G
Guest

Method Statement: Chemical Flushing, Cleaning, and Passivation of Chilled Water (CHW) Closed-Loop Networks inspection and test plan example.

Inspection and Test Plan for Method Statement: Chemical Flushing, Cleaning, and Passivation of Chilled Water (CHW) Closed-Loop Networks

AI-assisted inspection and test plan connected to a method statement, with PDF and Excel export.

Published 02 Oct 2026 Rev. 00 3 views
About this ITP: The ITP sets out inspections, witness/hold points, and acceptance criteria for each stage from pre-start checks to final lab results and handover.

More than a static template

Unlike a downloadable Word or PDF template, this ITP is an AI-assisted editable starting point directly connected to its method statement. Every inspection activity, hold point, and acceptance criterion is structured and ready to adapt to your project.

  • AI-assisted customization — Tailor inspection activities and acceptance criteria to your specific project scope.
  • Linked method statement — This ITP is connected to the corresponding method statement describing the work sequence.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review and verify all content against your project specifications and standards before use.

What you can customize

When you save this ITP to your account, every inspection row becomes editable. You can add, remove, or modify:

  • Inspection activity — Description of what is being inspected.
  • Inspection type — Hold point (H), Witness point (W), Review (R), or Monitor (M).
  • Responsibility — Contractor, subcontractor, engineer, or client.
  • Frequency — How often the inspection occurs.
  • Acceptance criteria — Referenced standard or specification requirement.
  • Records — Forms, test reports, or checklists required as evidence.

Why this ITP is used

To verify that the CHW system is cleaned, chemically conditioned, and compliant with technical and environmental requirements before commissioning.

Who uses this inspection and test plan

Main Contractor, Water Treatment Specialist, Engineer/Consultant, Environmental Officer, and QA/QC Engineer.

When this ITP is prepared and submitted

Applied from pre-start through dynamic flushing, chemical cleaning, passivation, sampling, and final acceptance.

Who receives or approves this ITP

Engineer/Consultant for approval and witnessing.

Inspection scope

Documentation review, isolation checks, flow/velocity verification, chemical dosing control, discharge compliance, inhibitor residual/pH control, and lab analysis.

Typical hold, witness, and review points

Pre-start readiness (Hold), Acid/chelant cleaning start (Hold), Inhibitor dosing (Witness), Sampling and lab dispatch (Hold), Final acceptance (Witness/Hold).

Typical inspection records

Checklists, flow logs, dosing logs, neutralization and discharge logs, calibration certs, chain-of-custody, and accredited lab certificates.

Important approval note

This ITP is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all inspection activities, hold points, and acceptance criteria must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

Always verify acceptance criteria against your applicable drawings, specifications, and regulatory requirements. Hold points must be confirmed with the relevant authority before work proceeds past that point.

Inspection and test plan

Activity Inspection / Test Acceptance Criteria Responsibility Record
Review and approval of Method Statement, ITP, and Chemical Submittals Document review and approval All documents approved prior to works commencement. MC/WTS/ENG Approved MS/ITP; Material Approvals
Pre-start walkdown and isolation verification Checklist and visual inspection Isolations complete; bypass installed; permits in place; instruments calibrated. MC/ENG Pre-Start Checklist; Photos
Temporary bypass loop pressure/leak test Leak test at system cold fill pressure + margin [Verify] No visible leaks; pressure drop ≤ 5% over 30–60 min. MC Leak Test Record
Dynamic high-velocity flushing (gross debris removal) Flow/velocity verification using ultrasonic meter Velocity ≥ 1.5 m/s or ≥1.5× design flow; Re > 4000 where practicable. MC/WTS/ENG (Witness) Flushing Log; Flow Records
Strainer inspection and cleaning DP measurement before/after Post-clean DP within 10% of baseline. MC Strainer Cleaning Log
Alkaline chemical cleaning circulation On-site pH and concentration checks hourly pH/concentration within supplier limits for specified contact time. WTS/ENG (Witness) Chemical Dosing Log
Neutralized rinse and discharge control Effluent pH and turbidity Discharge pH 6–9; turbidity within permit limit. MC/EO Neutralization & Discharge Log; Permit
Conditional acid/chelant cleaning (if required) pH, iron release trend, corrosion monitoring (if available) Controlled pH within approved range; no abnormal corrosion rate; max contact time not exceeded. WTS/ENG (Hold) Acid Cleaning Log; Approval
Biocide shock dosing (if specified) Residual/CT verification (if applicable) Meets supplier CT requirement. WTS Biocide Dosing Log
Passivation/inhibitor dosing On-site pH, inhibitor residual, conductivity Residual within supplier range; pH within metallurgy target. WTS/ENG (Witness) Inhibitor Dosing Log; Test Sheets
Final polishing via sidestream filtration Turbidity checks; filter DP Turbidity ≤ 5–10 NTU or project limit; stable operation. MC/WTS Sidestream Filter Log
Sampling and laboratory analysis Lab results for pH, EC, turbidity, chloride, metals, alkalinity, inhibitor residual, microbiology All parameters within project/BSRIA limits [Verify]. QA/QC/ENG (Hold) Chain-of-Custody; Lab Certificates
Final acceptance and demobilization Walkdown and documentation review System reinstated; documents complete; ENG acceptance. MC/ENG Completion Certificate; Handover Dossier

This table is a read-only public reference. Download the PDF or Excel version, or customize this ITP to edit it for your project.

Frequently asked questions

Yes. Add glycol concentration testing (e.g., refractometer), adjust inhibitor chemistry, and update discharge permit conditions accordingly.

They are based on BSRIA guidance and supplier recommendations, then finalized by the Engineer to suit project materials and requirements.

Any parameter outside accepted limits (e.g., turbidity, pH, inhibitor residual, chloride, or microbiology) or failure to achieve flushing velocity triggers NCR and rework.

Related method statement

This Inspection and Test Plan is associated with the Method Statement: Chemical Flushing, Cleaning, and Passivation of Chilled Water (CHW) Closed-Loop Networks method statement, which describes the step-by-step construction sequence, resources, materials, equipment, safety controls, and environmental controls for this activity.

View the Method Statement: Chemical Flushing, Cleaning, and Passivation of Chilled Water (CHW) Closed-Loop Networks method statement →

Continue with related inspection, method statement, article, and checklist resources.

Related resources