Method Statement: Exothermic Welding of Earthing and Lightning Protection Connections inspection and test plan example.

Inspection and Test Plan for Method Statement: Exothermic Welding of Earthing and Lightning Protection Connections

AI-assisted inspection and test plan connected to a method statement, with PDF and Excel export.

Published 16 Aug 2026 Rev. 00 306 views 156 downloads 1 shares
About this ITP: Structured ITP covering materials verification, pre-ignition hold point, 100% visual and hammer tests, sample resistance and pull-tests, and documentation close-out.

More than a static template

Unlike a downloadable Word or PDF template, this ITP is an AI-assisted editable starting point directly connected to its method statement. Every inspection activity, hold point, and acceptance criterion is structured and ready to adapt to your project.

  • AI-assisted customization — Tailor inspection activities and acceptance criteria to your specific project scope.
  • Linked method statement — This ITP is connected to the corresponding method statement describing the work sequence.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review and verify all content against your project specifications and standards before use.

What you can customize

When you save this ITP to your account, every inspection row becomes editable. You can add, remove, or modify:

  • Inspection activity — Description of what is being inspected.
  • Inspection type — Hold point (H), Witness point (W), Review (R), or Monitor (M).
  • Responsibility — Contractor, subcontractor, engineer, or client.
  • Frequency — How often the inspection occurs.
  • Acceptance criteria — Referenced standard or specification requirement.
  • Records — Forms, test reports, or checklists required as evidence.

Why this ITP is used

To ensure each exothermic weld meets project and standard requirements through controlled inspections and tests.

Who uses this inspection and test plan

QA/QC engineers, site engineers, client/engineer representatives, and third-party testers.

When this ITP is prepared and submitted

Before, during, and after welding to control materials, execution, and acceptance of joints.

Who receives or approves this ITP

Client/Engineer for approval and witnessing at hold points.

Inspection scope

Materials verification, mold/conductor preparation, ignition/welding, post-weld inspection, functional tests, coating, and records.

Typical hold, witness, and review points

Pre-ignition setup (Hold); post-weld visual/hammer (Hold); pull-test (Witness/Hold if specified).

Typical inspection records

MIRs, weld logs, photos, visual/hammer checklists, DLRO logs, pull-test certificates, coating inspection records, calibration certificates.

Important approval note

This ITP is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all inspection activities, hold points, and acceptance criteria must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

Always verify acceptance criteria against your applicable drawings, specifications, and regulatory requirements. Hold points must be confirmed with the relevant authority before work proceeds past that point.

Inspection and test plan

Activity Inspection / Test Acceptance Criteria Responsibility Record
Materials receipt – weld metal, disks, molds Visual, document check Correct types/sizes; undamaged; dry; certificates available QA/QC, Client/Engineer (Witness) MIR, Material approval, Batch log
Technician competency Certificate check Valid manufacturer training/certification [Verify] QA/QC Training record
Workfront readiness and PTW Permit verification Hot Work Permit active; controls in place HSE, Foreman, Client/Engineer (Witness) PTW, HSE checklist
Mold and conductor preparation Dryness, cleanliness check Mold dry; conductors bright metal, oil-free Technician, QA/QC Weld log
Pre-ignition setup – HOLD Setup verification Correct mold/charge, secure clamping, exclusion zone established QA/QC + Client/Engineer (Hold) IR/Hold-point sheet
Exothermic ignition and cooling Observation Safe ignition; no ejection; adequate cooling time Technician, HSE (Witness) Weld log
Post-weld visual inspection (100%) – HOLD Visual to acceptance criteria Full fill; no cracks/porosity/cold shuts; proper alignment QA/QC + Client/Engineer (Hold) IR with photos
Hammer test (100%) Hammer blows (0.5–1 kg) No cracking/loosening/movement QA/QC Inspection checklist
Electrical resistance (sampling) DLRO Joint R ≤ equivalent conductor R [Verify per spec] QA/QC Test log
Pull-test (sampling) – WITNESS/HOLD if specified Tensile pull to specified load No failure at specified load [Verify per project] QA/QC, Third-party Lab, Client/Engineer (Witness/Hold) Pull-test report
Zinc repair and joint coating DFT/coverage check (where applicable) Repair per ASTM A780; coating continuous, thickness per product datasheet QA/QC Coating inspection record
Records and close-out Document completeness All logs, photos, test certs filed and approved QA/QC Dossier/turnover pack

This table is a read-only public reference. Download the PDF or Excel version, or customize this ITP to edit it for your project.

Frequently asked questions

No. Typically performed on a sampling basis unless the project requires 100% testing. Verify frequency in the ITP.

Only if specifically required and suitable fixtures are available. Prefer mock-up samples to avoid damaging the installed system.

Related method statement

This Inspection and Test Plan is associated with the Method Statement: Exothermic Welding of Earthing and Lightning Protection Connections method statement, which describes the step-by-step construction sequence, resources, materials, equipment, safety controls, and environmental controls for this activity.