Installation of Lightning Protection Grounding Strips and Earthing Bonds Integrated into Structural Rebar inspection and test plan example.

Inspection and Test Plan for Installation of Lightning Protection Grounding Strips and Earthing Bonds Integrated into Structural Rebar

AI-assisted inspection and test plan connected to a method statement, with PDF and Excel export.

Published 25 Nov 2026 Rev. 00 1 views
About this ITP: The ITP sets inspection frequencies and release requirements for grounding strips and earthing bonds integrated into rebar. It requires checks on every concealed bond and continuity tests of the intended paths before the work is covered.

More than a static template

Unlike a downloadable Word or PDF template, this ITP is an AI-assisted editable starting point directly connected to its method statement. Every inspection activity, hold point, and acceptance criterion is structured and ready to adapt to your project.

  • AI-assisted customization — Tailor inspection activities and acceptance criteria to your specific project scope.
  • Linked method statement — This ITP is connected to the corresponding method statement describing the work sequence.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review and verify all content against your project specifications and standards before use.

What you can customize

When you save this ITP to your account, every inspection row becomes editable. You can add, remove, or modify:

  • Inspection activity — Description of what is being inspected.
  • Inspection type — Hold point (H), Witness point (W), Review (R), or Monitor (M).
  • Responsibility — Contractor, subcontractor, engineer, or client.
  • Frequency — How often the inspection occurs.
  • Acceptance criteria — Referenced standard or specification requirement.
  • Records — Forms, test reports, or checklists required as evidence.

Why this ITP is used

It verifies that concealed lightning protection bonds are structurally acceptable, electrically continuous and traceable before defects become inaccessible.

Who uses this inspection and test plan

Civil and MEP site engineers, electrical installers and test technicians, contractor QA/QC staff, and the contract-designated Engineer or Client representative.

When this ITP is prepared and submitted

From submittal review through installation and pre-concealment release, then after form stripping and at the handover to commissioning.

Who receives or approves this ITP

The ITP is usually submitted to the client representative, consultant, resident engineer, or project management consultant for review and approval before the related work activity starts.

Inspection scope

Material identity and compatibility, rebar and strip set-out, weld quality, clamp assembly and torque, defined continuity paths, terminal protection and release status.

Typical hold, witness, and review points

Hold before production installation, before concealment and at civil pre-pour authorization. Witness representative trials where specified and scheduled pre-concealment and post-pour continuity tests.

Typical inspection records

Material approvals, bond register, location photographs, weld and torque logs, continuity sheets, calibration records, signed releases, NCR dispositions and as-builts.

Important approval note

This ITP is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all inspection activities, hold points, and acceptance criteria must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

Always verify acceptance criteria against your applicable drawings, specifications, and regulatory requirements. Hold points must be confirmed with the relevant authority before work proceeds past that point.

Inspection and test plan

Activity Inspection / Test Acceptance Criteria Responsibility Record
Review coordinated design, submittals, structural bonding approval and test matrix Verify current drawings, approved bonding methods, structural restrictions, component compatibility, test endpoints and written limits. Approved documents available; no unresolved drawing conflicts, structural approvals or test criteria. MEP and Civil Site Engineers / QA/QC Engineer / Designated Release Authority Document register, approvals, RFIs and test matrix
Receive and verify components Check product code, dimensions, markings, lot traceability, condition, storage requirements and evidence of approval. Approved types and sizes; no damaged, wet, expired or unidentified items as applicable. Storekeeper / QA/QC Engineer Delivery and material inspection records
Inspect set-out and connection interfaces Check bar identity, joint location, strip cross-section and route, concrete cover, clear spacing, terminal set-out, and membrane and movement-joint interfaces. Matches coordinated IFC details and tolerances [Verify per project specifications]; no missing structural clearance or unapproved penetration. Civil and MEP Site Engineers / QA/QC Engineer Set-out checklist and marked-up drawings
Inspect exothermic bonds and mechanical clamps Check product configuration and preparation; visually inspect every completed weld; verify correct assembly and specified torque at every clamp. Weld meets manufacturer's visual acceptance criteria; clamp meets approved assembly and torque requirements; reinforcement is free of unauthorized damage. Bonding Installer / Lightning Protection Supervisor / QA/QC Engineer Trial record if required, bond register, weld and torque logs, photographs
Test electrical continuity before concealment Check instrument and leads, confirm endpoints and path configuration, measure low resistance, and account for parallel paths or apply the approved alternative. Recorded readings meet approved bond and path limits; measurement method demonstrates the intended path; no unverified bond or unresolved anomalous reading. Electrical Test Technician / QA/QC Engineer / Designated Witness Signed continuity results, instrument check and calibration records, witness record
Release before closing forms or other concealment Joint inspection of exposed work; check locations, joint records, test results, photographs, cover, access to terminals and NCR closure. Exposed bonds accepted and specified protection verified; traceability complete; written release received before concealment. Civil and MEP Site Engineers / QA/QC Engineer / Designated Release Authority Signed inspection request and civil/MEP pre-concealment clearance
Confirm pre-pour readiness and monitor concrete placement Confirm pre-concealment release, inspect accessible tails and terminals after form closure, and monitor for disturbance during placement. Form closing has not disturbed the accepted installation; terminals and tails secure; civil pour authorization obtained. Suspect damage triggers stop, investigation and renewed release as applicable. Civil Site Engineer / QA/QC Engineer / Pour Supervisor Pre-pour authorization and pour surveillance log
Verify after stripping and close out for commissioning Inspect exposed terminals and tails, repeat scheduled endpoint tests, check full routes when available and compare equivalent pre- and post-pour measurements. Accessible terminations accepted; required readings within approved limits; changes investigated and resolved; as-built and handover records complete. MEP Site Engineer / Test Technician / QA/QC Engineer / Designated Witness Post-pour readings, as-builts, final bond register and commissioning interface record

This table is a read-only public reference. Download the PDF or Excel version, or customize this ITP to edit it for your project.

Frequently asked questions

Record the endpoint IDs, instrument, test configuration, method, measured resistance, acceptance limit, result and technician. Note parallel paths or temporary disconnections that affect interpretation.

Unresolved nonconformances, missing required tests, unapproved attachments, inadequate cover, incomplete records or a missing written hold-point release prevent the affected work from proceeding.

Stop the affected work, assess the bond and route, reopen access if necessary, correct the damage, and repeat the applicable inspections and tests before obtaining a renewed release.

Related method statement

This Inspection and Test Plan is associated with the Installation of Lightning Protection Grounding Strips and Earthing Bonds Integrated into Structural Rebar method statement, which describes the step-by-step construction sequence, resources, materials, equipment, safety controls, and environmental controls for this activity.

View the Installation of Lightning Protection Grounding Strips and Earthing Bonds Integrated into Structural Rebar method statement →