Method Statement: Integrated Testing of Generator, Automatic Transfer Switch (ATS), and Essential Loads inspection and test plan example.

Inspection and Test Plan for Method Statement: Integrated Testing of Generator, Automatic Transfer Switch (ATS), and Essential Loads

AI-assisted inspection and test plan connected to a method statement, with PDF and Excel export.

Published 19 Nov 2026 Rev. 00 6 views
About this ITP: This ITP defines activities, tests, acceptance criteria, and witness/hold points for integrated testing of generator, ATS, and essential load systems.

More than a static template

Unlike a downloadable Word or PDF template, this ITP is an AI-assisted editable starting point directly connected to its method statement. Every inspection activity, hold point, and acceptance criterion is structured and ready to adapt to your project.

  • AI-assisted customization — Tailor inspection activities and acceptance criteria to your specific project scope.
  • Linked method statement — This ITP is connected to the corresponding method statement describing the work sequence.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review and verify all content against your project specifications and standards before use.

What you can customize

When you save this ITP to your account, every inspection row becomes editable. You can add, remove, or modify:

  • Inspection activity — Description of what is being inspected.
  • Inspection type — Hold point (H), Witness point (W), Review (R), or Monitor (M).
  • Responsibility — Contractor, subcontractor, engineer, or client.
  • Frequency — How often the inspection occurs.
  • Acceptance criteria — Referenced standard or specification requirement.
  • Records — Forms, test reports, or checklists required as evidence.

Why this ITP is used

To control and verify that generator and ATS systems meet functional and performance requirements under simulated mains failure and retransfer.

Who uses this inspection and test plan

Commissioning manager, test engineers, OEM reps, consultant/client witnesses, and HSE officers.

When this ITP is prepared and submitted

After installation and pre-commissioning checks are complete, before system handover and occupancy.

Who receives or approves this ITP

Engineer/Consultant and Client for witnessing and approval.

Inspection scope

Document reviews, site readiness, ATS/generator functional tests, load step and sustained run tests, alarms/shutdowns, retransfer, and documentation.

Typical hold, witness, and review points

Mains failure simulation, ATS transfer, 50%/100% step-loads, alarms/shutdowns, and final acceptance sign-off.

Typical inspection records

PTW, checklists, PQA data, timing logs, IR images, alarm matrix results, witness sign-off, final report.

Important approval note

This ITP is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all inspection activities, hold points, and acceptance criteria must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

Always verify acceptance criteria against your applicable drawings, specifications, and regulatory requirements. Hold points must be confirmed with the relevant authority before work proceeds past that point.

Inspection and test plan

Activity Inspection / Test Acceptance Criteria Responsibility Record
Pre-test documentation review Check approvals, SLDs, protection settings, risk assessment, PTW, OEM attendance. All documents approved; permits in place; instruments calibrated. CxM / Engineer Inspection checklist, approvals
Site readiness inspection Area cordoned, signage, ventilation, extinguishers, spill kits, egress routes. Safe work area confirmed. CxM / HSE HSE inspection form
Instrumentation setup verification PQA connections, scaling, time sync; IR camera setup. Correct and stable readings; event capture enabled. Lead Test Engineer PQA setup record
Generator pre-functional checks Fluids, leaks, battery/charger, heaters, ventilation, earthing, breaker interlocks. All within OEM limits; no leaks; interlocks working. Generator OEM Pre-functional checklist
ATS functional (no-load) Control logic, sensing, permissives, indication/BMS points. All functions correct; no spurious transfers. ATS OEM ATS function sheet
Mains failure simulation (HOLD) Open upstream breaker or disable sensing per plan; confirm start signal. Start signal issued per delay; no unsafe conditions. Authorized Person / Witness Switching record, event log
Generator start and stabilization Crank time, speed ramp, voltage/frequency stabilization. As per OEM/NFPA 110 Type; ready-to-load confirmed. Generator OEM / Test Eng. Startup log, PQA
ATS transfer to generator (WITNESS) Transfer timing; open vs closed transition behavior; inrush/overlap. Transfer within project limits; overlap ≤100 ms for closed-transition. ATS OEM / Engineer Timing record, PQA
Initial load pickup transients Record frequency/voltage dip and recovery. Dip/recovery within ISO 8528-5 class specified. [Verify] Test Eng. PQA plot
Step-load testing 25–100% (WITNESS at 50% and 100%) Increase load in steps; hold each ≥10 min; monitor temps and PQ. Stable operation; no trips; THD-V ≤15%; temps within OEM. Generator OEM / Engineer Step-load logs, IR report
Sustained full-load run Run ≥60 min at ~100% kW; thermography. No abnormal alarms; no hotspots above limits. Generator OEM / Test Eng. Runtime log, IR images
Load rejection test Open generator breaker from high load; observe overspeed/voltage excursion. Within OEM limits; safe recovery. Authorized Person / OEM PQA/event log
Alarms and shutdowns (WITNESS) Trigger key alarms/trips incl. E-stop, overcrank, low oil, high temp, UV/UF. Correct annunciation/action per matrix. Test Eng. / Engineer Alarm matrix record
Ancillary systems and BMS/SCADA I/O Fuel transfer/day-tank, ventilation interlocks, fire alarm interfaces, monitoring points. All I/O correct; interlocks operational. MEP Leads / BMS Eng. I/O test sheets
Return to normal supply (retransfer) Restore utility; verify retransfer delay, cooldown, stop. Per programmed logic; no parallel unless designed. ATS OEM / Engineer Timing log, PQA
Bypass-isolation ATS operation Transfer to bypass and back; interlocks and indications. No backfeed; safe operation. ATS OEM / Test Eng. Bypass checklist
Final documentation and sign-off (HOLD) Review results, deviations, and corrective actions; capture signatures. All acceptance met or approved deviations closed. CxM / Engineer / Client Commissioning report with signatures

This table is a read-only public reference. Download the PDF or Excel version, or customize this ITP to edit it for your project.

Frequently asked questions

Typically G2 or G3 per ISO 8528-5, defining acceptable transient dips and recovery times. Confirm with project specifications.

The Authorized Person (Electrical) executes switching per an approved PTW and switching schedule, with Consultant/Client witnessing at hold points.

Through signed ITP records, PQA plots, timing charts, IR reports, and a consolidated commissioning report with as-commissioned settings.

Related method statement

This Inspection and Test Plan is associated with the Method Statement: Integrated Testing of Generator, Automatic Transfer Switch (ATS), and Essential Loads method statement, which describes the step-by-step construction sequence, resources, materials, equipment, safety controls, and environmental controls for this activity.

View the Method Statement: Integrated Testing of Generator, Automatic Transfer Switch (ATS), and Essential Loads method statement →