Inspection of ductwork through a non-fire-rated wall verifies that the penetration matches project requirements for clearance, edge treatment, independent support, and perimeter finishing.
- Confirm wall classification and applicable project details before assessing the installation.
- Evaluate clearance with insulation, movement allowance, and perimeter finish requirements in mind.
- Verify that the wall opening, sleeve, and perimeter seal do not carry duct weight.
- Resolve missing requirements and installation discrepancies before concealment or final finishing.
The checklist
Confirm wall classification
- Confirm that the project documents identify the wall at this penetration as non-fire-rated. If the classification is missing or conflicting, record the issue for resolution before concealment.
Identify penetration requirements
- Locate the applicable project detail or specification for opening clearance, sleeve or edge treatment, and perimeter finish. Record any missing requirements for resolution rather than assuming a standard clearance.
Check other barrier requirements
- Check project documents for acoustic, smoke-control, or air-sealing requirements at this penetration, and identify the specified treatment where applicable.
Measure opening clearance
- Measure and record clearance around the duct against the project detail, accounting for specified insulation thickness and movement allowance.
Check insulation condition
- Where insulation is present, check that the opening does not compress or damage it or its vapor-retarder facing.
Inspect opening and adjacent framing
- Check for damage or cuts to adjacent framing and compare any alterations with the project details. Record damage or undocumented alterations for resolution before finishing.
Verify sleeve or edge protection
- Where a sleeve or edge protection is specified, verify its material, location, extent, and attachment against the applicable detail.
Check exposed edges
- Inspect exposed opening and sleeve edges for burrs or sharp projections that could damage the duct, insulation, or facing.
Verify duct support arrangement
- Compare the supports serving the penetration with the project support layout, including their locations and attachments. Do not assume supports are required on both sides unless specified.
Confirm independent support
- Verify that the duct is supported independently and that its weight is not carried by the wall opening, sleeve, or perimeter seal.
Inspect wall finish edges
- Inspect the wall edges around the penetration for loose material or damage requiring repair before perimeter finishing.
Check finish surface preparation
- Check that surfaces receiving sealant, backing, or trim are clean and prepared according to the specified finish system's installation instructions.
Verify space for perimeter finish
- Verify that the remaining perimeter gap accommodates the specified sealant, backing, or trim while retaining the movement allowance required by the project detail.
Record unresolved items
- Record each unresolved requirement or installation discrepancy, including its location and required follow-up. Do not mark the penetration ready for concealment or final finishing until these items are resolved.
Preview the printable checklist
Preview page one below. Open the image or download the PDF for all pages.
At a glance
- Project documents establish wall classification and penetration requirements.
- Non-fire-rated walls may still have acoustic, smoke-control, or air-sealing requirements.
- Clearance must accommodate the specified insulation, movement allowance, and perimeter finish.
- Independent support and resolved discrepancies are essential to finish readiness.
How to Use the Approved Inspection Checklist
- Gather the project documents covering wall classification, penetration details, barrier treatments, support layout, and perimeter finishing.
- Use the approved checklist at the penetration, comparing observed conditions and recorded measurements with those documents.
- Document missing requirements and installation discrepancies by location, including the follow-up needed for resolution.
- Confirm unresolved items have been addressed before marking the penetration ready for concealment or final finishing.
Use project requirements as the inspection baseline
The wall classification and applicable penetration detail establish what the inspector should evaluate. A missing or conflicting requirement is an issue to resolve, not a reason to assume a standard dimension or treatment.
- Base clearance, sleeve or edge treatment, and finish assessments on the applicable detail or specification.
- Check separately for acoustic, smoke-control, and air-sealing requirements.
Consider clearance as a coordinated space
The opening must accommodate more than the bare duct. Specified insulation, movement allowance, and perimeter finishing all affect whether the available space is suitable. Damaged insulation or vapor-retarder facing can indicate a problem even where an opening appears large enough.
- Compare measured clearance with the project detail rather than a generic gap.
- Consider insulation condition and the space needed for the specified backing, sealant, or trim.
Distinguish edge protection from duct support
Sleeves and protected edges serve the functions assigned by the project detail; they are not substitutes for independent duct supports. The support layout determines support locations and attachments, so supports on both sides of the wall should not be assumed necessary unless specified.
- Evaluate specified sleeve or edge protection against its detailed material, location, extent, and attachment.
- Confirm that duct weight is not carried by the opening, sleeve, or perimeter seal.
Treat finish readiness as a documented decision
Loose wall material, damaged edges, undocumented framing alterations, and unprepared finish surfaces can prevent the penetration from being ready for completion. Record unresolved conditions with their location and required follow-up, and keep the penetration from being marked ready until those conditions are resolved.
- Assess finish preparation against the specified system's installation instructions.
- Retain the movement allowance required by the project detail when assessing the perimeter finish space.