G
Guest

Method Statement: Trial Pit Excavation and Utility Exposure Works inspection and test plan example.

Inspection and Test Plan for Method Statement: Trial Pit Excavation and Utility Exposure Works

AI-assisted inspection and test plan connected to a method statement, with PDF and Excel export.

Published 10 Aug 2026 Rev. 00 2 views
About this ITP: This ITP governs inspection and testing for trial pits and utility exposure, from permits and service locating to backfill, reinstatement, and documentation.

More than a static template

Unlike a downloadable Word or PDF template, this ITP is an AI-assisted editable starting point directly connected to its method statement. Every inspection activity, hold point, and acceptance criterion is structured and ready to adapt to your project.

  • AI-assisted customization — Tailor inspection activities and acceptance criteria to your specific project scope.
  • Linked method statement — This ITP is connected to the corresponding method statement describing the work sequence.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review and verify all content against your project specifications and standards before use.

What you can customize

When you save this ITP to your account, every inspection row becomes editable. You can add, remove, or modify:

  • Inspection activity — Description of what is being inspected.
  • Inspection type — Hold point (H), Witness point (W), Review (R), or Monitor (M).
  • Responsibility — Contractor, subcontractor, engineer, or client.
  • Frequency — How often the inspection occurs.
  • Acceptance criteria — Referenced standard or specification requirement.
  • Records — Forms, test reports, or checklists required as evidence.

Why this ITP is used

To verify that trial pits and utility exposures are executed safely and to specification, ensuring accurate utility data for subsequent works.

Who uses this inspection and test plan

Site managers, utility locators, QA/QC engineers, surveyors, HSE officers, and client representatives.

When this ITP is prepared and submitted

Before and during trial pit excavation and until reinstatement and documentation are complete.

Who receives or approves this ITP

Client/Engineer and, where required, utility owners or highway authorities.

Inspection scope

Permits, CAT/GPR scans, set-out, excavation controls, temporary support, exposure verification, survey, backfill compaction, reinstatement, and records.

Typical hold, witness, and review points

Temporary support installation (Hold), surface reinstatement (Witness/Hold as specified), initial excavation near utilities (Witness), final survey (Witness).

Typical inspection records

Permit-to-Dig, scan reports, daily inspections, exposure photos, as-built survey, density test reports, reinstatement checklists, calibration certificates.

Important approval note

This ITP is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all inspection activities, hold points, and acceptance criteria must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

Always verify acceptance criteria against your applicable drawings, specifications, and regulatory requirements. Hold points must be confirmed with the relevant authority before work proceeds past that point.

Inspection and test plan

Activity Inspection / Test Acceptance Criteria Responsibility Record
Permit-to-Dig and pre-start briefing Permit validation; attendance register Valid permits; personnel briefed and signed Site Manager / HSE Permit copy; briefing sheets
Utility records collation and review Records completeness check All utility owners contacted; latest records received Project Manager / Utility Locator Records log; mark-up
On-site CAT/GPR scanning and mark-up Function/bump tests; scan coverage check PAS 128 QL-B achieved where practicable; all services marked Utility Locator Scan report; calibration certs; photos
Setting-out of trial pit Coordinate check vs control Set-out within ±20 mm [Verify] Surveyor Set-out report; photos
Surface cutting/removal Visual; hot work permit if applicable Clean edges; no damage to adjacent structures Crew Lead Daily log; photos
Initial excavation (mechanical within limits) Depth/offset spot checks No mechanical dig within 500 mm lateral/300 mm vertical of suspected services [Verify] Operator / Supervisor Daily log
Hand/vacuum excavation near utilities Visual Utilities exposed without damage; min 300 mm length visible Crew Lead Exposure checklist; photos
Temporary support installation Support inspection sheet Support per TWD; safe access/egress provided TWC/TWD / Supervisor TWC approval; inspection record
Atmospheric testing (if required) Gas readings recorded O2 19.5–23.5%; LEL <10%; H2S/CO within limits [Verify] HSE / Crew Lead Gas test log
Utility identification and survey Measurement check; closure check Survey accuracy ±10–25 mm [Verify]; metadata complete Surveyor / QA As-built points; utility log; photos
Backfill and compaction In-situ density per lot 95% MDD trafficked; 90–93% MDD footways [Verify] QA / Crew Lead Density test results; layer records
Warning tape installation Visual Correct color; 150–300 mm above crown [Verify] Supervisor Photo record
Surface reinstatement Thickness/level/finish checks Layer thickness -5/+10 mm; surface ±10 mm; finish matches QA / Supervisor Reinstatement checklist; tickets
Close-out documentation Document completeness All records submitted and approved Project Manager / QA Handover pack; as-built; ITP; photos

This table is a read-only public reference. Download the PDF or Excel version, or customize this ITP to edit it for your project.

Frequently asked questions

As a typical benchmark, perform at least one in-situ density test per pit or per 10 m³ of backfill, whichever is greater. Verify per project QA plan.

Through the utility scan report showing QL-B coverage, calibration certificates, marked-up plans, and QL-A records when utilities are exposed and surveyed.

The Temporary Works Coordinator/Designer approves the support system at a Hold point before personnel may enter the excavation.

Related method statement

This Inspection and Test Plan is associated with the Method Statement: Trial Pit Excavation and Utility Exposure Works method statement, which describes the step-by-step construction sequence, resources, materials, equipment, safety controls, and environmental controls for this activity.

View the Method Statement: Trial Pit Excavation and Utility Exposure Works method statement →

Continue with related inspection, method statement, article, and checklist resources.

Related resources