Method Statement: Installation of Rubber Fender System on Quay Wall (with Underwater Bolt Tightening, QA/QC, and Final Contact Test) inspection and test plan example.

Inspection and Test Plan for Method Statement: Installation of Rubber Fender System on Quay Wall (with Underwater Bolt Tightening, QA/QC, and Final Contact Test)

AI-assisted inspection and test plan connected to a method statement, with PDF and Excel export.

Published 29 Oct 2026 Rev. 00 3 views
About this ITP: Defines inspections, hold/witness points, acceptance criteria, and records for fender installation on a quay wall including diving and final contact test.

More than a static template

Unlike a downloadable Word or PDF template, this ITP is an AI-assisted editable starting point directly connected to its method statement. Every inspection activity, hold point, and acceptance criterion is structured and ready to adapt to your project.

  • AI-assisted customization — Tailor inspection activities and acceptance criteria to your specific project scope.
  • Linked method statement — This ITP is connected to the corresponding method statement describing the work sequence.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review and verify all content against your project specifications and standards before use.

What you can customize

When you save this ITP to your account, every inspection row becomes editable. You can add, remove, or modify:

  • Inspection activity — Description of what is being inspected.
  • Inspection type — Hold point (H), Witness point (W), Review (R), or Monitor (M).
  • Responsibility — Contractor, subcontractor, engineer, or client.
  • Frequency — How often the inspection occurs.
  • Acceptance criteria — Referenced standard or specification requirement.
  • Records — Forms, test reports, or checklists required as evidence.

Why this ITP is used

To ensure that installation quality and performance meet design intent and standards, with verifiable records for acceptance.

Who uses this inspection and test plan

Contractor QA/QC, Site Engineer, Diving Supervisor, Client/Engineer, and Vendor Representative.

When this ITP is prepared and submitted

From material receipt through installation, testing, and final acceptance of the fender system.

Who receives or approves this ITP

Client/Engineer and Port Authority as required.

Inspection scope

Covers materials, dimensional checks, anchor installation and testing, underwater torqueing, coatings, and performance testing.

Typical hold, witness, and review points

Hold: Anchor proof/pull-out, first-unit underwater torque, fender contact test. Witness: Set-out, fit-up, final inspection.

Typical inspection records

Material IRs, DFT logs, anchor test reports, torque logs, dive videos, load cell certificates, contact test report, as-builts.

Important approval note

This ITP is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all inspection activities, hold points, and acceptance criteria must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

Always verify acceptance criteria against your applicable drawings, specifications, and regulatory requirements. Hold points must be confirmed with the relevant authority before work proceeds past that point.

Inspection and test plan

Activity Inspection / Test Acceptance Criteria Responsibility Record
Material receiving inspection Visual, DFT spot checks, certificate verification (EN 10204 3.1) No damage/corrosion; coating within TDS; documentation complete. Contractor QA/QC, Engineer (surveillance) Material IR, photos, DFT log
Survey set-out verification Dimensional survey Within ±10 mm (H), ±5 mm (V) [Verify]. Surveyor/QA-QC, Engineer (witness) Survey report, redlines
Concrete strength confirmation Review test reports/cores/Schmidt [Verify] f'c ≥ 30 MPa [Verify]. Contractor QA/QC, Engineer (hold if required) Test report, IR
Hole drilling and preparation (if post-installed) Diameter/depth gauge; cleanliness check (brush–blow–brush) Dia per system; depth ±5 mm; hole dry/clean per TDS. Contractor QA/QC (witness) Drilling checklist
Anchor installation and curing Embedment/projection measurement; cure time vs temp Projection ±3 mm; cure complete before loading. Contractor QA/QC, Engineer (hold pre-load) Anchor log, IR
Anchor proof/pull-out test ASTM E488/BS 8539 method using calibrated rig Proof load ≥ 0.5× design tensile [Verify]; stable displacement (<1 mm residual). QA/QC, Engineer (hold) Test report, gauge certs
Fender/panel alignment and fit-up Level/plumb/offset measurements Within specified tolerances; correct orientation. Contractor QA/QC, Engineer (witness) Fit-up checklist, photos
Underwater bolt torque – initial Hydraulic torque wrench reading; cross-pattern tightening Specified torque achieved within +0/−10% first pass; threads intact; no stud rotation. Diving Supervisor/QA-QC, Engineer (witness/hold for first unit) Torque log, dive video
Torque verification – final/re-torque Breakaway torque on ≥10% fasteners after 24–48 h [Verify] Breakaway ≥0.8× specified torque [Verify]. QA/QC (contractor) Torque verification log
Coating touch-up inspection DFT measurement; holiday detection if specified Within system DFT; free of defects; color/finish acceptable. QA/QC, Engineer (surveillance) DFT log, IR
Fender contact test Controlled horizontal load with calibrated load cell; measure contact footprint/deflection Contact width ≥90% of panel width; reaction within ±10% of predicted at agreed test load; no abnormal movement. Contractor/QA-QC, Engineer (hold), Vendor Rep (advisory) Contact test report, load cell certs, photos/video
Final inspection and documentation Document completeness check All hold points closed; as-builts submitted; punch list cleared. Contractor QA/QC, Engineer (witness) Handover dossier

This table is a read-only public reference. Download the PDF or Excel version, or customize this ITP to edit it for your project.

Frequently asked questions

Applying the agreed proof load without continuous displacement and with residual movement within tolerance (typically ≤1 mm) using calibrated equipment.

Re-torqueing after 24–48 hours is recommended where specified by the vendor or project due to gasket/washer seating and relaxation effects.

Related method statement

This Inspection and Test Plan is associated with the Method Statement: Installation of Rubber Fender System on Quay Wall (with Underwater Bolt Tightening, QA/QC, and Final Contact Test) method statement, which describes the step-by-step construction sequence, resources, materials, equipment, safety controls, and environmental controls for this activity.

View the Method Statement: Installation of Rubber Fender System on Quay Wall (with Underwater Bolt Tightening, QA/QC, and Final Contact Test) method statement →

Continue with related inspection, method statement, article, and checklist resources.

Related resources