Inspection and Test Plan for EPDM Sheet Membrane Waterproofing for Concrete Podiums and Landscaped Plazas
AI-assisted inspection and test plan connected to a method statement, with PDF and Excel export.
More than a static template
Unlike a downloadable Word or PDF template, this ITP is an AI-assisted editable starting point directly connected to its method statement. Every inspection activity, hold point, and acceptance criterion is structured and ready to adapt to your project.
- AI-assisted customization — Tailor inspection activities and acceptance criteria to your specific project scope.
- Linked method statement — This ITP is connected to the corresponding method statement describing the work sequence.
- Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
- Editable starting point, not a final document — Review and verify all content against your project specifications and standards before use.
What you can customize
When you save this ITP to your account, every inspection row becomes editable. You can add, remove, or modify:
- Inspection activity — Description of what is being inspected.
- Inspection type — Hold point (H), Witness point (W), Review (R), or Monitor (M).
- Responsibility — Contractor, subcontractor, engineer, or client.
- Frequency — How often the inspection occurs.
- Acceptance criteria — Referenced standard or specification requirement.
- Records — Forms, test reports, or checklists required as evidence.
Why this ITP is used
It provides evidence that the membrane was installed and tested before it was concealed. It also prevents flooding an unapproved zone or covering unresolved defects.
Who uses this inspection and test plan
The waterproofing installer, Site Engineer, QA/QC team and Engineer/Consultant use it to schedule inspections, record results and release work. Structural and HSE personnel verify the flood-test controls relevant to their roles.
When this ITP is prepared and submitted
Use it before production installation and at each inspection or test stage through final handover.
Who receives or approves this ITP
Submit to the contract-designated Engineer/Consultant or other inspection authority in accordance with the project submittal schedule.
Inspection scope
Material receipt, substrate, full bonding, cold splices, drains, terminations, movement joints, flood testing, pre-cover condition, protection layers, ballast and closeout.
Typical hold, witness, and review points
Hold points include mock-up approval, substrate release, flood readiness and pre-cover release. Witness points include first production splices, concealed details, flood readings and protection checks.
Typical inspection records
Material and batch registers, substrate and weather logs, seam and zone plans, detail photographs, flood and retest reports, inspection releases and closeout documents.
Important approval note
This ITP is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all inspection activities, hold points, and acceptance criteria must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.
Always verify acceptance criteria against your applicable drawings, specifications, and regulatory requirements. Hold points must be confirmed with the relevant authority before work proceeds past that point.
Inspection and test plan
| Activity | Inspection / Test | Acceptance Criteria | Responsibility | Record |
|---|---|---|---|---|
| Readiness and representative mock-up | Review approvals, design interfaces and flood load authorization. Witness trial installation and specified adhesion and seam checks. | Approved drawings, materials, ITP, trial details and test criteria available; discrepancies closed. | Site Engineer and QA/QC submit; Engineer/Consultant releases. | Approved submittals, trial checklist and hold release |
| Material receipt and storage | Check model, thickness or type, certificate, lot, expiry, condition and storage conditions. | Matches approved system and submittals; in-date, undamaged and stored in supplier-specified conditions. | Storekeeper and QA/QC; Engineer/Consultant as specified. | Material inspection request and batch register |
| Prepared concrete and built-in interfaces | Check falls, drain levels, cracks, repairs, surface condition and profile; measure substrate moisture by approved method; verify cast-in interfaces. | Approved levels, surface limits, cure and moisture met; all design dispositions closed; no loose material, standing water or bond breakers. | Surveyor, Waterproofing Supervisor and QA/QC inspect; Engineer/Consultant releases. | Substrate acceptance, survey and moisture log |
| Membrane bonding and cold-applied seams | Check weather, coverage and application timing; visually inspect each sheet and full accessible seam length; measure laps and perform approved checks. | Application within approved limits; measured overlaps and seam geometry comply; no open seams, wrinkles affecting integrity, foreign matter or unapproved bond voids. | Installer performs; QA/QC inspects; Engineer/Consultant witnesses designated work. | Daily application log, seam map and approved trial or test results |
| Drains, penetrations, upstands and expansion joints | Inspect each detail. Measure joint gap and termination elevations, check fixing and overlaps, and verify drain weeps and movement allowances. | Approved details complete and continuous, with correct fixing, clamping, splice geometry and free movement; no blocked drainage or rigid bridging. | Waterproofing Supervisor and QA/QC inspect; Engineer/Consultant witnesses. | Details checklist, joint log, photographs and torque record where applicable |
| Pre-flood readiness | Review cure and defect closure, inspect test closures and gauges, confirm structural approval, maximum water elevation, overflow route, monitoring and baseline condition below. | Membrane complete and cured; signed load and test approvals; safe containment and drawdown arrangements verified. | Site Engineer, HSE and QA/QC verify; Engineer/Consultant releases. | Flood-test permit and pre-flood inspection release |
| Flood test and retest | Measure water elevations and dwell per approved plan; inspect accessible underside and perimeters; account for rainfall, evaporation and any plug or dam leakage. | Approved depth, coverage and dwell achieved within structural limits. No leakage, test-related dampness or unexplained water-level change beyond approved allowance. Invalid or failed tests repeated after corrective action. | Test attendant monitors; QA/QC records; Engineer/Consultant witnesses. | Signed test report, water-level and weather log, photographs and retest report if required |
| Pre-cover release | Verify accepted integrity test, remove temporary closures, reinspect exposed membrane and drains, and check that repairs were retested. | Accepted test and written release; membrane undamaged and drains clear; all relevant nonconformances closed. | QA/QC submits; Engineer/Consultant releases. | Pre-cover release and marked-up zone plan |
| Protection, drainage and ballast | Inspect layer sequence and overlaps, drain paths and access, root barrier where specified, ballast grading and depth, and stockpile and traffic controls. | Installed build-up matches approved details and levels; no displacement, blockage, puncture or unauthorized loads. | Waterproofing and Landscape Supervisors install; QA/QC inspects; Engineer/Consultant witnesses. | Layer inspections, delivery checks, ballast depth survey and photos |
| Final handover | Walk down accessible interfaces and review inspection, test, repair, warranty and as-built documentation. | All zones released; outstanding defects closed; drain access and maintenance restrictions communicated; dossier accepted. | Construction Manager and QA/QC submit; Engineer/Consultant releases. | Final inspection and handover certificate |
This table is a read-only public reference. Download the PDF or Excel version, or customize this ITP to edit it for your project.
Frequently asked questions
Related method statement
This Inspection and Test Plan is associated with the EPDM Sheet Membrane Waterproofing for Concrete Podiums and Landscaped Plazas method statement, which describes the step-by-step construction sequence, resources, materials, equipment, safety controls, and environmental controls for this activity.
View the EPDM Sheet Membrane Waterproofing for Concrete Podiums and Landscaped Plazas method statement →Continue with related inspection, method statement, article, and checklist resources.