Method Statement: Scrubbable Water-Based Epoxy Wall Painting for Emergency Stairwells – Method Statement
AI-assisted method statement with matching ITP, PDF download, and Excel export.
More than a static template
Unlike a downloadable Word or PDF template, this method statement is an AI-assisted editable starting point connected directly to a matching Inspection and Test Plan. Every section is structured, project-adaptable, and ready to export.
- AI-assisted drafting — Customize every section with AI for your specific project scope.
- Linked ITP — A matching inspection and test plan is generated alongside the method statement.
- Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
- Editable starting point, not a final document — Review, verify, and adjust all content against your project requirements before use.
Static template vs. Quollnet workflow
| Feature | Static template | Quollnet |
|---|---|---|
| Project-specific content | Manual fill-in required | AI-assisted customization |
| Linked ITP | Separate document, no link | Matching ITP included |
| Export formats | Usually PDF only | PDF and Excel |
| Structured sections | Free-form layout | 13 standardized sections |
| Saved to your account | Local file only | Cloud-saved, reusable |
| Content accuracy | You verify everything | AI-assisted, you still verify |
| Cost | Often free but time-intensive | Free to customize and download |
What you can customize
When you save this method statement to your account, every section becomes editable. The following 13 sections are included:
- Scope — Defines the activity and its boundaries.
- References — Standards, specifications, and drawings.
- Responsibilities — Roles and accountabilities.
- Resources — Labour, plant, and equipment summary.
- Materials — Materials and compliance requirements.
- Equipment — Tools and equipment details.
- Prerequisites — Hold points and pre-conditions.
- Method sequence — Step-by-step construction sequence.
- Safety controls — HSE risk controls and PPE.
- Environmental controls — Environmental mitigation measures.
- QA/QC — Quality inspection and test requirements.
- ITP — Inspection and Test Plan table (has its own page).
- Attachments — Referenced drawings and documentation.
Why this method statement is used
This method statement is used to define and communicate the approved procedure for carrying out method statement: scrubbable water-based epoxy wall painting for emergency stairwells on site. It ensures the work is planned in advance, the correct resources and controls are in place, and all personnel understand responsibilities, sequence, quality requirements, and safety controls before work begins. It aligns site execution with the documented scope and acceptance expectations.
Who uses this method statement
This method statement is used by contractors, site supervisors, project engineers, QA/QC engineers, HSE officers, consultants, and client representatives. It serves as a shared reference for planning, execution, supervision, inspection, and approval of the activity on site.
When it is prepared and submitted
The method statement is prepared before the work activity starts and submitted as part of the pre-construction documentation package for review and approval.
Who reviews or approves it
The method statement is usually submitted to the client representative, consultant, resident engineer, or project management consultant for review and approval before the work commences.
Important approval note
This method statement is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all content must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.
For example: if your specification requires a departure from a referenced standard, that departure must be documented and approved separately — this method statement will not capture that automatically. Always verify against your applicable drawings, specifications, and regulatory requirements.
Method statement content
Scope
Overview
This method statement covers end-to-end delivery of a scrubbable water-based epoxy coating system to emergency stairwell walls across multiple floors, including:
- Masonry assessment and repair (crack/spall patching, void filling, edge arrises)
- Protection and masking of installed corner guards, handrails, signage, fixtures
- Surface preparation, cleaning, and environmental conditioning
- Application of epoxy primer and two finish coats by roller
- Temporary lighting provision and maintenance (workface ≥ 300 lux) [Verify per project specifications]
- Mechanical ventilation setups to control humidity, odor, and cure (target 4–10 ACH) [Verify per project HSE plan]
- In-process WFT and post-cure DFT verification, adhesion testing
- Scrub and impact resistance verification on control panels
- Final cleaning, reinstatement, and safety exit corridor handover sign-offs
Areas Included
- Stairwell walls (concrete/masonry block/plaster skim as applicable)
- Stringer soffits, wall returns at landings, and door reveals (if specified)
Exclusions
- Structural repairs beyond minor masonry patching
- Floor coating, ceiling painting, steelwork painting (unless noted)
- New corner guard installation (masking/protection only unless otherwise instructed)
Key Performance Targets [Verify per project specifications]
- Total DFT (primer + 2 topcoats): 120–200 µm total
- Adhesion to substrate: ≥ 1.0–1.5 MPa (ASTM D4541) or Cross-hatch ≥ 4B (ASTM D3359) where pull-off impractical
- Scrub resistance (ASTM D2486) on control panel: ≥ 5,000 cycles to defined end-point
- Impact resistance (ASTM D2794) on control panel: ≥ 20 in-lb (2.26 J) direct without cracking/delamination
- Uniformity: No sags, runs, pinholes, dry spray, color mismatch visible at 1.5 m under 300–500 lux lighting
- Egress: Maintain code-compliant escape route width and signage throughout the works [Verify per local code]
References
| Document Type | Reference / Number | Revision | Notes |
|---|---|---|---|
| Standard | ASTM D6132 | ||
| Standard | ASTM D4414 | Use notch/comb gauges at start and during works. | |
| Standard | ASTM D4258 | ||
| Standard | ASTM D4259 | Avoid acid etching in enclosed stairwells unless specifically approved. | |
| Standard | ASTM D4263 | Supplement with electrical moisture meter as required. | |
| Standard | ASTM D4541 / ISO 4624 | Use dollies suitable for masonry; avoid damage to fire-rated walls without approval. | |
| Standard | ASTM D3359 | Method A/B per film thickness and substrate hardness. | |
| Standard | ASTM D2486 | Laboratory or approved third-party test on concurrently coated panels. | |
| Standard | ASTM D2794 | Performed on standardized panels coated alongside site works. | |
| Standard | ASTM D3960 / ISO 11890-2 | As declared by manufacturer and verified by data sheet/COC. |
Responsibilities
| Role | Responsibility | Name / Party |
|---|---|---|
| PM | Approve RAMS, ensure egress plan maintained, approve access sequencing | Contractor |
| Engineer | Verifies substrate condition, environmental compliance, WFT/DFT tracking | Contractor |
| QA/QC | Witness/hold points, test frequency, NCR control | Contractor |
| HSE | Ventilation plan, exposure controls, egress integrity | Contractor |
| Supervisor | Batch control, pot life, recoat window, film build | Contractor |
| Consultant | Approves substrates, color/finish, final handover | Engineer/Employer |
Resources
| Resource Type | Description | Quantity | Remarks |
|---|---|---|---|
| Labor | Epoxy systems experienced | As scheduled | |
| Labor | Minor patch/repair works | As required | |
| Labor | Install/maintain task lighting and safe power | 1 | |
| Labor | Daily inspections, permits, toolbox talks | 1 |
Materials
| Material | Specification / Grade | Quantity | Remarks |
|---|---|---|---|
| Epoxy primer | Manufacturer-approved for topcoat | As BOQ | |
| Epoxy topcoat | Total system DFT 120–200 µm [Verify] | As BOQ | |
| Repair mortar | For thin patch 5–30 mm | As required | |
| Acrylic/epoxy filler | Manufacturer-approved | As required | |
| Cleaner | As required | ||
| Masking | As required |
Equipment
| Equipment | Capacity / Type | Quantity | Inspection Required |
|---|---|---|---|
| Rollers/brushes | Sets per crew | ||
| Mixer | 1 per crew | ||
| WFT gauge | 2 | ||
| DFT gauge | 1 | ||
| Adhesion tester | 1 | ||
| Meters | 1 set | ||
| Access | As required | ||
| Ventilation | Per stairwell | ||
| Lighting | Per bay |
Prerequisites
- Approved Method Statement and ITP; COSHH/SDS available on site
- MIR approvals for primer and topcoat; color schedule and sheen confirmed
- Access and egress plan agreed with Facilities/Fire Safety: maintain code-compliant route width and two-way communication [Verify per local code]
- Permit-to-Work: Work at Height, Electrical (temporary power), Hot Work if grinding, and area isolation [Verify per project HSE plan]
- Mock-up sample area (min 2 m²) approved for color/texture/finish and DFT approach
- Substrate readiness: masonry repairs completed and cured; moisture test acceptable (ASTM D4263) and pH ≤ 9 [Verify]
- Environmental control plan: ventilation path, noise hours, odor control; confirm no impact to occupied areas
- Calibrations in date for DFT gauge and adhesion tester; inspection checklists ready
- Corner guard protection and masking materials available; sequence agreed with building operations
- Emergency staircase signage/alternative routing coordinated for active work zones
Method Sequence
| Step | Activity | Description | Responsibility | Inspection / Hold Point |
|---|---|---|---|---|
| 1 | Site Induction, Permits, Area Isolation | Conduct task-specific induction and toolbox talk. Obtain PTW. Barricade active work zone; maintain emergency egress route width per code; display detour signage. | HSE Manager / Supervisor | Permit/Barrier check |
| 2 | Temporary Lighting & Ventilation Setup | Install LED lights to achieve ≥ 300 lux on wall face. Set fans/ducting to achieve target 4–10 ACH; measure and log temperature and RH. | Electrician / Supervisor | Lux/RH/Temp reading |
| 3 | Protection & Masking | Mask corner guards, handrails, signage, and floor intersections with low-tack tape and protective film. Install drop sheets; protect fire devices (without obstructing function). | Supervisor | Visual |
| 4 | Masonry Inspection & Repairs | Sound the substrate; mark defects. Grind loose/unsound areas. Patch with polymer-modified mortar (5–30 mm). Tool and finish to level. Cure 24–48 h or per datasheet. | Mason / Engineer | WIR: substrate/repairs |
| 5 | Surface Preparation & Cleaning | Detergent wash (ASTM D4258), rinse, dry. Mechanically abrade glossy/contaminated areas (ASTM D4259). Remove dust with HEPA vacuum and lint-free wipes. | Supervisor | Cleanliness check |
| 6 | Substrate Condition Checks | Verify moisture (ASTM D4263 16–24 h plastic sheet) and/or moisture meter; pH ≤ 9; ambient T 10–35 °C, RH ≤ 85%, substrate ≥ 3 °C above dew point. | Site Engineer | Hold Point: substrate acceptance |
| 7 | Primer Mixing & Application | Stir A & B separately, then combine per mix ratio; mix 2–3 min. Observe induction time if required (10–20 min) [Verify]. Apply by roller; target WFT to achieve specified DFT. | Painting Supervisor | WFT spot checks |
| 8 | Primer Cure & Sand (if required) | Allow to cure as per TDS (e.g., 4–8 h at 25 °C) [Verify]. Light denibbing of nibs/runs; vacuum clean. | Painting Supervisor | Touch-dry and recoatability check |
| 9 | Topcoat 1 Mixing & Application | Mix per datasheet. Cut-in edges; apply by roller with cross-rolling/back-rolling for uniformity. Record WFT. | Painting Supervisor | WFT checks |
| 10 | Intercoat DFT & Recoat Window | After cure, measure interim DFT (ASTM D6132). Confirm recoat window not exceeded or surface re-abraded as required. | QA/QC Inspector | Witness |
| 11 | Topcoat 2 Application | Apply second coat to achieve total specified DFT; maintain wet edge; avoid sags/runs. | Painting Supervisor | In-process |
| 12 | Final DFT & Finish Inspection | Measure final DFT using ASTM D6132. Inspect finish under ≥ 300 lux for defects; rectify as required. | QA/QC Inspector | Hold Point: final DFT |
| 13 | Adhesion Testing (Representative) | Perform pull-off (ASTM D4541) on discreet areas/panels; where not feasible, use ASTM D3359 cross-hatch. | QA/QC Inspector | Witness |
| 14 | Control Panels: Scrub & Impact Tests | Coat standardized panels concurrently. After full cure (e.g., 7 days) test: ASTM D2486 scrub ≥ 5,000 cycles; ASTM D2794 impact ≥ 20 in-lb (direct) without failure. | QA/QC / Third Party Lab | Witness (as applicable) |
| 15 | Demasking, Touch-ups, Cleaning | Remove masking within 24–48 h of final cure; repair edges; clean area; reinstate signage. | Supervisor | Visual |
| 16 | Handover & Safety Sign-offs | Submit quality dossier; perform joint inspection; obtain Fire/Life Safety approval for corridor re-opening. | PM / Consultant | Hold Point: Handover |
Safety Controls
Principal Hazards and Controls
- Hazard: Work at height on stair flights/landings
- Likely consequence: Fall from height causing serious injury
- Engineering/procedural control: Use mobile towers to EN 1004 [Verify]; fit guardrails/toe boards; lock casters; use podium steps for short tasks; keep three points of contact; exclude public from working bay with barriers
- Required PPE: Hard hat, non-slip safety footwear, gloves
- Collective preventive measure: Edge protection, tower tags (inspected), controlled access
-
Inspection/permit/supervision: Daily pre-use tower inspection; Work at Height PTW; competent supervisor
-
Hazard: Stairwell egress obstruction
- Likely consequence: Impeded evacuation during emergency
- Engineering/procedural control: Phase works by half-flight; maintain minimum code-compliant width at all times; install illuminated detour arrows; no storage in escape route
- PPE: High-visibility vest
- Collective measures: Physical barriers and signs; spotter during material moves
-
Inspection/permit: Daily HSE walkthrough; approval from Fire/Life Safety officer [Verify per local regulations]
-
Hazard: Epoxy/amine sensitizers exposure (even water-based)
- Likely consequence: Dermatitis, respiratory/eye irritation, sensitization
- Engineering/procedural control: Closed mixing in drip trays; local ventilation achieving 4–10 ACH; use mixing lids; prohibit eating/drinking in area; SDS briefing
- PPE: Nitrile gloves, safety goggles/face shield, disposable coveralls; half-mask respirator A1P2/ABEK1P2 where indicated by SDS [Verify]
- Collective measures: Dedicated mixing station with spill kit; hand-wash station
-
Inspection/permit: COSHH assessment; HSE monitoring of ventilation log; supervisor sign-off
-
Hazard: Dust and silica from grinding/abrading
- Likely consequence: Respiratory irritation, silicosis (long-term)
- Engineering/procedural control: HEPA-shrouded grinders; wet-wipe and HEPA vacuum cleanup; limit dry sanding
- PPE: P3 particulate respirator, goggles
- Collective measures: Enclosure of local area with zipper screens; negative air machine if required
-
Inspection/permit: Hot Work permit if sparks; equipment PAT and inspection records
-
Hazard: Manual handling of paint/mortar and moving towers
- Likely consequence: Strains/sprains, crush injuries
- Engineering/procedural control: Team lifts; use trolleys; break down loads < 20 kg [Verify per local guidance]
- PPE: Gloves, safety boots
- Collective measures: Material staging on landings; clear travel paths
-
Inspection/permit: Manual handling training verification
-
Hazard: Electrical risks from temporary lighting and fans
- Likely consequence: Electric shock, fire
- Engineering/procedural control: RCD-protected circuits; cable management above floor level; weekly PAT where applicable
- PPE: Insulated gloves for electricians
- Collective measures: Lockable distribution boards; IP-rated connectors
-
Inspection/permit: Electrical PTW; competent electrician sign-off
-
Hazard: Noise from grinders/fans
- Likely consequence: Hearing damage, disturbance to occupants
- Engineering/procedural control: Low-noise equipment; time restrictions; maintain < 85 dBA at workface [Verify]
- PPE: Hearing protection where required
- Collective measures: Acoustic curtains where feasible
-
Inspection/permit: Noise monitoring logs
-
Hazard: Chemical spills/wash water discharge
- Likely consequence: Slip hazards, environmental contamination
- Engineering/procedural control: Mix over containment trays; no washings to drains; use absorbents; dedicated waste drums
- PPE: Chemical-resistant gloves, goggles
- Collective measures: Spill kits at mixing areas
-
Inspection/permit: Environmental permit/plan compliance
-
Hazard: Fire detectors/alarms overspray or contamination
- Likely consequence: False alarms, impaired detection
- Engineering/procedural control: Mask detectors with approved caps and reinstate daily; coordinate with Fire/Life Safety
- PPE: Standard
- Collective measures: Daily checklists; reinstatement log
- Inspection/permit: Authorization from facility fire officer [Verify]
Environmental Controls
- VOC and Odor Control: Select low-VOC water-based epoxy (≤ 100 g/L) [Verify]. Maintain 4–10 ACH ventilation; exhaust to exterior away from intakes/occupied zones.
- Dust Control: Use HEPA extraction on grinding, HEPA vacuum cleanup, damp wipe surfaces. Avoid compressed air blow-downs.
- Noise: Schedule noisy tasks during permitted hours; monitor to remain within project limits [Verify].
- Waste Management: Segregate liquid epoxy/solvent waste from solid waste. No discharge to drains. Label containers; dispose via licensed handler.
- Spill Prevention: Secondary containment at mixing; spill kits (absorbent pads, neutralizer) within 10 m of mixing area.
- Lighting Energy: Use LED task lights; switch off outside work hours.
- Material Efficiency: Batch sizes matched to pot life; record leftover volumes to optimize ordering.
- Environmental Monitoring Records: Maintain logs for ACH, temperature, RH, and waste transfer notes.
QA/QC
Submittals
- MIR with COC, TDS, SDS for primer/topcoat, repair mortars
- Color and sheen samples; mock-up approval record
Calibration & Instruments
- DFT gauge calibrated within 12 months (certificate on file)
- Adhesion tester calibration verification/functional check prior to use
- Hygrometer, thermometer, moisture meter with calibration evidence
Inspection & Testing Plan Highlights
- Substrate Hold Point: after repairs and prep; verify moisture (ASTM D4263), pH (≤ 9), cleanliness (ASTM D4258)
- In-Process WFT: First panel each shift then every 25 m²; adjust technique to meet target
- Interim and Final DFT: ASTM D6132; minimum frequency 3 spots per 10 m², each spot = 3 readings
- Acceptance for DFT: Average ≥ specified; ≥ 90% of readings ≥ minimum; none < 80% of minimum [Verify]
- Adhesion: Representative areas/panels; pull-off ≥ 1.0–1.5 MPa or cross-hatch ≥ 4B [Verify]
- Finish: Visual under ≥ 300 lux; no sags/runs/holidays; color uniformity
- Control Panels: ASTM D2486 scrub ≥ 5,000 cycles; ASTM D2794 impact ≥ 20 in-lb direct [Verify]
Documentation
- Batch mixing logs (time, ratio, pot life start/end, environmental conditions)
- WFT/DFT logs, adhesion test reports, environmental logs
- NCR and corrective action records
- Final handover package: As-built color schedule, warranties, maintenance/cleaning recommendations
Hold/Witness Points
- HP1: Substrate acceptance (Engineer/Consultant)
- WP1: Interim DFT after first topcoat
- HP2: Final DFT and finish
- WP2: Adhesion tests
- WP3: Control panel results review
Attachments
- Manufacturer Technical Data Sheets (Primer, Topcoat)
- Safety Data Sheets (SDS)
- Mixing and Application Checklist
- Environmental Monitoring Log (T, RH, DP, ACH)
- WFT/DFT Recording Sheets
- Adhesion Test Report Template
- Mock-up Approval Form
- Daily Pre-start and Close-out Checklists
- Permit-to-Work Forms (Work at Height, Electrical, Hot Work if applicable)
- Handover/Sign-off Certificate
This content is a read-only public reference. Download or customize to get an editable version.
ITP preview
The first inspection activities from the linked ITP for Method Statement: Scrubbable Water-Based Epoxy Wall Painting for Emergency Stairwells:
| Activity | Inspection / Test | Acceptance Criteria | Responsibility | Record |
|---|---|---|---|---|
| Materials receipt (primer/topcoat) | Review COC/TDS/SDS; visual for damage | Conforms to submittals; within shelf life; unopened | QA/QC Inspector | MIR, delivery inspection form |
| Mock-up preparation and approval | Color, sheen, texture; DFT check | Approved sample panel; DFT within range | Site Engineer / Consultant | Mock-up approval |
| Masonry repair inspection | Visual soundness; cure time | Repairs flush, sound, cured per TDS | Engineer / QA/QC | WIR sign-off, photos |
Showing 3 of 14 inspection activities. View full ITP →
Related Inspection and Test Plan
An Inspection and Test Plan (ITP) is available for Method Statement: Scrubbable Water-Based Epoxy Wall Painting for Emergency Stairwells. The ITP defines the inspection activities, acceptance criteria, hold and witness points, responsible parties, and records required to verify the work described in this method statement.
View the Method Statement: Scrubbable Water-Based Epoxy Wall Painting for Emergency Stairwells ITP →