NCR Meaning in Construction
Quick meaning (construction QA/QC)
NCR in construction means Non-Conformance Report (also written Nonconformance Report).
It is a formal QA/QC record raised when work, materials, testing, or documentation does not comply with project requirements.
Note: “NCR” has other meanings in other industries. This page is strictly about construction quality (QA/QC). It’s also commonly mistyped as “NRC”.
One-sentence definition
An NCR (Non-Conformance Report) is a controlled QA/QC document used to identify, contain, correct, verify, and close a confirmed case of non-compliance with contract specifications, approved drawings, method statements, ITPs, or applicable standards.
Common alternative names (same concept)
On different projects/clients, NCR may be called:
-
Nonconformance Report
-
Non-Conformity Report
-
Non-Conformance Notice
-
Non-Compliance Notice (NCN)
-
Defect / Defective Work Notice (often contractual wording)
-
Rejection Notice (materials/work rejection)
-
Corrective Action Request (CAR) (sometimes separate, sometimes merged)
What triggers an NCR (typical causes)
An NCR is typically raised after confirmed non-compliance, such as:
1) Failed test
Examples:
-
concrete strength result below requirement
-
weld NDT rejection
-
pressure test failure
-
soil compaction below spec
2) Rejected inspection
Examples:
-
installation not per approved drawing
-
tolerance exceeded
-
wrong material used
-
work executed without required inspection hold point
3) Unauthorized deviation
Examples:
-
change in rebar size/spacing without approval
-
unapproved material substitution
-
method statement not followed in a way that affects compliance
4) Missing mandatory records
Examples:
-
inspection not performed and work is already covered
-
required test missing or invalid
-
traceability certificates not available where required
What an NCR is NOT (to prevent misuse)
-
Not a snag list / punch list item (usually minor completion/finishing)
-
Not a “general complaint” document
-
Not automatically a dispute or claim
-
Not proof of fault by itself (it’s a record of non-compliance and required actions)
Who issues NCRs on a project
Depending on project structure, NCRs may be issued by:
-
Consultant / Engineer / Supervision team (most common externally)
-
Contractor QA/QC (internal NCRs for control before consultant action)
-
Client representative (less common; often via consultant)
Regardless of issuer, the contractor is typically required to respond, implement corrective action, and provide closure evidence.
Standard NCR workflow (from issue to closure)
A construction NCR generally follows this lifecycle:
-
Identify non-conformance (inspection/test/audit/site finding)
-
Record facts + location + references (drawing/spec/ITP)
-
Containment (stop affected activity, quarantine material, prevent concealment)
-
Contractor response
-
root cause (why it happened)
-
corrective action (how to fix this case)
-
preventive action (how to prevent recurrence)
-
-
Disposition by Engineer/Consultant
-
accept as-is (rare, with justification)
-
repair
-
remove and replace
-
accept with concession/technical deviation (if allowed)
-
-
Verification
-
re-inspection / re-test
-
evidence submitted (photos, reports, results)
-
-
Close NCR
-
signed, dated, status updated in the register/log
-
What “good” NCR writing looks like (minimum standard)
A strong NCR statement is:
-
factual (no opinions, no blame language)
-
specific (exact location, element, trade)
-
referenced (spec clause, drawing number, ITP step)
-
verifiable (photos, measurements, test report IDs)
Bad: “Work is not acceptable.”
Good: “Rebar spacing at Grid B-4 measured at 250 mm vs drawing S-103 requirement 200 mm; area inspected on 2026-01-06; photos ref NCR-P-014-01 to 03.”
Why NCRs matter (practical value)
A functioning NCR system:
-
prevents unsafe continuation of works
-
reduces rework through early detection
-
improves quality performance through corrective/preventive action
-
protects handover documentation
-
creates defensible records for disputes (when needed)
Upcoming NCR pages in this series
You’ll publish tool-first pages and focused info pages. Each page will address one intent:
-
NCR Log / Register (Tool): tracking status, ageing, and closure
-
Observation vs NCR vs Snag vs Defect (Info): when to use each record
-
When to Issue an NCR (Info): failed tests, rejected inspections, missing records
-
NCR Severity Matrix (Tool): minor/major/critical classification
-
Notice to Correct Letter (Tool): contractual escalation template
-
Proceed at Contractor’s Risk Letter (Tool): conditional continuation template
-
Continue Work with an Open NCR? (Info): stop-work vs proceed-at-risk logic
-
Can an NCR Lead to Termination? (Info): default, notices, and time limits
-
Open NCRs at Handover (Info): taking-over and defects implications
Summary
-
Term: NCR
-
Meaning (construction): Non-Conformance Report
-
Purpose: control confirmed non-compliance (identify → correct → verify → close)
-
Triggers: failed test, rejected inspection, unauthorized deviation, missing mandatory record
-
Key fields: description + location + requirement reference + corrective action + verification evidence + closure
-
Not: snag list, generic complaint, automatic claim