construction · 13 checks

During-Print Quality Inspection Checklist for 3D Concrete Walls

Complete this checklist for one defined observation visit during active printing of a wall or segment. Repeat the checklist for later visits. Record location/layer, measurements and process context in the inspection record; compare with the approved model, qualified printing parameters and project ITP. Stop or escalate when continued printing could conceal a critical defect or create instability. For the complete before/during/after inspection guidance and the other visit-specific checklists, read the Quollnet inspection guide: https://quollnet.com/article/3d-printed-concrete-inspection-checklist

QA inspectors check the layers of a 3D concrete wall as a robotic printer deposits fresh concrete.

The checklist

Process identity

  1. Wall/segment and current approved print-file revision match the active production run.
  2. Material batch and required printer/process monitoring records are traceable to this visit.

Extrusion and geometry

  1. Extrusion is continuous without unacceptable gaps, under-extrusion or over-extrusion.
  2. Measured bead width and layer height meet approved tolerances at required sampling locations.
  3. Layer alignment and contact are within the approved geometry requirements.
  4. Wall position and developing geometry remain within approved setting-out tolerances.

Buildability and system control

  1. No progressive slumping, bulging, leaning or loss of stability is observed.
  2. Nozzle clearance is appropriate; no unacceptable drag, collision or deposited-layer disturbance is observed.
  3. Layer intervals and material age remain within the qualified process window.
  4. Process/environmental parameters remain within the approved operating range.

Interfaces and defects

  1. Required reinforcement/embedded items installed during this visit are checked before concealment under the applicable ITP.
  2. Visible defects or deviations are identified, located, recorded and escalated under the project procedure.

Visit disposition

  1. Any failed critical condition has led to the required hold, notification or engineering disposition before proceeding.

Preview the printable checklist

Preview page one below. Open the image or download the PDF for all pages.

First-page preview of the 3D Concrete Printing — During-Print Quality printable checklist template.
3D Concrete Printing — During-Print Quality · Page 1 preview · Open image with all pages

At a glance

  • For a single quality surveillance visit while a specific wall/segment is being printed.
  • Observe extrusion, bead/layer geometry, layer contact, print stability, process timing and embedded items.
  • No generic numeric limits: use the approved qualified process and project acceptance criteria.

Elie Saad's photo
Elie Saad
25333
663
54
80

Related Articles

Broader reading and guidance connected to this checklist topic.

3d Printed Concrete Qa/qc: Inspection, Process Control & Acceptance
3
en
3d Printed Concrete Qa/qc: Inspection, Process Control & Acceptance
EN
3d Printed Concrete Qa/qc: Inspection, Process Control & Acceptance

Practical QA/QC guide for 3D printed concrete walls: qualification, pre-print checks, live process control, interruptions, testing, defects and accept...

Article 2026-10-01
3d Printed Concrete Defects: Visual Field Guide For Site Engineers
3
en
3d Printed Concrete Defects: Visual Field Guide For Site Engineers
EN
3d Printed Concrete Defects: Visual Field Guide For Site Engineers

Visual field guide to 3D printed concrete defects: tearing, gaps, misalignment, slumping, restart interfaces, cracks, causes, records and escalation.

Article 2026-10-03
Concrete Cube Vs Cylinder Strength: Why The 0.8 Rule Can Mislead
C
en
Concrete Cube Vs Cylinder Strength: Why The 0.8 Rule Can Mislead
EN
Concrete Cube Vs Cylinder Strength: Why The 0.8 Rule Can Mislead

Concrete cube vs cylinder strength explained: why geometry changes results, why 0.8/0.85 conversions can mislead, and how QA/QC should compare results...

Article 2026-09-11
High Or Low Concrete Slump: Retest, Hold, Adjust Or Reject?
H
en
High Or Low Concrete Slump: Retest, Hold, Adjust Or Reject?
EN
High Or Low Concrete Slump: Retest, Hold, Adjust Or Reject?

What to do when concrete slump is high or low: confirm test validity, compare with project requirements, hold, retest, adjust only if authorized, and ...

Article 2026-08-11
Project Quality Plan (project Manual) In Construction: Contents And Workflow Guide
P
en
Project Quality Plan (project Manual) In Construction: Contents And Workflow Guide
EN
Project Quality Plan (project Manual) In Construction: Contents And Workflow Guide

What is a Project Quality Plan (PQP) in construction? Learn what a PQP contains, how it protects contractors, and why it is essential for project acce...

Article 2026-04-07

Related Checklists

Keep the workflow moving with nearby templates chosen from similar checklist content.

Site engineers verify foundation setting-out and printer readiness before 3D concrete wall printing starts. image
3
construction
3D Concrete Printing Pre-Print Readiness Inspection Checklist
Construction
3D Concrete Printing Pre-Print Readiness Inspection Checklist

Use this checklist for one pre-print site visit covering a defined wall or print segment. Check each requirement against the current approved construc...

Create a construction QA/QC checklist titled:
3D Printed Concrete Inspection Checklist — Before, During & After Printing
Purpose
Create a practical field inspection checklist for site engineers, QA/QC engineers, inspectors and 3D-concrete-printing contractors inspecting extrusion-based 3D printed concrete walls.
The checklist must be usable during an actual print and should generate a professional supporting article explaining how to use it.
Important technical principle
3D printed concrete inspection must control both:
1. the finished wall, and
2. the printing process that produced it.
The checklist should therefore preserve evidence of:
- what was printed;
- which approved digital/model/print-file revision was used;
- which material batch was used;
- how the printer was configured;
- what happened during printing;
- interruptions and restart conditions;
- reinforcement and embeds;
- final geometry;
- defects;
- curing;
- specimens/testing; and
- final disposition/release.
Do not invent universal tolerances
Do not state generic millimetre limits, bead-offset percentages, maximum layer intervals or other numerical acceptance limits unless they are clearly identified as project/system-specific examples.
Acceptance must normally refer to:
- approved project specification;
- approved drawings/model;
- qualified printing system;
- approved method/procedure;
- Inspection and Test Plan (ITP);
- manufacturer/system requirements;
- structural design requirements; and
- applicable codes/standards.
Where a value is project-specific, provide a field such as:
Acceptance / Reference: __________
or
Specified value: ________
Terminology
Use Print File / Toolpath Revision, not only “G-code,” because not every printer exposes G-code.
Use:
- Hold
- Witness
- Surveillance
where appropriate.
Every inspection item should allow:
- Pass
- Fail
- N/A
- Recorded value / observation
- Evidence / photo reference
- Action / NCR / observation reference where relevant
Checklist structure
Header / traceability
Capture:
- Project
- Location
- Wall / Print Segment ID
- Grid / Element reference
- Inspection date and time
- WIR / Inspection reference
- Approved drawing/model revision
- Print file/toolpath revision
- Printer ID
- Nozzle/configuration ID if applicable
- Approved mix/material ID
- Batch/lot ID
- Operator
- Contractor representative
- QA/QC inspector
PHASE 1 — BEFORE PRINTING / PRE-PRINT RELEASE
Include inspection items for:
Document and digital control
- Approved drawing/model revision
- Approved print file/toolpath revision
- Wall geometry, cavities and openings
- Required reinforcement and embeds
- Approved method statement/procedure
- Applicable ITP inspection point
Survey and substrate
- Wall centreline / coordinates
- Corners and openings
- Foundation/substrate level
- Starting surface condition
- Starter bars/dowels/anchors
Printer setup and calibration
- Printer zero/reference point
- Coordinate-system alignment
- Printer level/setup
- Working envelope
- Motion path
- Collision clearance
- Calibration/verification status
Material traceability and readiness
- Approved mix/material ID
- Batch/lot
- Mixing/batching time
- Accelerator/admixture dosage where relevant
- Material within approved printing/open-time window
- Printability requirements satisfied
Do not imply that conventional slump alone establishes printability.
Reinforcement, embeds and MEP
- Vertical reinforcement
- Horizontal reinforcement/ties where relevant
- Anchors
- Sleeves
- Service ducts
- Electrical boxes
- Inserts
- Openings
- Items that will become inaccessible during printing
Environmental conditions
Record:
- Ambient temperature
- Relative humidity
- Wind
- Direct solar exposure
- Rain/weather risk
- Required protection against drying/skinning
Pre-print release
Include a clear:
READY TO PRINT / HOLD
decision.
PHASE 2 — DURING PRINTING / LIVE PROCESS CONTROL
Include:
Extrusion continuity
Inspect for:
- continuous flow;
- under-extrusion;
- over-extrusion;
- tearing;
- gaps;
- pump pulsation;
- nozzle blockage.
Bead and layer geometry
Record where required:
- bead width;
- layer height;
- wall thickness;
- cavity/shell dimensions.
Compare against the approved system requirements rather than inventing universal limits.
Layer alignment
Monitor:
- lateral offset;
- face alignment;
- corners/curves;
- cumulative dimensional drift.
Buildability
Inspect lower layers for:
- spreading;
- slumping;
- bulging;
- leaning;
- buckling;
- progressive deformation;
- local instability/collapse.
Nozzle clearance and contact
Check for:
- nozzle drag;
- collision;
- scraping of earlier layers;
- disturbance of reinforcement/embeds;
- changes in nozzle-to-wall clearance.
Note that nozzle contact can disturb still-fresh underlying layers and may affect interlayer contact beyond the visibly damaged surface.
Layer interval / timing
Record:
- relevant layer interval;
- planned pauses;
- unplanned pauses;
- comparison with approved maximum interval/restart procedure.
Do not use a universal “cold joint” limit.
Reinforcement and embeds installed during printing
Verify before concealment:
- horizontal ties;
- reinforcement;
- mesh;
- anchors;
- sleeves;
- service inserts;
- insulation if applicable.
Live defect monitoring
Include recognition of:
- tearing;
- under/over-extrusion;
- gaps;
- misalignment;
- slumping/bulging;
- nozzle damage;
- voids;
- poor layer contact;
- cracking;
- dimensional drift.
PRINT INTERRUPTION / RESTART RECORD
Make this a prominent dedicated subsection.
Record:
- wall/segment;
- layer/elevation;
- stop time;
- restart time;
- total downtime;
- reason;
- material batch before stop;
- material batch after restart;
- environmental conditions;
- exposed-layer condition;
- cleaning or surface preparation;
- additional material/treatment used;
- inspection before restart;
- approval/disposition;
- approved by.
MANDATORY STOP / HOLD CONDITIONS
Create a clearly visible warning section.
Examples of conditions requiring stop, hold or immediate technical review should include:
- physical wall location does not match digital/model coordinates;
- wrong print revision;
- missing structural reinforcement, anchor or critical embed;
- progressive bulging/buckling/instability;
- partial collapse;
- major extrusion discontinuity;
- significant nozzle collision;
- wall geometry progressively moving outside the approved envelope;
- interruption exceeding the approved restart/process limit;
- visible layer separation/delamination;
- any condition where continuing would conceal or worsen a nonconformance.
Distinguish between:
Immediate stop
and
Hold for engineering / QA disposition
where appropriate.
PHASE 3 — AFTER PRINTING / FINAL INSPECTION
As-built geometry
Check:
- wall location;
- wall length;
- total height;
- wall thickness;
- plumbness;
- straightness/alignment;
- openings;
- corners;
- connection zones;
- cavity dimensions where applicable.
Record survey/as-built reference.
Visual defects
Inspect for:
- tearing;
- gaps/voids;
- layer separation;
- restart interfaces;
- cracks;
- local deformation;
- exposed reinforcement;
- damaged surfaces;
- dimensional abnormalities.
Reinforcement / embeds / openings
Verify final position and presence of accessible:
- reinforcement;
- anchors;
- sleeves;
- penetrations;
- inserts;
- openings.
Curing and protection
Verify:
- approved curing method;
- start time;
- protection from drying;
- thermal/weather protection;
- protection from physical damage.
Test specimens and companion printed elements
Record:
- specimen IDs;
- companion wall/panel IDs;
- material batch link;
- scheduled test age(s);
- required test reference.
Do not hard-code 7- and 28-day testing as universal.
Cavity grouting / structural infill
Include only if applicable:
- cavity cleanliness;
- reinforcement;
- seals/formwork;
- readiness for grout/infill;
- release status.
Final release
Include:
- Accepted
- Accepted with comments / conditional
- Hold
- Rejected / NCR
and signatures/approval fields as appropriate.
DEFECT / DEVIATION LOG
Include a small structured register with:
- Location / layer / elevation
- Defect or deviation
- Photo/evidence reference
- Observation / NCR reference
- Engineering disposition
- Repair action
- Reinspection status
- Closure reference
Supporting article
Generate a supporting article explaining:
3D Printed Concrete Inspection Checklist: Before, During & After Printing
The article should:
- explain why inspection of 3D printed concrete differs from conventional concrete;
- explain that process history is part of the quality evidence;
- explain Hold / Witness / Surveillance points;
- explain the before/during/after workflow;
- explain why print interruptions need a dedicated record;
- explain that visible defects are not automatically structural failures;
- explain when printing should be stopped;
- explain that project/system-specific tolerances govern acceptance;
- explain that the normal project WIR can be used for inspection of printed work;
- mention that an NCR should be raised when a defined requirement has actually been breached;
- clearly state that the checklist is a practical project template and not a substitute for the approved ITP, structural design, qualified printing system or project specification.
Reference framework
Use current authoritative sources where applicable, particularly:
- ICC 1150-2026 — Standard for Automated Construction Technology for 3D Printing Walls
- ISO/ASTM 52939:2023 — Additive manufacturing for construction — Qualification principles
- relevant NIST additive construction / cement-based additive manufacturing research
Do not invent requirements that these sources do not contain.
Output / usability
The checklist should work well as:
- an interactive QChecklist;
- a printable PDF;
- an editable/exportable Excel record.
Keep field text concise enough for actual site use. Avoid long explanatory paragraphs inside checklist rows. Put explanations in the supporting article instead.
The final checklist should feel like a real QA/QC inspection record, not a blog summary. image
3
construction
3D Printed Concrete Inspection Checklist: Before, During, After
Construction
3D Printed Concrete Inspection Checklist: Before, During, After

3D Printed Concrete Inspection Checklist — Before, During & After Printing is a practical, field-ready QA/QC tool for extrusion-based 3D concrete prin...

Inspector checks reinforcement and embedded conduits in a 3D printed concrete wall before concealment. image
3
construction
3D Printed Concrete Reinforcement and Embedded Services Inspection Checklist
Construction
3D Printed Concrete Reinforcement and Embedded Services Inspection Checklist

Complete at a defined hold or witness visit before specified reinforcement, anchors, sleeves, boxes or other critical embedded items become concealed ...

Retaining wall stem reinforcement (vertical) inspection image
R
construction
Retaining wall stem reinforcement (vertical) inspection
Construction
Retaining wall stem reinforcement (vertical) inspection

Retaining wall stem reinforcement (vertical) inspection confirms the vertical rebar is installed to the approved drawings before any concrete is place...

excavator of all types Daily Pre-Start Walkaround
Safety + visible defects: leaks, hoses, pins, bucket teeth, guards, mirrors/cameras, alarms, fire extinguisher, fluids, general damage. image
E
safety
Excavator Daily Pre-Start Walkaround Safety Checklist
Safety
Excavator Daily Pre-Start Walkaround Safety Checklist

Excavator Daily Pre-Start Walkaround ensures every machine begins the shift safe, compliant, and fit for purpose. This daily pre-operation inspection,...