Inspect façade flashing installation above windows and doors for site inspectors and superintendents, verifying water-shedding geometry, compatible materials, and WRB integration to achieve durable, leak-resistant, and specification-compliant head details.
- Confirm slope, end dams, and drip edges shed water reliably.
- Verify compatible metals, sealants, and fasteners with documented evidence.
- Check shingle-fashion WRB integration and clear drainage paths.
- Interactive, commentable checklist with export and QR code verification.
The checklist
Pre-Installation Conditions Above Openings
- Confirm substrate at head is clean, dry, and plane within ±3 mm over 1 m using a straightedge; remove protrusions and dust. Record measurements and a close-up photo; obtain supervisor initials.
- Verify lintel or head angle is installed level within ±3 mm over opening width and bears ≥150 mm each side; measure with tape and level; photo lintel ends and mark readings.
- Check clearance above frame for flashing and sealant: provide ≥10 mm continuous space; measure at both jambs and midspan; photo with ruler visible.
- Confirm weather window: no precipitation forecast during installation/curing and ambient 5–35 °C; capture weather app screenshot and note time on inspection log.
Materials and Components Verification
- Verify flashing metal matches submittals (e.g., 0.7 mm aluminium or 0.55 mm stainless steel), factory finish intact, no kinks; record product codes, lot numbers, and photos.
- Confirm primers, tapes, and sealants are compatible with metals and WRB; perform a field adhesion test per manufacturer (no cohesive failure); photo peel test and retain labels.
- Check pre-formed end dams and drip edge: end dam height ≥25 mm; drip hem ≥3 mm; overhang 10–15 mm beyond face; measure with calipers and photo each feature.
- Confirm fasteners are stainless steel (A2/A4) and compatible; length achieves ≥12 mm embedment; prepare layout plan; photo boxes and corrosion-resistance markings.
Installation Geometry and Slope
- Measure outward fall using a digital level or inclinometer: achieve ≥2% (1:50) toward façade face across full width; record readings and a photo of the device display.
- Verify upstand height behind cladding/WRB is ≥100 mm and supported; measure at three points; photo upstand continuity before covering.
- Inspect laps at joints/corners: provide ≥100 mm overlap in water-flow direction with 50 mm butyl tape; roll firmly; no fishmouths or gaps; close-up photos at each joint.
- Confirm drip edge forms a continuous break line; overhang 10–15 mm; no reverse slope or buckling; measure and photograph the full length and a macro of the hem.
Fixings and Sealing
- Fasten flashing at ≤200 mm centres with edge distance ≥15 mm; avoid penetrating horizontal water-shedding surface where possible; photo fastener spacing with a scale.
- Seal penetrations and terminations using compatible sealant; apply 6–8 mm tooled bead, continuous and smooth to shed water; photo before and after tooling.
- Provide expansion gaps at abutments of 3–6 mm; install backer rod where joint depth permits; verify with feeler gauge and photo gap measurement and backer placement.
- Install end dams tight to jambs; seal three sides continuously; perform gentle spray test for 3 minutes targeting head/jamb interface—no leaks permitted; record video and notes.
Integration With WRB and Drainage
- Integrate shingle-fashion: WRB above laps over flashing upstand ≥75 mm; tape seams per manufacturer; photo sequence showing layer order before cladding.
- Ensure drainage continuity: clear cavity ≥25 mm behind cladding; provide weeps/vents at ≤400 mm centres or per approved project specifications and authority requirements; count and photo.
- Isolate dissimilar metals (e.g., aluminium to concrete/steel) with separation tape or membrane; verify full-length coverage; photo start, mid, and end points.
- Clean surfaces; remove swarf and sealant smears; confirm outlets and weeps unobstructed; apply temporary protection if required; capture final overview photos and obtain installer/inspector signatures.
Preview the printable checklist
Preview page one below. Open the image or download the PDF for all pages.
At a glance
- Focus on the head conditions above windows and doors: confirm outward fall, upstand height, end dams, laps, and overhangs, then verify WRB integration and clear weep paths. Capture photos, readings, and batch data for traceable compliance.
- Reduce water ingress, staining, and hidden decay by validating geometry, compatible materials, and correct fastening and sealing. Practical acceptance cues—like ≥2% fall, 100 mm upstands, and 100 mm laps—deliver predictable, repeatable outcomes across trades and shifts.
- Interactive online checklist with tick, comment, and export features secured by QR code. Field teams can attach photos, record measurements, tag locations, and generate shareable PDF/Excel reports for supervisors, designers, and authorities within minutes.
How to Use This Interactive Inspection Checklist
- Preparation: Assemble digital level/inclinometer, 5 m tape, calipers, straightedge, sealant tools, camera/phone, PPE (gloves, eye protection, fall protection), drawings, and approved submittals. Confirm access is safe, surfaces are dry, and installers are available to expose work as needed.
- Using the Interactive Checklist: Open the checklist, select the elevation and opening ID, then start interactive mode. Tick items as you verify, attach photos and measurements, and add comments tagging responsible trades. Use quick-pick tolerances to speed pass/fail decisions.
- Export and Share: Generate a timestamped PDF/Excel export including photos, notes, and locations. Share with the installer, superintendent, designer, and QA lead. Use the embedded QR code on the report to authenticate field records.
- Sign-Off and Archiving: Capture digital signatures from the inspector and installer. File the report under the elevation and grid reference, link to RFI/deficiency logs if applicable, and archive with drawings for future maintenance references.
Why head flashing above openings is critical
Head flashings above windows and doors intercept water driven into the façade and redirect it outward before it can reach frames, insulation, or structure. Most failures trace back to missing end dams, insufficient outward fall, or poor WRB tie-in. Staining lines, damp reveals, and recurring interior leaks are telltale symptoms. A disciplined inspection verifies the gap above frames, lintel alignment, and substrate flatness to support straight, drip-forming flashings. It then confirms material compatibility so galvanic corrosion or sealant failures do not undermine the detail months later. Acceptance cues such as a visible drip hem, continuous laps, and documented slope measurements provide early assurance. On mixed-material façades—masonry, rainscreen, or EIFS—the same water-shedding principles apply, but tolerances and integration steps differ by system. Capture photos before cladding close-up to prove sequence and continuity, and require installer initials on each bay. These habits reduce remediation risk and protect warranties while keeping elevations clean and durable.
- Outward fall, end dams, and drip hem stop hidden water paths.
- WRB must lap over the upstand in shingle fashion.
- Material compatibility prevents galvanic corrosion and sealant failure.
- Capture photos before concealment for traceable compliance.
Geometry, tolerances, and verification methods
Reliable head flashings depend on measurable geometry. A minimum outward fall of 2% (1:50) moves water to the drip edge even in light winds. Upstands of at least 100 mm allow the WRB to overlap securely, and 100 mm laps at joints provide redundancy. Overhangs between 10–15 mm with a 3 mm hem create a sharp drip that breaks surface tension. Use a digital level for slope, calipers for hems, and a tape for laps and overhangs. Sealant beads should be 6–8 mm and properly tooled; overlarge beads trap water, undersized beads fail adhesion. Fastener spacing at 200 mm centres with adequate edge distance avoids oil-canning and blow-offs. Record actual measurements in the checklist for each opening, attach macro photos at joints, and tag locations on elevation drawings to speed punch-list clearance.
- Measure slope with a digital level—target ≥2% outward.
- Hem ≥3 mm and overhang 10–15 mm create a clean drip.
- Provide ≥100 mm upstand; lap joints ≥100 mm.
- Fasteners ≤200 mm centres with ≥15 mm edge distance.
Integration with WRB and drainage continuity
Even perfect metalwork leaks if upstream layers are reversed. The WRB must overlap the flashing upstand, not the other way around, and all seams require manufacturer-approved tape or liquid flashing. Corner patches and end dams stop lateral water migration into jambs. Maintain a clear cavity—typically ≥25 mm—so water can move to weeps or open joints at regular spacing. Where dissimilar metals meet, install separation membranes to avoid corrosion streaking and premature failure. Conduct a gentle hose test after sealing end dams to confirm the head–jamb interface performs before cladding conceals the detail. Document everything: photos of the sequence, lot labels of tapes and sealants, and signatures. This record supports approvals per approved project specifications and authority requirements and provides assurance when elevations are enclosed rapidly by downstream trades.
- Shingle-fashion layering: WRB over upstand, never reversed.
- Clear cavity ≥25 mm with regular weeps or vents.
- Seal end dams and corners; verify with spray test.
- Record labels, photos, and signatures for traceability.