Method Statement: Floating Screed Installation over Thermal/Acoustic Insulation Systems inspection and test plan example.

Inspection and Test Plan for Method Statement: Floating Screed Installation over Thermal/Acoustic Insulation Systems

AI-assisted inspection and test plan connected to a method statement, with PDF and Excel export.

Published 18 Oct 2026 Rev. 00 3 views
About this ITP: This ITP defines inspections and tests for floating screeds over insulation, including UFH pressure testing, SR and level verification, and moisture acceptance prior to finishes.

More than a static template

Unlike a downloadable Word or PDF template, this ITP is an AI-assisted editable starting point directly connected to its method statement. Every inspection activity, hold point, and acceptance criterion is structured and ready to adapt to your project.

  • AI-assisted customization — Tailor inspection activities and acceptance criteria to your specific project scope.
  • Linked method statement — This ITP is connected to the corresponding method statement describing the work sequence.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review and verify all content against your project specifications and standards before use.

What you can customize

When you save this ITP to your account, every inspection row becomes editable. You can add, remove, or modify:

  • Inspection activity — Description of what is being inspected.
  • Inspection type — Hold point (H), Witness point (W), Review (R), or Monitor (M).
  • Responsibility — Contractor, subcontractor, engineer, or client.
  • Frequency — How often the inspection occurs.
  • Acceptance criteria — Referenced standard or specification requirement.
  • Records — Forms, test reports, or checklists required as evidence.

Why this ITP is used

To assure that the screed installation over insulation meets specified performance for flatness, levels, strength, joints, and moisture before finishes.

Who uses this inspection and test plan

QA/Quality Manager, Site Engineer, Screeding Supervisor, MEP Coordinator, and independent testers.

When this ITP is prepared and submitted

From pre-pour inspections through curing and protection, up to release for finishes and handover.

Who receives or approves this ITP

Main Contractor and Employer’s Representative/Consultant

Inspection scope

Materials verification, substrate/DPM, insulation and membranes, UFH pressure test, placement, curing, SR/level survey, optional strength, moisture acceptance, and documentation.

Typical hold, witness, and review points

HP1 pre-pour build-up; HP2 UFH pressure test; W1 workability/flow; W2 SR/level survey; HP3 moisture acceptance.

Typical inspection records

Checklists, photos, delivery tickets, calibration certificates, flow logs, SR sheets, survey reports, pressure test certs, moisture certs, NCRs, handover pack.

Important approval note

This ITP is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all inspection activities, hold points, and acceptance criteria must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

Always verify acceptance criteria against your applicable drawings, specifications, and regulatory requirements. Hold points must be confirmed with the relevant authority before work proceeds past that point.

Inspection and test plan

Activity Inspection / Test Acceptance Criteria Responsibility Record
Substrate and DPM verification Visual inspection; DPM continuity check Clean, sound substrate; DPM/VCL present and intact where specified; no standing water. Site Engineer / QA Pre-pour checklist; photos
Perimeter strip installation Continuity and height check Continuous 5–10 mm strip; no acoustic bridges; height exceeds FFL by ≥10 mm. QA / Supervisor Inspection record; photos
Insulation board placement Gaps/rocking check; grade verification No gaps >3 mm; no rocking >1 mm; board grade/thickness per approved submittal. QA / Site Engineer MIR; delivery tickets; photos
Separation membrane installation Lap and tape inspection Laps ≥150 mm; fully taped; upturns intact; no punctures. QA / Supervisor Checklist; photos
UFH pressure test Pressure/Leak test Stable pressure over test duration within tolerance; certificate issued. MEP / QA Pressure test certificate
Level control pins/tripods set Laser level check Pins within ±3 mm of target; minimum thickness achieved. Site Engineer Level log; photos
Reinforcement (fibres/mesh) Dosage/placement check PP fibre dosage per spec; mesh laps ≥100 mm; mesh supported at mid-depth. QA / Supervisor Batch tickets; inspection sheet
Mix workability/flow Flow spread (CAF) or agreed workability check Within manufacturer’s limits (e.g., 230–270 mm CAF) or as specified. QA / Screed Supplier Rep (if any) Test logs
Placement and finish monitoring Visual; interim SR checks Uniform finish; no segregation; interim SR within target. Supervisor / QA Daily report
Curing/protection Curing regime check Cement: covered 3–7 days; CAF: ventilated per supplier; temp ≥5°C; access restricted. Supervisor / QA Curing log; photos
Surface Regularity (SR) and Level survey 2 m straightedge; level survey SR per spec (SR1/2/3); level tolerance ±5 mm local/±10 mm overall [Verify]. Site Engineer / QA SR sheets; survey report
In-situ strength/indentation (if specified) BRE screed tester / BS EN 13892-4 Meets specified ISCR/category [Verify]. Independent tester / QA Test report
Moisture testing before finishes In-situ RH or CM test Resilient: ≤75% RH; timber: ≤65% RH; CAF: ≤0.5% CM or per adhesive manufacturer [Verify]. QA / Finishes Contractor Moisture certificates
Final handover Documentation review; visual inspection All ITP items closed; no damage; protection in place; records complete. Main Contractor / QA Handover dossier

This table is a read-only public reference. Download the PDF or Excel version, or customize this ITP to edit it for your project.

Frequently asked questions

Initial SR checks should be performed post-cure to allow timely remedial works. Final verification can be done prior to finishes.

Not always. It is project-specific. When required, test with a BRE screed tester or per BS EN 13892-4 to the specified category.

Typically the Quality Manager with the Finishes Contractor, supported by calibrated RH/CM test certificates.

Related method statement

This Inspection and Test Plan is associated with the Method Statement: Floating Screed Installation over Thermal/Acoustic Insulation Systems method statement, which describes the step-by-step construction sequence, resources, materials, equipment, safety controls, and environmental controls for this activity.

View the Method Statement: Floating Screed Installation over Thermal/Acoustic Insulation Systems method statement →

Related resources