Method Statement – Security Command Centre Fit-Out and Commissioning – Method Statement
Method Statement – Security Command Centre Fit-Out and Commissioning method statement and inspection test plan example.

Method Statement – Security Command Centre Fit-Out and Commissioning – Method Statement

AI-assisted method statement with matching ITP, PDF download, and Excel export.

Published 22 Oct 2026 Rev. 00 82 views 26 downloads
About this method statement: This method statement details the end-to-end fit-out of a security command centre. It covers video wall assembly, consoles, racks, cabling, UPS, lighting, HVAC interface, testing, calibration, and final commissioning.

More than a static template

Unlike a downloadable Word or PDF template, this method statement is an AI-assisted editable starting point connected directly to a matching Inspection and Test Plan. Every section is structured, project-adaptable, and ready to export.

  • AI-assisted drafting — Customize every section with AI for your specific project scope.
  • Linked ITP — A matching inspection and test plan is generated alongside the method statement.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review, verify, and adjust all content against your project requirements before use.

Static template vs. Quollnet workflow

FeatureStatic templateQuollnet
Project-specific contentManual fill-in requiredAI-assisted customization
Linked ITPSeparate document, no linkMatching ITP included
Export formatsUsually PDF onlyPDF and Excel
Structured sectionsFree-form layout13 standardized sections
Saved to your accountLocal file onlyCloud-saved, reusable
Content accuracyYou verify everythingAI-assisted, you still verify
CostOften free but time-intensiveFree to customize and download

What you can customize

When you save this method statement to your account, every section becomes editable. The following 13 sections are included:

  • Scope — Defines the activity and its boundaries.
  • References — Standards, specifications, and drawings.
  • Responsibilities — Roles and accountabilities.
  • Resources — Labour, plant, and equipment summary.
  • Materials — Materials and compliance requirements.
  • Equipment — Tools and equipment details.
  • Prerequisites — Hold points and pre-conditions.
  • Method sequence — Step-by-step construction sequence.
  • Safety controls — HSE risk controls and PPE.
  • Environmental controls — Environmental mitigation measures.
  • QA/QC — Quality inspection and test requirements.
  • ITP — Inspection and Test Plan table (has its own page).
  • Attachments — Referenced drawings and documentation.

Why this method statement is used

This method statement is used to define and communicate the approved procedure for carrying out method statement – security command centre fit-out and commissioning on site. It ensures the work is planned in advance, the correct resources and controls are in place, and all personnel understand responsibilities, sequence, quality requirements, and safety controls before work begins. It aligns site execution with the documented scope and acceptance expectations.

Who uses this method statement

This method statement is used by contractors, site supervisors, project engineers, QA/QC engineers, HSE officers, consultants, and client representatives. It serves as a shared reference for planning, execution, supervision, inspection, and approval of the activity on site.

When it is prepared and submitted

The method statement is prepared before the work activity starts and submitted as part of the pre-construction documentation package for review and approval.

Who reviews or approves it

The method statement is usually submitted to the client representative, consultant, resident engineer, or project management consultant for review and approval before the work commences.

Important approval note

This method statement is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all content must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

For example: if your specification requires a departure from a referenced standard, that departure must be documented and approved separately — this method statement will not capture that automatically. Always verify against your applicable drawings, specifications, and regulatory requirements.

Method statement content

Scope

Overview

This Method Statement covers the end-to-end fit-out and commissioning of a Security Command Centre (SCC), including:
- Structural mounting and alignment of a modular video wall.
- Installation of operator console furniture and ergonomic adjustments.
- Equipment rack installation, power distribution units (PDUs), bonding/earthing.
- Cable containment and management (trays/ladder/underfloor raceways), cable pulling and terminations for power, structured cabling, AV, interconnects, and control.
- UPS installation and integration, including autonomy and transfer testing.
- Interface with environmental conditioning (HVAC/BMS) and control room lighting (ergonomic, low-glare, dimmable).
- Integration with structured cabling and AV systems.
- Verification of operator sightlines and ergonomics.
- Display calibration, audio and control integration, system endurance tests, and final commissioning.

Exclusions

  • Base building civil works and major MEP infrastructure outside the room boundary.
  • Core network/servers beyond demarcation points.
  • Fire alarm system installation (except interface and coordination for penetrations and device relocations as needed).

Constraints and Assumptions

  • Room is weather-tight and access-controlled.
  • Permanent electrical supply available and pre-tested up to SCC DBs/UPS input.
  • All architectural finishes substantially complete with low-reflectance coatings at video wall backdrop [Verify per project specifications].
  • All manufacturer installation manuals and shop drawings approved prior to works.

References

Document TypeReference / NumberRevisionNotes
Standard ISO 11064 (all parts) – Ergonomics of control centres Layout, workstation design, environmental, displays, and evaluation.
Standard IEC 60364 – Low-voltage electrical installations (or NFPA 70/BS 7671 as applicable) [Verify per project] Wiring, protection, earthing/bonding.
Standard IEC 62040 – UPS systems UPS safety, performance, testing.
Standard ISO/IEC 11801 & ISO/IEC 14763-2/-3; TIA-568, TIA-569 Structured cabling performance, installation, pathways, testing (copper/fiber).
Standard EIA-310 – Rack equipment mounting Rack dimensions and mounting.
Standard EN 12464-1 / IES standards – Lighting of indoor work places Illuminance, UGR, uniformity, glare control.
Standard ASHRAE (e.g., 55 for thermal comfort); Acoustic NR/NC criteria Thermal comfort and background noise criteria for control rooms.
Standard IEC 61000 (EMC), IEC 60529 (IP ratings) EMC compatibility and enclosure ingress ratings.
Standard EN 1366-3 / UL systems – Fire-stopping of service penetrations Penetration seals and certification.
Guideline SMPTE/ITU-R BT.709 – Display/colorimetry; Manufacturer calibration specs Video wall calibration targets (gamma, white point, luminance).
Standard ISO 9241-307 – Electronic visual display requirements (pixel defects) Display pixel fault classes and inspection.

Responsibilities

RoleResponsibilityName / Party
PM Project Manager Main Contractor
CM Site Manager / Construction Manager Main Contractor
MEP Supv. MEP Supervisor Main Contractor
AV Lead AV Lead Engineer Specialist Subcontractor
Cabling Lead Structured Cabling Lead Specialist Subcontractor
Cx Manager Commissioning Manager Main Contractor
HSE HSE Manager / Officer Main Contractor
QA/QC Quality Engineer Main Contractor
Client/Engineer Client/Engineer Representative Employer

Resources

Resource TypeDescriptionQuantityRemarks
Personnel 1
Personnel 1
Personnel 1
Personnel 1
Personnel 2–4 [Verify] Adjust to project scale
Personnel 3–6 Based on video wall size
Personnel 2–4 [Verify]

Materials

MaterialSpecification / GradeQuantityRemarks
Video wall displays Resolution, pixel pitch, brightness ≥500 cd/m² [Verify] As per layout ISO 9241-307 pixel class per spec
Operator console furniture ISO 11064-3 compliant; sit-stand 650–1250 mm [Verify] As per layout
Equipment racks Static load rating ≥1000 kg [Verify] e.g., 42U x 600/800W [Verify]
Mounting anchors/fasteners M10–M12 rated per design; torque per datasheet [Verify] As calculated
Copper data cables Cat6A F/UTP or S/FTP, Class EA to ISO/IEC 11801 As per BoQ
Fiber optic cables OM4/OS2 with LC connectors; IEC 61754 As per BoQ
UPS with batteries IEC 62040; autonomy per load (e.g., 15–30 min) [Verify] As per design
Ergonomic lighting fixtures EN 12464-1 compliant; UGR ≤19; CRI ≥80; 3000–4000K As per layout
Earthing/bonding bars and straps IEC 60364-5-54; green/yellow 16–25 mm² [Verify] As required

Equipment

EquipmentCapacity / TypeQuantityInspection Required
Vacuum lifter for displays ≥100 kg 1
Laser level 1
Torque wrench 5–100 Nm 2
Cable certifier e.g., Fluke DSX-8000 or equivalent 1
OTDR + light source/power meter 1
Colorimeter/spectroradiometer ΔE and cd/m² capable 1
Lux meter + UGR assessment tool 1
Micro-ohmmeter/continuity tester 0–2 Ω 1
Thermal imaging camera 1
MEWP/step-up platform 1

Prerequisites

  • Approved shop drawings, coordination drawings, and method statement/ITP.
  • Verified room dimensions, substrate strength (concrete/steel wall) and as-built services scan (GPR/ferroscan as applicable) for mounting and cable routes.
  • Permanent power available up to SCC DB/UPS input. Earth system tested and available.
  • HVAC operational or temporary conditioning to maintain 20–24°C and 40–60% RH during installation and calibration [Verify per project specifications].
  • Access/permits: Working at Height (WAH), Electrical Isolation/LOTO, Hot Works (if coring required), and delivery permits.
  • Manufacturer installation manuals and lifting/handling instructions for video wall and UPS.
  • Tools and test equipment with valid calibration certificates.
  • Fire-stopping system approvals for planned penetrations.
  • Room finishes: low-gloss paint behind video wall (low reflectance), glare control measures, acoustic finishes where specified.
  • Pre-commissioning checklists prepared and approved.

Method Sequence

StepActivityDescriptionResponsibilityInspection / Hold Point
1 Site handover and verification Joint inspection of room, verification of access, substrate condition, services locations, and dimensional checks against approved drawings. CM / AV Lead / MEP Supv. Inspection Request (IR) with photos and dimension log
2 Material receipt and storage Offload using pallet jack/vacuum lifter; store displays vertically in crate; UPS/batteries stored per MSDS; humidity/temperature-controlled area. CM / Storekeeper Delivery inspection
3 Set-out and marking Mark video wall datum lines, console positions, racks, and containment runs using laser level. Confirm sightline geometry with operator eye positions. AV Lead / QA/QC Hold point for set-out verification
4 Install cable containment Install trays/ladder/underfloor ducts and grommets. Provide fire-stopping sleeves where required. Maintain separation between power and data (≥150 mm or divider) [Verify]. MEP Supv. IR for containment
5 Racks installation and bonding Position racks per layout; anchor to floor if required; install rack earth bar and bond to main earth with labeled strap. MEP Supv. IR for rack placement
6 Video wall support/mount frame Install mounting rails/frames and anchors as per manufacturer. Torque anchors to spec; verify substrate capacity. AV Lead Hold point for anchor inspection
7 Power rough-in and PDUs Pull dedicated radial circuits to racks and video wall; install PDUs/RCBOs; identify circuits; ensure segregation from signal cables. MEP Supv. IR + testing
8 UPS installation Place UPS and batteries; install input/output/bypass cabling; earthing; ventilation clearance maintained; firmware updates as required. MEP Supv. / UPS Vendor Vendor start-up witness
9 Structured cabling and AV cabling Pull copper/fiber and AV signal cables via containment. Respect bend radius (Cu ≥4×OD; Fiber ≥10×OD static) and maximum pulls. Cabling Lead / AV Lead Progress inspections
10 Terminations and labeling Terminate copper to keystones/patch panels; fiber to LC with proper polish/cleaning; apply permanent labels per scheme. Cabling Lead IR for terminations
11 Cable testing and certification Test copper (Permanent Link) and fiber (LSPM + OTDR). Record results and remediate failures. Cabling Lead / QA/QC Witness testing
12 Lighting installation and aiming Install ergonomic, dimmable lighting; set scenes to minimize screen glare; integrate with control if specified. MEP Supv. / Lighting Vendor IR + measurement
13 Console furniture installation Assemble consoles; verify sit-stand operation and clearances; route cables via raceways; install task lighting/monitor arms. AV Lead / Furniture Vendor IR
14 Video wall panel mounting Mount panels using OEM micro-adjust mounts; align for planar flatness and seam uniformity. AV Lead Hold point pre-power
15 Display calibration Warm-up displays; calibrate luminance, white point (D65), gamma; verify uniformity and color difference. AV Lead / QA/QC Witness calibration
16 Sightline and ergonomics verification Check operator eye-level vs display heights; verify viewing angles, character height/legibility; adjust mounts/console positions as needed. AV Lead / Ergonomist / Client Rep Witness check
17 Systems integration Patch and configure AV, control processors, KVM, CCTV decoders, network, and audio. Implement presets and failover logic. AV Lead / IT Functional tests
18 UPS and power quality tests Perform load/battery autonomy test and transfer to/from bypass; verify THD and thermal conditions in racks. UPS Vendor / MEP Supv. / QA/QC Witness
19 Environmental conditioning interface Verify HVAC capacity, airflow, temperature and RH stability; check BMS/alarm interfaces. MEP Supv. / Cx Manager Measurement
20 Endurance and failover testing Run continuous operation with typical sources; simulate failures (source/server link/UPS events) and verify recovery. Cx Manager / AV Lead / Client Rep SAT
21 Training and handover Provide operator and maintenance training; submit O&M manuals, as-builts, warranties; snag rectification. PM / AV Lead / MEP Supv. Handover meeting

Health, Safety, and Environment (HSE) – Safety Controls

Task-specific hazards and controls

1) Manual handling of displays/UPS
- Hazard: Musculoskeletal injury, crush/pinch.
- Consequence: Strains, fractures, dropped loads.
- Engineering/procedural control: Use vacuum lifters, trolleys; team lifts with clear commands; weight/CoG known; keep in crates until at install point.
- Required PPE: Safety shoes, cut-resistant gloves, back support as needed.
- Collective measure: Exclusion zone during lifts; banksman in place.
- Inspection/permit: Pre-use lifting equipment inspection; lifting plan/toolbox talk.

2) Working at height (video wall mounting/aiming)
- Hazard: Falls from step-ups/MEWP.
- Consequence: Serious injury/fatality.
- Control: Use suitable podium steps/MEWP with guardrails; maintain 3-point contact; do not overreach; secure tools with lanyards.
- PPE: Harness with lanyard if required by MEWP; hard hat with chin strap.
- Collective: Barricade work area; spotter.
- Inspection/permit: WAH permit; MEWP inspection tag; operator license [Verify per project HSE plan and local regulations].

3) Electrical works and UPS energization
- Hazard: Electric shock/arc flash.
- Consequence: Burns, cardiac arrest, fire.
- Control: LOTO; prove dead before work; use insulated tools; fit covers; vendor start-up for UPS; maintain creepage/clearances.
- PPE: Arc-rated clothing as required, insulated gloves, face shield for live testing within permitted scope.
- Collective: Barriers and signage during energization; dedicated test window.
- Inspection/permit: Electrical permit to work; calibrated test meters.

4) Anchor drilling into walls/floors
- Hazard: Striking concealed services; flying debris; silica dust.
- Consequence: Electrocution, flooding, eye injury, respiratory harm.
- Control: Services scan and permit; use drilling jigs with dust extraction; vacuum class M/H; stop if unexpected voids.
- PPE: Safety glasses, hearing protection, FFP2/3 mask.
- Collective: Spotter monitoring scan map; barriers.
- Inspection/permit: Penetration permit; anchor torque recorded; sample pull-tests witnessed.

5) Trip hazards from cabling and packaging
- Hazard: Slips/trips.
- Consequence: Minor to serious injury.
- Control: Maintain tidy work fronts; cable mats/ramps; immediate waste removal.
- PPE: Safety footwear.
- Collective: Clear walkways marked; daily 5S checks.
- Inspection/permit: Housekeeping inspections.

6) Battery handling (UPS)
- Hazard: Chemical exposure/thermal runaway.
- Consequence: Burns, fumes, fire.
- Control: OEM crates; no smoking/ignition sources; MSDS available; spill kit; trained personnel only.
- PPE: Chemical-resistant gloves, goggles, apron for electrolyte risks (VRLA minimal but consider).
- Collective: Ventilated area; emergency eyewash where required.
- Inspection/permit: Vendor supervision; COSHH assessment [Verify per project].

7) Noise and vibration from tools
- Hazard: Hearing damage.
- Consequence: Temporary/permanent hearing loss.
- Control: Low-noise tools; limit exposure time per HAVS policy.
- PPE: Hearing protection.
- Collective: Schedule noisy tasks off-hours.
- Inspection/permit: Noise monitoring if required.

8) Fire risk from hot works (if coring/cutting required)
- Hazard: Sparks/ignition of finishes.
- Consequence: Fire/smoke damage.
- Control: Hot work permit; fire watch; cover combustibles; extinguishers on hand.
- PPE: Flame-resistant gloves, goggles.
- Collective: Isolation of detectors or covers with approval.
- Inspection/permit: Hot work permit and fire watch logs.

Environmental Controls

  • Waste electrical and electronic equipment (WEEE): Segregate displays, electronics, cabling offcuts, and batteries. Use licensed recyclers; retain transfer notes.
  • Packaging waste: Returnable crates where possible; recycle cardboard/plastics; avoid polystyrene where feasible.
  • Dust control: Use on-tool extraction and HEPA vacuums; damp wipe displays and consoles; protect HVAC intakes.
  • Noise management: Limit drilling to permitted hours; use low-noise anchors; provide notice to occupants.
  • Energy management: Use temporary LED task lighting; switch off equipment when not in use; enable display eco-modes post-calibration as allowed.
  • Spill prevention: Secondary containment for batteries/UPS fluids; spill kits available; immediate cleanup and reporting.
  • VOCs and air quality: Select low-VOC adhesives/paints; allow off-gassing before commissioning.
  • Environmental monitoring: Log temperature/RH during calibration and endurance tests.
    [Verify per project HSE plan and local regulations]

QA/QC Requirements

Controls and Records

  • Submittals: OEM datasheets, shop drawings, wiring schematics, lighting calculations, anchor design, UPS method, test equipment calibration certificates.
  • Inspections: IRs at each stage; hold/witness points for set-out, anchors, video wall alignment, calibration, UPS start-up, endurance test.
  • Testing frequencies: 100% test of copper/fiber links; 100% display calibration; sample anchor pull-out tests (≥10% or min 3 per wall) [Verify per project specifications].
  • Labeling: Per ISO/IEC 14763-2 scheme; heat-shrink or printed labels at both ends; racks and PDUs uniquely identified.
  • Tolerances:
  • Containment level ±5 mm/5 m; support spacing ≤1.5 m [Verify].
  • Rack verticality ±2 mm/2 m; bonding ≤0.1 Ω to earth bar.
  • Video wall flatness ±2 mm across array; seam uniformity ±0.3 mm [Verify].
  • Lighting: 300–500 lux task; UGR ≤19; uniformity ≥0.6 [Verify per EN 12464-1].
  • HVAC: 20–24°C; RH 40–60%; background noise NR/NC 30–35.
  • Power tests per IEC 60364: continuity, insulation resistance (≥1 MΩ @ 500 VDC), polarity, EFLI, RCD trip tests where applicable.
  • UPS tests per IEC 62040: autonomy test at 25–50% load; transfer to/from bypass; alarms/remote monitoring.
  • Calibration: Target D65 6500K ±200K; gamma 2.2±0.1; luminance 120–160 cd/m² ±10%; ΔEavg ≤2 (max ≤3); uniformity ≤10%; pixel defects within ISO 9241-307 class as specified.
  • Sightlines: Vertical ≤35°, horizontal ≤30°; minimum character height ≥ viewing distance/200; optimal viewing distance ≈ 1.2–2.5 × pixel pitch(mm) [Verify per OEM].
  • Fire-stopping: Tested systems (EN 1366-3/UL); ID tags and as-builts recorded.
  • Documentation: Certification reports (PDF + native files), calibration files, UPS logs, lighting survey, environmental logs, O&M manuals, warranties.

Attachments

  • Approved shop drawings and coordination drawings (latest revision).
  • Manufacturer installation manuals for video wall, mounts, racks, UPS, lighting.
  • Lifting plan and WAH permits; electrical PTW/LOTO forms.
  • Cable schedules and labeling scheme.
  • Test equipment calibration certificates.
  • Anchor design calculations and product ETA/ICC approvals.
  • Fire-stopping system datasheets and approvals.
  • Pre-commissioning checklists; IR templates.
  • O&M manuals, spare parts lists, and warranties.
  • Training materials and user guides.

This content is a read-only public reference. Download or customize to get an editable version.

ITP preview

The first inspection activities from the linked ITP for Method Statement – Security Command Centre Fit-Out and Commissioning:

ActivityInspection / TestAcceptance CriteriaResponsibilityRecord
Room and substrate verificationDimensions, substrate integrity, services scan reviewRoom dims within tolerance; substrate sound; no clashes with servicesCM / QA-QCIR, survey report
Containment installationSupport spacing, level, bondingSpacing ≤1.2–1.5 m [Verify]; level ±5 mm/5 m; bonding ≤0.1 ΩMEP Supv. / QA-QCIR, continuity record
Rack installation & bondingPlumb and bonding testVerticality ±2 mm/2 m; bonding ≤0.1 Ω to earthMEP Supv. / QA-QCIR, bonding test

Showing 3 of 18 inspection activities. View full ITP →

Related Inspection and Test Plan

An Inspection and Test Plan (ITP) is available for Method Statement – Security Command Centre Fit-Out and Commissioning. The ITP defines the inspection activities, acceptance criteria, hold and witness points, responsible parties, and records required to verify the work described in this method statement.

View the Method Statement – Security Command Centre Fit-Out and Commissioning ITP →

Frequently asked questions

ISO 11064 (all parts) provides requirements for layout, workstations, displays, environment, and evaluation of control rooms.

Typical targets are luminance 120–160 cd/m², D65 white point (6500K ±200K), gamma 2.2±0.1, color ΔEavg ≤2 (max ≤3), and screen uniformity ≤10% [Verify per manufacturer].

Copper is certified to Class EA (ISO/IEC 11801) using a field certifier; fiber is tested using LSPM and OTDR for insertion loss and reflectance per ISO/IEC 14763-3.

Vendor-supervised start-up, battery autonomy tests at 25–50% load, and transfer to/from bypass with no unintended interruption, per IEC 62040.

By checking that all critical content is within vertical viewing angles ≤35°, horizontal ≤30°, and that character height is at least the viewing distance divided by 200, per ISO 11064 guidance.