Method Statement: Installation and Removal of Aluminum Hydraulic Shores and Trench Shields for Sewer Pipeline Installations inspection and test plan example.

Inspection and Test Plan for Method Statement: Installation and Removal of Aluminum Hydraulic Shores and Trench Shields for Sewer Pipeline Installations

AI-assisted inspection and test plan connected to a method statement, with PDF and Excel export.

Published 22 Sep 2026 Rev. 00 145 views 50 downloads
About this ITP: This ITP defines inspections, tests, hold/witness points, and records for installing and removing aluminum hydraulic shores and trench shields in sewer trenches.

More than a static template

Unlike a downloadable Word or PDF template, this ITP is an AI-assisted editable starting point directly connected to its method statement. Every inspection activity, hold point, and acceptance criterion is structured and ready to adapt to your project.

  • AI-assisted customization — Tailor inspection activities and acceptance criteria to your specific project scope.
  • Linked method statement — This ITP is connected to the corresponding method statement describing the work sequence.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review and verify all content against your project specifications and standards before use.

What you can customize

When you save this ITP to your account, every inspection row becomes editable. You can add, remove, or modify:

  • Inspection activity — Description of what is being inspected.
  • Inspection type — Hold point (H), Witness point (W), Review (R), or Monitor (M).
  • Responsibility — Contractor, subcontractor, engineer, or client.
  • Frequency — How often the inspection occurs.
  • Acceptance criteria — Referenced standard or specification requirement.
  • Records — Forms, test reports, or checklists required as evidence.

Why this ITP is used

To verify trench protective systems and associated works meet safety and quality requirements before allowing worker entry and during operations.

Who uses this inspection and test plan

Competent Person, Site Supervisor, TWC/TWE, HSE, QC Technicians, and third-party inspectors.

When this ITP is prepared and submitted

From pre-excavation through installation, daily checks, pipe laying, backfilling, and final extraction/demobilization.

Who receives or approves this ITP

Client/Engineer and HSE authority as required.

Inspection scope

Permits, utilities, soil/groundwater, AHS/shield integrity, pressure/spacing checks, access/egress, compaction, sequencing of removal, and daily inspections.

Typical hold, witness, and review points

Hold: Permit-to-Load issue, initial shore pressurization, first shield placement. Witness: daily inspections, compaction tests, shore removal sequence.

Typical inspection records

Permits, soil logs, pressure logs, lifting records, daily inspection forms, test results, photo records, NCRs/corrective actions.

Important approval note

This ITP is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all inspection activities, hold points, and acceptance criteria must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

Always verify acceptance criteria against your applicable drawings, specifications, and regulatory requirements. Hold points must be confirmed with the relevant authority before work proceeds past that point.

Inspection and test plan

Activity Inspection / Test Acceptance Criteria Responsibility Record
Permits and documentation review All permits approved and in date. Project Manager / TWC Permit register / ITP checklist
Utility clearance and trial holes Utilities located; tolerance zone respected. Supervisor / Competent Person Permit-to-Excavate; photos
Soil classification and groundwater assessment Soil type recorded; dewatering plan implemented if required. Competent Person Soil log
AHS equipment inspection and gauge calibration No defects; gauge calibration ≤12 months. Supervisor / HSE Inspection checklist; calibration cert
Shore installation pressure test (each level) Pressure hold/bleed test Pressure stable within ≤5% drop; within ±10% balance between cylinders [Benchmark – verify per MTD]. Shoring Crew / Competent Person AHS pressure log
Shore spacing and configuration check Conforms to MTD/TWE design; bottom of trench ≤0.6 m below lowest shore. Competent Person Shoring inspection sheet
Trench shield placement and rating verification Shield rating adequate for depth/soil; bottom gap ≤0.6 m; verticality acceptable. Lifting Supervisor / Competent Person Lift checklist; photo record
Access/egress and edge protection Ladders ≤7.5 m apart; extend ≥0.9 m; edges protected. Supervisor / HSE HSE checklist
Pipe bedding and alignment Survey checks Invert/grade within tolerance; bedding thickness per spec. Site Engineer Survey report; ITP record
Compaction testing ASTM D6938/D1556 Pipe zone ≥95% MDD; general 90–95% MDD [Verify per spec]. QC Technician Test reports
Controlled removal of shores during backfill Remove lowest shore only after compaction to safe level; no sloughing or movement observed. Supervisor / Competent Person AHS removal log
Shield movement (leapfrog) control No personnel inside; lift ≤0.6 m during pull; rigging per plan. Lifting Supervisor Lifting log
Daily excavation/shoring inspection No defects; conditions acceptable for entry. Competent Person Daily inspection form

This table is a read-only public reference. Download the PDF or Excel version, or customize this ITP to edit it for your project.

Frequently asked questions

Only if specified by the project or authority. However, internal hold points by TWC/TWE and Competent Person are mandatory.

Manufacturer’s tabulated data, Permit-to-Load, pressure logs, spacing measurements, daily inspection forms, and photographs of installations.

Related method statement

This Inspection and Test Plan is associated with the Method Statement: Installation and Removal of Aluminum Hydraulic Shores and Trench Shields for Sewer Pipeline Installations method statement, which describes the step-by-step construction sequence, resources, materials, equipment, safety controls, and environmental controls for this activity.

View the Method Statement: Installation and Removal of Aluminum Hydraulic Shores and Trench Shields for Sewer Pipeline Installations method statement →

Continue with related inspection, method statement, article, and checklist resources.

Related resources