Method Statement: Scrubbable Water-Based Epoxy Wall Painting for Emergency Stairwells inspection and test plan example.

Inspection and Test Plan for Method Statement: Scrubbable Water-Based Epoxy Wall Painting for Emergency Stairwells

AI-assisted inspection and test plan connected to a method statement, with PDF and Excel export.

Published 24 Nov 2026 Rev. 00 5 views 1 downloads
About this ITP: Defines inspections and tests for epoxy stairwell wall painting, including substrate hold points, WFT/DFT checks, adhesion, and durability verification.

More than a static template

Unlike a downloadable Word or PDF template, this ITP is an AI-assisted editable starting point directly connected to its method statement. Every inspection activity, hold point, and acceptance criterion is structured and ready to adapt to your project.

  • AI-assisted customization — Tailor inspection activities and acceptance criteria to your specific project scope.
  • Linked method statement — This ITP is connected to the corresponding method statement describing the work sequence.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review and verify all content against your project specifications and standards before use.

What you can customize

When you save this ITP to your account, every inspection row becomes editable. You can add, remove, or modify:

  • Inspection activity — Description of what is being inspected.
  • Inspection type — Hold point (H), Witness point (W), Review (R), or Monitor (M).
  • Responsibility — Contractor, subcontractor, engineer, or client.
  • Frequency — How often the inspection occurs.
  • Acceptance criteria — Referenced standard or specification requirement.
  • Records — Forms, test reports, or checklists required as evidence.

Why this ITP is used

To ensure coatings meet durability, safety, and aesthetic requirements in critical egress routes through defined inspection and testing.

Who uses this inspection and test plan

Contractor QA/QC, Site Engineer, Consultant/Client Representative, and HSE personnel.

When this ITP is prepared and submitted

From material receipt to final handover, with hold/witness points at key stages such as substrate acceptance and final DFT.

Who receives or approves this ITP

Consultant/Engineer for review and approval.

Inspection scope

Materials verification, substrate readiness, in-process WFT, interim/final DFT, adhesion, durability panels, and final acceptance.

Typical hold, witness, and review points

Substrate hold point, interim DFT witness, final DFT hold point, adhesion witness, handover hold point.

Typical inspection records

MIRs, WIRs, WFT/DFT logs, adhesion test reports, environmental logs, lab certificates, handover certificates.

Important approval note

This ITP is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all inspection activities, hold points, and acceptance criteria must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

Always verify acceptance criteria against your applicable drawings, specifications, and regulatory requirements. Hold points must be confirmed with the relevant authority before work proceeds past that point.

Inspection and test plan

Activity Inspection / Test Acceptance Criteria Responsibility Record
Materials receipt (primer/topcoat) Review COC/TDS/SDS; visual for damage Conforms to submittals; within shelf life; unopened QA/QC Inspector MIR, delivery inspection form
Mock-up preparation and approval Color, sheen, texture; DFT check Approved sample panel; DFT within range Site Engineer / Consultant Mock-up approval
Masonry repair inspection Visual soundness; cure time Repairs flush, sound, cured per TDS Engineer / QA/QC WIR sign-off, photos
Surface preparation cleanliness ASTM D4258/D4259 references; dust wipe Free of dust/grease; uniform profile QA/QC Prep checklist
Substrate condition hold point Moisture (ASTM D4263), pH, T/RH/DP Within manufacturer/project limits [Verify] Consultant / Engineer Substrate inspection form
Primer application in-process WFT checks (ASTM D4414) WFT targets met; uniform coverage Supervisor / QA/QC WFT log
Intercoat inspection after primer Cleanliness; readiness to recoat Tack-free; no contaminants QA/QC Intercoat report
Topcoat 1 application WFT checks; visual Uniform film; no defects Supervisor / QA/QC WFT log, daily report
Interim DFT after Topcoat 1 DFT (ASTM D6132) Within specified interim range [Verify] QA/QC / Consultant DFT log
Topcoat 2 application WFT checks; visual finish Uniform, defect-free Supervisor / QA/QC WFT log, daily report
Final DFT and finish hold point DFT (ASTM D6132); visual under ≥ 300 lux Average ≥ specified; no reading < 80% of min [Verify]; finish acceptable QA/QC / Consultant DFT log, punch list
Adhesion testing (representative) ASTM D4541 or ASTM D3359 ≥ 1.0–1.5 MPa or ≥ 4B [Verify] QA/QC Adhesion test report
Control panels durability tests ASTM D2486 scrub; ASTM D2794 impact Meets specified values [Verify] Third-party Lab / QA/QC Lab certificates
Final handover inspection Documentation review; visual walkdown All ITP points closed; NCRs cleared; egress reinstated PM / Consultant Handover certificate

This table is a read-only public reference. Download the PDF or Excel version, or customize this ITP to edit it for your project.

Frequently asked questions

Typically 3 spot measurements per 10 m² per coat, with each spot comprising 3 gauge readings. Adjust per project specs.

Yes, when specified for durability verification. Panels are coated concurrently and tested for scrub (ASTM D2486) and impact (ASTM D2794).

Related method statement

This Inspection and Test Plan is associated with the Method Statement: Scrubbable Water-Based Epoxy Wall Painting for Emergency Stairwells method statement, which describes the step-by-step construction sequence, resources, materials, equipment, safety controls, and environmental controls for this activity.

View the Method Statement: Scrubbable Water-Based Epoxy Wall Painting for Emergency Stairwells method statement →