Contractor
Crew Comply with tolerances, protect pipes, housekeeping Contractor
3rd Party Provide calibrated equipment and certified results Independent Lab
Engineer Witness/hold points per ITP, approve records Engineer

Resources

Resource TypeDescriptionQuantityRemarks
Personnel 1 Foreman, 1 Site Engineer, 1 Surveyor, 1 HSE Officer, 1 Fusion Technician (if HDPE), 6–10 Pipe Layers/Laborers, 1 Excavator Operator, 1 Banksman ~12–16
Subcontractor CCTV survey and leak/air testing As required

Materials

MaterialSpecification / GradeQuantityRemarks
PVC-U DN100–DN600, SDR per design
HDPE (PE100) DN100–DN600
EPDM/NBR
Solvent cement/primer
Lubricant
Granular material Class I/II per ASTM D2321
Fill
EPDM/SS clamp
Tape/Wire

Equipment

EquipmentCapacity / TypeQuantityInspection Required
20–35 t 1–2 Yes
As required Yes
3–6" pumps 1–2
1 set
3–4
1 Yes
1
1
1

Prerequisites

  • Approved IFC drawings, specifications, and this Method Statement with ITP.
  • Permit to Dig with utility survey (ASCE 38/PAS 128 quality level), mark-out, and positive identification via vacuum potholing where conflicts are suspected.
  • Temporary Works Design for trench support approved where trench depth/ground conditions require shoring [Verify per project].
  • Traffic Management Plan approved where working in carriageways.
  • Dewatering/Discharge permit in place if groundwater is anticipated.
  • Materials approvals (Pipes, gaskets, cement/primer, connectors) and delivery inspections completed.
  • Calibration certificates current for lasers, fusion equipment, density gauge.
  • Competency/qualifications: fusion technician certified; nuclear gauge operator certified; plant operators licensed; confined space team trained.
  • HSE documentation: Task risk assessment (RAMS), toolbox talk completed, emergency/ rescue plan for confined spaces, Hot Work Permit (for fusion) as needed.
  • Weather and groundwater conditions assessed; works sequenced to minimize open trench length.
  • Pre-start coordination with adjacent trades/utilities; notification to stakeholders as required.

Method Sequence

StepActivityDescriptionResponsibilityInspection / Hold Point
1 Site handover and survey control Confirm benchmarks and establish control points along alignment. Protect and verify before use. Surveyor / Site Engineer Internal check
2 Utility detection and permits Scan with cable/pipe locator and GPR; mark utilities. Obtain Permit to Dig. Pothole to confirm depth/position where required. HSE / Site Engineer Hold Point: Permit to Dig
3 Setting out line and level Set out pipe centerline and manhole positions. Establish design invert at start and end, and intermediate points using pipe laser. Surveyor Witness by QA/QC
4 Trench excavation Excavate to formation level considering bedding thickness. Maintain safe side slopes or install shoring/boxes. Limit open trench length to manageable sections (e.g., ≤30–50 m) [Verify]. Foreman / Excavator Operator Hold Point: Formation level check
5 Dewatering and trench stability Install sump pumps/wellpoints if required. Maintain water level below formation. Prevent soil piping and base instability. Foreman Routine
6 Formation preparation Trim formation; remove soft spots. If over-excavated, fill with compacted bedding material. Foreman Witness
7 Bedding placement Place 100–150 mm bedding (Class I/II). Screed to designed grade using laser. Do not compact directly under pipe seat excessively. Foreman / Site Engineer Hold Point: pre-lay bedding
8 Pipe laying orientation Lay from downstream to upstream; sockets facing upstream. Verify pipe cleanliness before jointing. Pipe Layer Continuous
9 uPVC push-fit jointing Apply approved lubricant to spigot and gasket. Insert to witness mark with controlled force. Ensure gasket not displaced. Pipe Layer Witness
10 uPVC solvent-weld jointing (if specified) Dry-fit to confirm interference. Clean/prime (ASTM F656). Apply cement (ASTM D2564) evenly, assemble with 1/4 turn. Wipe excess; support until set. Pipe Layer Witness / Hot Work permit not required (cold bond)
11 HDPE butt fusion Face/align pipes; heat to specified bead; apply fusion pressure/time; cool under pressure. Record parameters using data logger. Fusion Technician Hold/Witness
12 HDPE electrofusion (if used) Scrape oxide layer, clean, insert alignment clamps, connect EF box, weld per barcode parameters, allow full cooling. Fusion Technician Witness
13 Alignment and gradient verification Use pipe laser/level to confirm invert at each pipe and at manholes. Site Engineer Witness
14 Manhole connection (new or existing) Core drill manhole wall to pipe OD; fit flexible connector (ASTM C923). Install rocker pipes (0.5–1.0 m) adjacent to manhole. Rebench as required; seal watertight. Foreman / Mason Hold Point: before backfill at connection
15 Initial surround and sidefill Place and compact sidefill evenly to springline and to 150–300 mm above crown. Hand-tamp near pipe, avoid displacement. Foreman Witness
16 Warning tape and tracer wire Install detectable warning tape ~300 mm above pipe. Lay tracer wire along trench with test boxes at access points [if required by Client]. Foreman Witness
17 Backfill in layers (non-traffic) Place selected backfill in ≤200–250 mm layers and compact. Foreman Witness
18 Backfill in carriageway Place engineered backfill per authority spec in ≤150–200 mm layers; compact with suitable equipment; protect pipe from dynamic loads until ≥300 mm cover. Foreman Hold/Witness
19 Leakage testing (gravity) After initial backfill and stabilization, test per EN 1610 using air or water as specified. Isolate sections between manholes. QA/QC / Specialist Witness (Engineer)
20 Deflection testing (flexible pipes) Mandrel/deflectometer test after suitable period (e.g., 30 days) or as directed. QA/QC / Specialist Witness (Engineer)
21 CCTV survey CCTV inspect entire run, record observations and coding per WRC MSCC or NASSCO PACP. Specialist Witness (Engineer)
22 As-built survey Survey inverts, coordinates of manholes/laterals, and pipe gradients. Update GIS if applicable. Surveyor Review
23 Surface reinstatement to formation Reinstate to formation/subgrade or as specified, protect awaiting final pavement. Foreman Witness
24 Demobilization and housekeeping Remove shoring, signage, surplus materials. Close permits. Handover O&M/records. PM / QA/QC Final inspection

Health, Safety and Environment (HSE) - Safety Controls

Risk-assessed, task-specific controls

  • Hazard: Underground utility strike (electric/gas/fiber)
  • Likely consequence: Electrocution, gas explosion, service outage
  • Engineering/procedural control: Permit to Dig; pre-excavation GPR/CAT scan; mark and maintain exclusion zones; vacuum potholing to verify; hand-dig within 1 m of suspected utilities
  • Required PPE: Dielectric gloves when required, safety boots, arc-rated PPE if working near HV per utility rules [Verify]
  • Collective preventive measure: Physical barriers/goalposts over known utilities; spotter/banksman during excavation
  • Inspection/permit/supervision: Permit to Dig; daily briefings; utility owner approvals where needed

  • Hazard: Trench collapse/engulfment

  • Likely consequence: Fatal crush/asphyxiation
  • Engineering/procedural control: Shoring/trench boxes per Temporary Works Design; keep surcharge loads ≥1 m from edge; staged excavation; limit open length; do not enter unsupported trench >1.2 m deep
  • Required PPE: Hard hat, boots, gloves, hi-vis, gas monitor if required
  • Collective preventive measure: Edge protection (guardrails), ladder access every 6–9 m, trench crossing boards
  • Inspection/permit/supervision: Daily competent person inspection; after rain or dewatering changes; excavation permit

  • Hazard: Plant–people interface (struck-by/crushed)

  • Likely consequence: Serious injury/fatality
  • Engineering/procedural control: Segregated walkways; exclusion zones; assigned banksman; 360° cameras/alarms; reverse alarms
  • Required PPE: Hi-vis, hard hat, steel-toe boots
  • Collective preventive measure: Physical barriers and spotters; traffic management per approved plan
  • Inspection/permit/supervision: Daily plant checks; TM audits

  • Hazard: Lifting of pipes/manhole components

  • Likely consequence: Dropped load injuries, crush damage to pipes
  • Engineering/procedural control: Certified lifting accessories; tag lines; lift plan; avoid lifting over persons; use spreader bars for long pipes
  • Required PPE: Helmet with chin strap, gloves, boots, eye protection
  • Collective preventive measure: Exclusion zone around lift; competent crane/rig operator
  • Inspection/permit/supervision: LOLER/third-party certificates; lifting plan approval; appointed person supervision

  • Hazard: Confined space entry to manholes

  • Likely consequence: Asphyxiation/toxic exposure (H2S), drowning
  • Engineering/procedural control: Confined Space Permit; gas test (O2, H2S, CO, LEL); forced ventilation; top-man standby; retrieval tripod/winch; rescue plan and drills
  • Required PPE: Harness, gas detector, gloves, boots, helmet, eye protection
  • Collective preventive measure: Barricade openings; continuous atmospheric monitoring
  • Inspection/permit/supervision: Permit to Enter; competent entry supervisor

  • Hazard: Hot surfaces/electrical during PE fusion

  • Likely consequence: Burns/electric shock
  • Engineering/procedural control: Dedicated fusion area; barriers; verify voltage; residual current device (RCD); cool-down times enforced
  • Required PPE: Heat-resistant gloves, long sleeves, face shield/eye protection
  • Collective preventive measure: Fire extinguisher CO2/foam available; no flammables nearby
  • Inspection/permit/supervision: Equipment PAT/calibration; hot work permit if local rules require [Verify]

  • Hazard: Solvent cement/primer vapors (uPVC)

  • Likely consequence: Eye/respiratory irritation, dermatitis, fire risk
  • Engineering/procedural control: Use in well-ventilated areas; lids closed when not in use; small decanting; no ignition sources
  • Required PPE: Nitrile gloves, safety glasses, half-mask respirator with organic vapor cartridges if ventilation poor [Verify]
  • Collective preventive measure: Spill kit; SDS available; storage in flammable cabinet
  • Inspection/permit/supervision: COSHH/chemical handling review; container expiry check

  • Hazard: Water ingress/flooding in trench

  • Likely consequence: Drowning, floatation of pipes, base instability
  • Engineering/procedural control: Predict groundwater; install pumps/standby unit; place sandbags/berms to divert stormwater; secure pipes from flotation during events
  • Required PPE: Waders as needed, gloves, boots
  • Collective preventive measure: Emergency pump; alarm for heavy rain
  • Inspection/permit/supervision: Dewatering permit; monitor discharge quality

  • Hazard: Noise/vibration from compaction equipment

  • Likely consequence: Hearing loss, HAVS
  • Engineering/procedural control: Select low-vibration tools; job rotation; maintain equipment
  • Required PPE: Hearing protection (SNR per site), anti-vibration gloves
  • Collective preventive measure: Noise barriers where feasible
  • Inspection/permit/supervision: Exposure monitoring; HAVS logs

[Verify per project HSE plan and local regulations]

Environmental Controls

  • Spoil management: Segregate reusable material from waste; stockpile on impermeable mat away from drains; cover to prevent runoff/dust.
  • Silt and water control: Use silt fences and inlet protection; route dewatering to settlement tank/bag; discharge only under permit with turbidity within limits [Verify].
  • Fuel/chemical management: Bunded areas for fuels; drip trays under pumps; spill kits within 20 m; immediate cleanup and report.
  • Dust suppression: Water bowsers/misting during dry conditions; wheel wash when exiting public roads.
  • Noise/time restrictions: Adhere to working hour permits; maintain equipment; use acoustic shrouds where practicable.
  • Waste: Dispose solvent cans, rags, gasket offcuts as per waste codes; recycle uPVC/HDPE offcuts via approved recycler where available.
  • Soil/groundwater contamination: Stop-work protocol on suspected contamination; isolate area; sampling plan.
  • Ecology/archaeology: If finds encountered, cease work and notify responsible authority.
  • Carbon/efficiency: Optimize haul routes; backhaul with imported fill where practical; use low-emission plant when available.
    [Verify per project environmental plan and local regulations]

Quality Assurance / Quality Control

Controls and Records

  • Submittals: Material data sheets, certificates of compliance, calibration certs, fusion procedures, manufacturer installation guides.
  • Incoming material inspection: Check pipe markings (standard, stiffness class, DN, batch), ovality ≤3%, surface condition, gaskets condition, solvent cement shelf life.
  • Survey and set-out: Independent check of benchmarks; pre-pour style checklists for bedding and levels.
  • Jointing QA:
  • uPVC push-fit: 100% visual; insertion depth marks confirmed.
  • uPVC solvent: Verify primer/cement brand and cure time; random pull checks where feasible on small dia offcuts [Verify].
  • HDPE fusion: Qualified technicians only; equipment calibrated; 100% weld logs; bead visual acceptance; produce and test trial welds at start of shift/change of parameters per spec [Verify test method].
  • Compaction QA: Layer thickness and MDD target (≥95% non-traffic; ≥98% traffic areas [Verify]); field density testing frequency typical: 1 test per 50 m per lift in carriageway and 1 per 100 m per lift in non-traffic areas [Verify per project].
  • Leakage testing: Conduct EN 1610 air or water tests as specified; isolate between manholes; repair leaks and retest until passing.
  • Deflection testing: For flexible pipes (HDPE/structured wall), perform after bedding consolidation; typical acceptance ≤5%.
  • CCTV: Post-test CCTV with coding; rectify defects and re-survey if required.
  • Documentation: ITP with hold/witness points; IRs; daily reports; as-built drawings (coordinates and inverts); O&M handover including test certificates, weld logs, CCTV.
  • Nonconformance: Log NCRs and corrective actions; trend analysis for recurring issues.
  • Preservation: Cap open pipe ends daily; protect pipes from UV per manufacturer if long storage; avoid dropping or point loading.

Attachments

  • IFC drawings and alignment plans
  • Utility survey and potholing records
  • Temporary Works Design for shoring and approvals
  • Dewatering plan and discharge permit
  • Manufacturer installation guides for uPVC/HDPE systems
  • HDPE fusion procedure, operator certifications, and equipment calibration certificates
  • Material compliance certificates and MSDS (solvent cement/primer, lubricants)
  • Compaction test plans and frequencies
  • EN 1610 leakage test method statement by specialist
  • CCTV survey procedure and sample report format
  • As-built survey templates and coding standards
  • Risk assessments (RAMS), permits (PTD, Confined Space, Hot Work if applicable)

This content is a read-only public reference. Download or customize to get an editable version.

ITP preview

The first inspection activities from the linked ITP for Method Statement: Installation of Underground uPVC/HDPE Gravity Drainage Networks:

ActivityInspection / TestAcceptance CriteriaResponsibilityRecord
Permits and pre-start checksPermit to Dig, TMP, TWD approvalsAll approvals in place and valid; briefings completedPM / HSE / QA-QCApproved permits, TBT records
Materials receipt (pipes, gaskets, cement)Visual, documentation reviewCompliant markings; no damage; valid certs/shelf lifeQA-QCMIR, delivery photos
Survey setting outLevel/line checksWithin stated tolerancesSite Engineer / SurveyorSet-out records

Showing 3 of 17 inspection activities. View full ITP →

Related Inspection and Test Plan

An Inspection and Test Plan (ITP) is available for Method Statement: Installation of Underground uPVC/HDPE Gravity Drainage Networks. The ITP defines the inspection activities, acceptance criteria, hold and witness points, responsible parties, and records required to verify the work described in this method statement.

View the Method Statement: Installation of Underground uPVC/HDPE Gravity Drainage Networks ITP →

Frequently asked questions

A typical trench width is pipe OD plus 300 mm, providing at least 150 mm clearance each side. Verify against project specifications and authority requirements.

Commonly EN 1610 leakage testing (air or water), deflection testing for flexible pipes (e.g., HDPE), compaction testing of backfill, and a post-lay CCTV survey.

Use Class I/II granular bedding per ASTM D2321, typically well-graded sand 0/4 mm or crushed stone 4/10 mm, minimum 100 mm thick, screeded to grade.

Use butt fusion for straight pipe-to-pipe joints where access allows and EF for fittings or confined spaces. Both must follow ISO 21307/ASTM F2620 with calibrated equipment.

Typical targets are ≥95% MDD (ASTM D698) in non-traffic areas and ≥98% MDD (ASTM D1557) beneath pavements. Confirm targets and testing frequency per project specs.

Continue with related Quollnet resources connected to this method statement.

Related resources