Method Statement: Scrubbable Water-Based Epoxy Wall Painting for Emergency Stairwells – Method Statement
Method Statement: Scrubbable Water-Based Epoxy Wall Painting for Emergency Stairwells method statement and inspection test plan example.

Method Statement: Scrubbable Water-Based Epoxy Wall Painting for Emergency Stairwells – Method Statement

AI-assisted method statement with matching ITP, PDF download, and Excel export.

Published 24 Nov 2026 Rev. 00 5 views
About this method statement: This method statement details how to repair and prepare stairwell walls, apply a scrubbable water-based epoxy system, and verify durability and DFT. It includes rigorous QA/QC, ventilation, access coordination, and final handover procedures.

More than a static template

Unlike a downloadable Word or PDF template, this method statement is an AI-assisted editable starting point connected directly to a matching Inspection and Test Plan. Every section is structured, project-adaptable, and ready to export.

  • AI-assisted drafting — Customize every section with AI for your specific project scope.
  • Linked ITP — A matching inspection and test plan is generated alongside the method statement.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review, verify, and adjust all content against your project requirements before use.

Static template vs. Quollnet workflow

FeatureStatic templateQuollnet
Project-specific contentManual fill-in requiredAI-assisted customization
Linked ITPSeparate document, no linkMatching ITP included
Export formatsUsually PDF onlyPDF and Excel
Structured sectionsFree-form layout13 standardized sections
Saved to your accountLocal file onlyCloud-saved, reusable
Content accuracyYou verify everythingAI-assisted, you still verify
CostOften free but time-intensiveFree to customize and download

What you can customize

When you save this method statement to your account, every section becomes editable. The following 13 sections are included:

  • Scope — Defines the activity and its boundaries.
  • References — Standards, specifications, and drawings.
  • Responsibilities — Roles and accountabilities.
  • Resources — Labour, plant, and equipment summary.
  • Materials — Materials and compliance requirements.
  • Equipment — Tools and equipment details.
  • Prerequisites — Hold points and pre-conditions.
  • Method sequence — Step-by-step construction sequence.
  • Safety controls — HSE risk controls and PPE.
  • Environmental controls — Environmental mitigation measures.
  • QA/QC — Quality inspection and test requirements.
  • ITP — Inspection and Test Plan table (has its own page).
  • Attachments — Referenced drawings and documentation.

Why this method statement is used

This method statement is used to define and communicate the approved procedure for carrying out method statement: scrubbable water-based epoxy wall painting for emergency stairwells on site. It ensures the work is planned in advance, the correct resources and controls are in place, and all personnel understand responsibilities, sequence, quality requirements, and safety controls before work begins. It aligns site execution with the documented scope and acceptance expectations.

Who uses this method statement

This method statement is used by contractors, site supervisors, project engineers, QA/QC engineers, HSE officers, consultants, and client representatives. It serves as a shared reference for planning, execution, supervision, inspection, and approval of the activity on site.

When it is prepared and submitted

The method statement is prepared before the work activity starts and submitted as part of the pre-construction documentation package for review and approval.

Who reviews or approves it

The method statement is usually submitted to the client representative, consultant, resident engineer, or project management consultant for review and approval before the work commences.

Important approval note

This method statement is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all content must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

For example: if your specification requires a departure from a referenced standard, that departure must be documented and approved separately — this method statement will not capture that automatically. Always verify against your applicable drawings, specifications, and regulatory requirements.

Method statement content

Scope

Overview

This method statement covers end-to-end delivery of a scrubbable water-based epoxy coating system to emergency stairwell walls across multiple floors, including:
- Masonry assessment and repair (crack/spall patching, void filling, edge arrises)
- Protection and masking of installed corner guards, handrails, signage, fixtures
- Surface preparation, cleaning, and environmental conditioning
- Application of epoxy primer and two finish coats by roller
- Temporary lighting provision and maintenance (workface ≥ 300 lux) [Verify per project specifications]
- Mechanical ventilation setups to control humidity, odor, and cure (target 4–10 ACH) [Verify per project HSE plan]
- In-process WFT and post-cure DFT verification, adhesion testing
- Scrub and impact resistance verification on control panels
- Final cleaning, reinstatement, and safety exit corridor handover sign-offs

Areas Included

  • Stairwell walls (concrete/masonry block/plaster skim as applicable)
  • Stringer soffits, wall returns at landings, and door reveals (if specified)

Exclusions

  • Structural repairs beyond minor masonry patching
  • Floor coating, ceiling painting, steelwork painting (unless noted)
  • New corner guard installation (masking/protection only unless otherwise instructed)

Key Performance Targets [Verify per project specifications]

  • Total DFT (primer + 2 topcoats): 120–200 µm total
  • Adhesion to substrate: ≥ 1.0–1.5 MPa (ASTM D4541) or Cross-hatch ≥ 4B (ASTM D3359) where pull-off impractical
  • Scrub resistance (ASTM D2486) on control panel: ≥ 5,000 cycles to defined end-point
  • Impact resistance (ASTM D2794) on control panel: ≥ 20 in-lb (2.26 J) direct without cracking/delamination
  • Uniformity: No sags, runs, pinholes, dry spray, color mismatch visible at 1.5 m under 300–500 lux lighting
  • Egress: Maintain code-compliant escape route width and signage throughout the works [Verify per local code]

References

Document TypeReference / NumberRevisionNotes
Standard ASTM D6132
Standard ASTM D4414 Use notch/comb gauges at start and during works.
Standard ASTM D4258
Standard ASTM D4259 Avoid acid etching in enclosed stairwells unless specifically approved.
Standard ASTM D4263 Supplement with electrical moisture meter as required.
Standard ASTM D4541 / ISO 4624 Use dollies suitable for masonry; avoid damage to fire-rated walls without approval.
Standard ASTM D3359 Method A/B per film thickness and substrate hardness.
Standard ASTM D2486 Laboratory or approved third-party test on concurrently coated panels.
Standard ASTM D2794 Performed on standardized panels coated alongside site works.
Standard ASTM D3960 / ISO 11890-2 As declared by manufacturer and verified by data sheet/COC.

Responsibilities

RoleResponsibilityName / Party
PM Approve RAMS, ensure egress plan maintained, approve access sequencing Contractor
Engineer Verifies substrate condition, environmental compliance, WFT/DFT tracking Contractor
QA/QC Witness/hold points, test frequency, NCR control Contractor
HSE Ventilation plan, exposure controls, egress integrity Contractor
Supervisor Batch control, pot life, recoat window, film build Contractor
Consultant Approves substrates, color/finish, final handover Engineer/Employer

Resources

Resource TypeDescriptionQuantityRemarks
Labor Epoxy systems experienced As scheduled
Labor Minor patch/repair works As required
Labor Install/maintain task lighting and safe power 1
Labor Daily inspections, permits, toolbox talks 1

Materials

MaterialSpecification / GradeQuantityRemarks
Epoxy primer Manufacturer-approved for topcoat As BOQ
Epoxy topcoat Total system DFT 120–200 µm [Verify] As BOQ
Repair mortar For thin patch 5–30 mm As required
Acrylic/epoxy filler Manufacturer-approved As required
Cleaner As required
Masking As required

Equipment

EquipmentCapacity / TypeQuantityInspection Required
Rollers/brushes Sets per crew
Mixer 1 per crew
WFT gauge 2
DFT gauge 1
Adhesion tester 1
Meters 1 set
Access As required
Ventilation Per stairwell
Lighting Per bay

Prerequisites

  • Approved Method Statement and ITP; COSHH/SDS available on site
  • MIR approvals for primer and topcoat; color schedule and sheen confirmed
  • Access and egress plan agreed with Facilities/Fire Safety: maintain code-compliant route width and two-way communication [Verify per local code]
  • Permit-to-Work: Work at Height, Electrical (temporary power), Hot Work if grinding, and area isolation [Verify per project HSE plan]
  • Mock-up sample area (min 2 m²) approved for color/texture/finish and DFT approach
  • Substrate readiness: masonry repairs completed and cured; moisture test acceptable (ASTM D4263) and pH ≤ 9 [Verify]
  • Environmental control plan: ventilation path, noise hours, odor control; confirm no impact to occupied areas
  • Calibrations in date for DFT gauge and adhesion tester; inspection checklists ready
  • Corner guard protection and masking materials available; sequence agreed with building operations
  • Emergency staircase signage/alternative routing coordinated for active work zones

Method Sequence

StepActivityDescriptionResponsibilityInspection / Hold Point
1 Site Induction, Permits, Area Isolation Conduct task-specific induction and toolbox talk. Obtain PTW. Barricade active work zone; maintain emergency egress route width per code; display detour signage. HSE Manager / Supervisor Permit/Barrier check
2 Temporary Lighting & Ventilation Setup Install LED lights to achieve ≥ 300 lux on wall face. Set fans/ducting to achieve target 4–10 ACH; measure and log temperature and RH. Electrician / Supervisor Lux/RH/Temp reading
3 Protection & Masking Mask corner guards, handrails, signage, and floor intersections with low-tack tape and protective film. Install drop sheets; protect fire devices (without obstructing function). Supervisor Visual
4 Masonry Inspection & Repairs Sound the substrate; mark defects. Grind loose/unsound areas. Patch with polymer-modified mortar (5–30 mm). Tool and finish to level. Cure 24–48 h or per datasheet. Mason / Engineer WIR: substrate/repairs
5 Surface Preparation & Cleaning Detergent wash (ASTM D4258), rinse, dry. Mechanically abrade glossy/contaminated areas (ASTM D4259). Remove dust with HEPA vacuum and lint-free wipes. Supervisor Cleanliness check
6 Substrate Condition Checks Verify moisture (ASTM D4263 16–24 h plastic sheet) and/or moisture meter; pH ≤ 9; ambient T 10–35 °C, RH ≤ 85%, substrate ≥ 3 °C above dew point. Site Engineer Hold Point: substrate acceptance
7 Primer Mixing & Application Stir A & B separately, then combine per mix ratio; mix 2–3 min. Observe induction time if required (10–20 min) [Verify]. Apply by roller; target WFT to achieve specified DFT. Painting Supervisor WFT spot checks
8 Primer Cure & Sand (if required) Allow to cure as per TDS (e.g., 4–8 h at 25 °C) [Verify]. Light denibbing of nibs/runs; vacuum clean. Painting Supervisor Touch-dry and recoatability check
9 Topcoat 1 Mixing & Application Mix per datasheet. Cut-in edges; apply by roller with cross-rolling/back-rolling for uniformity. Record WFT. Painting Supervisor WFT checks
10 Intercoat DFT & Recoat Window After cure, measure interim DFT (ASTM D6132). Confirm recoat window not exceeded or surface re-abraded as required. QA/QC Inspector Witness
11 Topcoat 2 Application Apply second coat to achieve total specified DFT; maintain wet edge; avoid sags/runs. Painting Supervisor In-process
12 Final DFT & Finish Inspection Measure final DFT using ASTM D6132. Inspect finish under ≥ 300 lux for defects; rectify as required. QA/QC Inspector Hold Point: final DFT
13 Adhesion Testing (Representative) Perform pull-off (ASTM D4541) on discreet areas/panels; where not feasible, use ASTM D3359 cross-hatch. QA/QC Inspector Witness
14 Control Panels: Scrub & Impact Tests Coat standardized panels concurrently. After full cure (e.g., 7 days) test: ASTM D2486 scrub ≥ 5,000 cycles; ASTM D2794 impact ≥ 20 in-lb (direct) without failure. QA/QC / Third Party Lab Witness (as applicable)
15 Demasking, Touch-ups, Cleaning Remove masking within 24–48 h of final cure; repair edges; clean area; reinstate signage. Supervisor Visual
16 Handover & Safety Sign-offs Submit quality dossier; perform joint inspection; obtain Fire/Life Safety approval for corridor re-opening. PM / Consultant Hold Point: Handover

Safety Controls

Principal Hazards and Controls

  • Hazard: Work at height on stair flights/landings
  • Likely consequence: Fall from height causing serious injury
  • Engineering/procedural control: Use mobile towers to EN 1004 [Verify]; fit guardrails/toe boards; lock casters; use podium steps for short tasks; keep three points of contact; exclude public from working bay with barriers
  • Required PPE: Hard hat, non-slip safety footwear, gloves
  • Collective preventive measure: Edge protection, tower tags (inspected), controlled access
  • Inspection/permit/supervision: Daily pre-use tower inspection; Work at Height PTW; competent supervisor

  • Hazard: Stairwell egress obstruction

  • Likely consequence: Impeded evacuation during emergency
  • Engineering/procedural control: Phase works by half-flight; maintain minimum code-compliant width at all times; install illuminated detour arrows; no storage in escape route
  • PPE: High-visibility vest
  • Collective measures: Physical barriers and signs; spotter during material moves
  • Inspection/permit: Daily HSE walkthrough; approval from Fire/Life Safety officer [Verify per local regulations]

  • Hazard: Epoxy/amine sensitizers exposure (even water-based)

  • Likely consequence: Dermatitis, respiratory/eye irritation, sensitization
  • Engineering/procedural control: Closed mixing in drip trays; local ventilation achieving 4–10 ACH; use mixing lids; prohibit eating/drinking in area; SDS briefing
  • PPE: Nitrile gloves, safety goggles/face shield, disposable coveralls; half-mask respirator A1P2/ABEK1P2 where indicated by SDS [Verify]
  • Collective measures: Dedicated mixing station with spill kit; hand-wash station
  • Inspection/permit: COSHH assessment; HSE monitoring of ventilation log; supervisor sign-off

  • Hazard: Dust and silica from grinding/abrading

  • Likely consequence: Respiratory irritation, silicosis (long-term)
  • Engineering/procedural control: HEPA-shrouded grinders; wet-wipe and HEPA vacuum cleanup; limit dry sanding
  • PPE: P3 particulate respirator, goggles
  • Collective measures: Enclosure of local area with zipper screens; negative air machine if required
  • Inspection/permit: Hot Work permit if sparks; equipment PAT and inspection records

  • Hazard: Manual handling of paint/mortar and moving towers

  • Likely consequence: Strains/sprains, crush injuries
  • Engineering/procedural control: Team lifts; use trolleys; break down loads < 20 kg [Verify per local guidance]
  • PPE: Gloves, safety boots
  • Collective measures: Material staging on landings; clear travel paths
  • Inspection/permit: Manual handling training verification

  • Hazard: Electrical risks from temporary lighting and fans

  • Likely consequence: Electric shock, fire
  • Engineering/procedural control: RCD-protected circuits; cable management above floor level; weekly PAT where applicable
  • PPE: Insulated gloves for electricians
  • Collective measures: Lockable distribution boards; IP-rated connectors
  • Inspection/permit: Electrical PTW; competent electrician sign-off

  • Hazard: Noise from grinders/fans

  • Likely consequence: Hearing damage, disturbance to occupants
  • Engineering/procedural control: Low-noise equipment; time restrictions; maintain < 85 dBA at workface [Verify]
  • PPE: Hearing protection where required
  • Collective measures: Acoustic curtains where feasible
  • Inspection/permit: Noise monitoring logs

  • Hazard: Chemical spills/wash water discharge

  • Likely consequence: Slip hazards, environmental contamination
  • Engineering/procedural control: Mix over containment trays; no washings to drains; use absorbents; dedicated waste drums
  • PPE: Chemical-resistant gloves, goggles
  • Collective measures: Spill kits at mixing areas
  • Inspection/permit: Environmental permit/plan compliance

  • Hazard: Fire detectors/alarms overspray or contamination

  • Likely consequence: False alarms, impaired detection
  • Engineering/procedural control: Mask detectors with approved caps and reinstate daily; coordinate with Fire/Life Safety
  • PPE: Standard
  • Collective measures: Daily checklists; reinstatement log
  • Inspection/permit: Authorization from facility fire officer [Verify]

Environmental Controls

  • VOC and Odor Control: Select low-VOC water-based epoxy (≤ 100 g/L) [Verify]. Maintain 4–10 ACH ventilation; exhaust to exterior away from intakes/occupied zones.
  • Dust Control: Use HEPA extraction on grinding, HEPA vacuum cleanup, damp wipe surfaces. Avoid compressed air blow-downs.
  • Noise: Schedule noisy tasks during permitted hours; monitor to remain within project limits [Verify].
  • Waste Management: Segregate liquid epoxy/solvent waste from solid waste. No discharge to drains. Label containers; dispose via licensed handler.
  • Spill Prevention: Secondary containment at mixing; spill kits (absorbent pads, neutralizer) within 10 m of mixing area.
  • Lighting Energy: Use LED task lights; switch off outside work hours.
  • Material Efficiency: Batch sizes matched to pot life; record leftover volumes to optimize ordering.
  • Environmental Monitoring Records: Maintain logs for ACH, temperature, RH, and waste transfer notes.

QA/QC

Submittals

  • MIR with COC, TDS, SDS for primer/topcoat, repair mortars
  • Color and sheen samples; mock-up approval record

Calibration & Instruments

  • DFT gauge calibrated within 12 months (certificate on file)
  • Adhesion tester calibration verification/functional check prior to use
  • Hygrometer, thermometer, moisture meter with calibration evidence

Inspection & Testing Plan Highlights

  • Substrate Hold Point: after repairs and prep; verify moisture (ASTM D4263), pH (≤ 9), cleanliness (ASTM D4258)
  • In-Process WFT: First panel each shift then every 25 m²; adjust technique to meet target
  • Interim and Final DFT: ASTM D6132; minimum frequency 3 spots per 10 m², each spot = 3 readings
  • Acceptance for DFT: Average ≥ specified; ≥ 90% of readings ≥ minimum; none < 80% of minimum [Verify]
  • Adhesion: Representative areas/panels; pull-off ≥ 1.0–1.5 MPa or cross-hatch ≥ 4B [Verify]
  • Finish: Visual under ≥ 300 lux; no sags/runs/holidays; color uniformity
  • Control Panels: ASTM D2486 scrub ≥ 5,000 cycles; ASTM D2794 impact ≥ 20 in-lb direct [Verify]

Documentation

  • Batch mixing logs (time, ratio, pot life start/end, environmental conditions)
  • WFT/DFT logs, adhesion test reports, environmental logs
  • NCR and corrective action records
  • Final handover package: As-built color schedule, warranties, maintenance/cleaning recommendations

Hold/Witness Points

  • HP1: Substrate acceptance (Engineer/Consultant)
  • WP1: Interim DFT after first topcoat
  • HP2: Final DFT and finish
  • WP2: Adhesion tests
  • WP3: Control panel results review

Attachments

  • Manufacturer Technical Data Sheets (Primer, Topcoat)
  • Safety Data Sheets (SDS)
  • Mixing and Application Checklist
  • Environmental Monitoring Log (T, RH, DP, ACH)
  • WFT/DFT Recording Sheets
  • Adhesion Test Report Template
  • Mock-up Approval Form
  • Daily Pre-start and Close-out Checklists
  • Permit-to-Work Forms (Work at Height, Electrical, Hot Work if applicable)
  • Handover/Sign-off Certificate

This content is a read-only public reference. Download or customize to get an editable version.

ITP preview

The first inspection activities from the linked ITP for Method Statement: Scrubbable Water-Based Epoxy Wall Painting for Emergency Stairwells:

ActivityInspection / TestAcceptance CriteriaResponsibilityRecord
Materials receipt (primer/topcoat)Review COC/TDS/SDS; visual for damageConforms to submittals; within shelf life; unopenedQA/QC InspectorMIR, delivery inspection form
Mock-up preparation and approvalColor, sheen, texture; DFT checkApproved sample panel; DFT within rangeSite Engineer / ConsultantMock-up approval
Masonry repair inspectionVisual soundness; cure timeRepairs flush, sound, cured per TDSEngineer / QA/QCWIR sign-off, photos

Showing 3 of 14 inspection activities. View full ITP →

Related Inspection and Test Plan

An Inspection and Test Plan (ITP) is available for Method Statement: Scrubbable Water-Based Epoxy Wall Painting for Emergency Stairwells. The ITP defines the inspection activities, acceptance criteria, hold and witness points, responsible parties, and records required to verify the work described in this method statement.

View the Method Statement: Scrubbable Water-Based Epoxy Wall Painting for Emergency Stairwells ITP →

Frequently asked questions

Substrate temperature 10–35 °C, at least 3 °C above dew point, RH ≤ 85%, acceptable moisture (ASTM D4263) and pH ≤ 9. Verify per manufacturer and project specs.

Using an ultrasonic DFT gauge per ASTM D6132. Take at least 3 spot measurements per 10 m², each spot comprising 3 readings, and log results.

Control panels coated alongside site works are tested per ASTM D2486. Acceptance is typically ≥ 5,000 cycles to failure [Verify per project specs].

Use ASTM D3359 cross-hatch adhesion on discreet areas or test on representative panels. Obtain Consultant approval for alternative verification.

Works are phased by half-flights, barriers/signage are installed, and the minimum code-compliant route width is maintained at all times. Coordination with Fire/Life Safety is required.