Pre-Print Readiness Checklist for 3D Concrete Printing

Use this checklist for one pre-print site visit covering a defined wall or print segment. Check each requirement against the current approved construction documents, qualified printing procedure and ITP; record measured values and evidence in the inspection entry as needed. Any failed critical item or outstanding hold point must be resolved before printing starts.

Site engineers verify foundation setting-out and printer readiness before 3D concrete wall printing starts.

The checklist

Document and design controls

  1. Approved IFC drawing/model revision identifies the wall or segment to be printed.
  2. Print file/toolpath revision matches the approved wall geometry and openings.
  3. Required printing-system qualification and trial-print acceptance are current for this operation.

Substrate and interfaces

  1. Foundation/substrate setting-out, position and levels have been verified against survey control.
  2. Starting surface is cleaned and prepared in accordance with the approved foundation-to-wall interface procedure.
  3. Required starter bars, dowels and anchors are in their approved positions before printing.
  4. Reinforcement, openings and service-embed locations are coordinated with the print path.

Printer and work-zone readiness

  1. Printer base, rails/working envelope and robot clearance are ready for the planned toolpath.
  2. Printer positioning, nozzle height and material-flow calibration checks are current.
  3. Required machine guarding, exclusion zones and emergency-stop checks are satisfactory.

Materials and environmental conditions

  1. Correct approved material/mix and traceable production batch are available for the planned segment.
  2. Required pre-print printability checks meet the approved qualified-process limits.
  3. Ambient conditions are within approved printing limits and curing/protection arrangements are ready.

Inspection release

  1. Approved ITP, sampling plan and applicable hold/witness notifications are available for this activity.
  2. All mandatory pre-start inspections and hold-point releases have been obtained before printing.

Preview the printable checklist

Preview page one below. Open the image or download the PDF for all pages.

First-page preview of the 3D Concrete Printing — Pre-Print Readiness printable checklist template.
3D Concrete Printing — Pre-Print Readiness · Page 1 preview · Open image with all pages

At a glance

  • For one wall/segment immediately before the printing operation starts.
  • Check drawing and toolpath control, foundation, printer, materials, safety and inspection releases.
  • Project-approved tolerances and designated hold points govern; this template provides no universal numerical limits.