Method Statement for Installation of Round Spiral Galvanized Steel Ductwork – Method Statement
AI-assisted method statement with matching ITP, PDF download, and Excel export.
More than a static template
Unlike a downloadable Word or PDF template, this method statement is an AI-assisted editable starting point connected directly to a matching Inspection and Test Plan. Every section is structured, project-adaptable, and ready to export.
- AI-assisted drafting — Customize every section with AI for your specific project scope.
- Linked ITP — A matching inspection and test plan is generated alongside the method statement.
- Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
- Editable starting point, not a final document — Review, verify, and adjust all content against your project requirements before use.
Static template vs. Quollnet workflow
| Feature | Static template | Quollnet |
|---|---|---|
| Project-specific content | Manual fill-in required | AI-assisted customization |
| Linked ITP | Separate document, no link | Matching ITP included |
| Export formats | Usually PDF only | PDF and Excel |
| Structured sections | Free-form layout | 13 standardized sections |
| Saved to your account | Local file only | Cloud-saved, reusable |
| Content accuracy | You verify everything | AI-assisted, you still verify |
| Cost | Often free but time-intensive | Free to customize and download |
What you can customize
When you save this method statement to your account, every section becomes editable. The following 13 sections are included:
- Scope — Defines the activity and its boundaries.
- References — Standards, specifications, and drawings.
- Responsibilities — Roles and accountabilities.
- Resources — Labour, plant, and equipment summary.
- Materials — Materials and compliance requirements.
- Equipment — Tools and equipment details.
- Prerequisites — Hold points and pre-conditions.
- Method sequence — Step-by-step construction sequence.
- Safety controls — HSE risk controls and PPE.
- Environmental controls — Environmental mitigation measures.
- QA/QC — Quality inspection and test requirements.
- ITP — Inspection and Test Plan table (has its own page).
- Attachments — Referenced drawings and documentation.
Why this method statement is used
This method statement is used to define and communicate the approved procedure for carrying out method statement for installation of round spiral galvanized steel ductwork on site. It ensures the work is planned in advance, the correct resources and controls are in place, and all personnel understand responsibilities, sequence, quality requirements, and safety controls before work begins. It aligns site execution with the documented scope and acceptance expectations.
Who uses this method statement
This method statement is used by contractors, site supervisors, project engineers, QA/QC engineers, HSE officers, consultants, and client representatives. It serves as a shared reference for planning, execution, supervision, inspection, and approval of the activity on site.
When it is prepared and submitted
The method statement is prepared before the work activity starts and submitted as part of the pre-construction documentation package for review and approval.
Who reviews or approves it
The method statement is usually submitted to the client representative, consultant, resident engineer, or project management consultant for review and approval before the work commences.
Important approval note
This method statement is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all content must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.
For example: if your specification requires a departure from a referenced standard, that departure must be documented and approved separately — this method statement will not capture that automatically. Always verify against your applicable drawings, specifications, and regulatory requirements.
Method statement content
Scope and Document Control
Document control
- project_name:
- method_date: {today} — resolve to the issue date in YYYY-MM-DD format before submission.
- submitted_by:
- submitted_to:
Work covered
This method covers receipt, setting out, support installation, assembly, sealing, damper installation, inspection, and handover of suspended indoor round spiral galvanized steel ductwork. It applies to straight ducts, round fittings, internal coupling sleeves, ring brackets, and manual or actuated volume control dampers (VCDs) where scheduled. It includes coordination with cable trays, conduits, pipework, plumbing gradients, ceiling systems, and maintenance access.
Duct insulation, final air balancing, actuator wiring, and firestopping are carried out under their respective approved methods. This method defines the release and interface checks for those trades. A volume control damper is not a fire or smoke damper. Do not use this method to install a fire or smoke damper, or to install grease exhaust, hazardous exhaust, smoke-control ductwork, or exterior ductwork without a separate approved method.
Applicable Documents and Standards
| Document Type | Reference / Number | Revision | Notes |
|---|---|---|---|
| Contract documents | Mechanical specification; issued-for-construction drawings; duct and damper schedules; approved coordinated shop drawings; approved project ITP | Current approved revisions | Apply the contract order of precedence; refer conflicts for written resolution before proceeding. |
| Duct construction standard | SMACNA HVAC Duct Construction Standards—Metal and Flexible; or BS EN 1506 and BS EN 12237 where the EN route is specified | Contract-specified editions | Use the specified design route. BS EN 1506 addresses circular duct dimensions; BS EN 12237 addresses strength and leakage. Do not treat the two routes as interchangeable for acceptance. |
| Leakage test standard | SMACNA HVAC Air Duct Leakage Test Manual or BS EN 12237, as specified | Contract-specified edition | Confirm test pressure and sign, leakage criterion, test extent, and reporting basis before testing. |
| Galvanized steel material standards | ASTM A653/A653M or BS EN 10346, as specified | Contract-specified edition | Verify base metal thickness and coating designation separately against approved material data. |
| Damper product standard and instructions | BS EN 1751 where specified; approved damper schedule and manufacturer installation instructions | Current approved submittal | Use the specified product ratings. A damper product leakage rating does not establish installed duct-system leakage acceptance. |
| Installation and structural approvals | Approved support and anchor details; anchor manufacturer instructions and applicable approval; approved duct, sleeve, fastener and mastic product data | Current approved submittals | Include structural drilling restrictions, hanger loading, coupling engagement, sealant application limits, and curing requirements. |
Roles and Responsibilities
| Role | Responsibility | Name / Party |
|---|---|---|
| Mechanical Site Engineer | Mechanical contractor | |
| MEP Coordinator | Main contractor / MEP contractor | |
| HVAC Supervisor | Mechanical contractor | |
| QA/QC Inspector | Mechanical contractor | |
| HSE Supervisor | Main contractor / mechanical contractor | |
| Engineer / Client Representative | As designated by the contract |
Personnel and Specialist Resources
| Resource Type | Description | Quantity | Remarks |
|---|---|---|---|
| Supervision | Lead setting out, bracket installation, assembly and daily coordination. | One designated lead per active workfront | |
| Installation crew | Install approved anchors, duct supports, joints, mastic and VCDs. | Crew size based on item weight, length and access assessment | Provide trained anchor installers where required by the approval or contract. |
| Specialist support | Operate access or lifting equipment and control the exclusion zone where mechanical lifting is required. | As required by access and lifting plan | |
| Inspection and testing | Conduct inspections and perform specified anchor or leakage tests with suitable instruments. | As required by ITP |
Materials
| Material | Specification / Grade | Quantity | Remarks |
|---|---|---|---|
| Round spiral galvanized steel duct and fittings | Approved diameters, base metal thickness, zinc coating, pressure class and joint construction. | Per approved takeoff | |
| Coupling sleeves and fasteners | Approved diameter, engagement, fastener type, corrosion compatibility and fastening pattern. | Per joint schedule | Use gasketed sleeves only where the approved detail specifies them; follow the manufacturer's sealing instructions. |
| Duct mastic and reinforcement | Approved for galvanized steel, specified operating conditions and project fire/smoke requirements. | Per joint area and product coverage | Verify batch, expiry, substrate compatibility and product storage limits. |
| Ring brackets and suspension components | Approved dimensions, substrate suitability, load capacity and required restraint details. | Per approved support schedule | Maintain specified finish and corrosion compatibility. Do not substitute hanger or anchor components without approval. |
| Round volume control dampers | Approved diameter, pressure rating, casing connections, operating arrangement and scheduled performance. | Per damper schedule | Check handle, quadrant and lock or actuator and linkage as applicable. |
Plant, Tools and Inspection Equipment
| Equipment | Capacity / Type | Quantity | Inspection Required |
|---|---|---|---|
| Inspected mobile tower or mobile elevating work platform | Rated for personnel and tools at the required working height; do not use as a duct lifting device unless explicitly approved for that task. | Pre-use and statutory/project inspections | |
| Rated duct lift or approved hoist and rigging | Working load limit sufficient for the verified load and lifting configuration. | Pre-use checks and current certification where required | |
| Substrate scanner, drill, dust extraction, depth gauge, hole-cleaning kit and torque wrench | Suitable for actual substrate and approved anchor diameter, depth and torque. | Pre-use checks and valid calibration for torque wrench where required | |
| Laser level, tape, sheet-metal cutter, deburring tool, fastening tool, sealant applicators, inspection light and mirror | Suitable for duct sizes and approved workmanship criteria. | Pre-use condition and measurement verification | |
| Duct leakage tester, differential pressure instrument and rated test blanks | Measuring range and resolution suited to specified pressure and allowable leakage; blanks and restraints suitable for test loads. | Current calibration and pre-test setup check |
Prerequisites and Workfront Release
- Obtain approval of coordinated plans and sections, duct and fitting schedules, material submittals, joint and support details, damper access details, risk assessment and ITP. Resolve open clashes and technical queries affecting the workfront.
- Confirm duct diameters, metal thickness and coating, pressure and leakage classes, hanger spacing, support loads and restraints, anchor details, coupling insertion and fastening requirements, and mastic application and curing limits. Enter the approved values on installation checklists. Do not derive anchor capacity, hanger spacing or joint engagement from a generic allowance.
- Confirm structural acceptance of loads and fixing locations, the actual substrate, and drilling restrictions. Identify concealed services, reinforcement and post-tensioning. Obtain the applicable permits and structural clearance before drilling. Do not attach hangers to cable trays, pipes, ceiling grids, or other services unless a shared support has been specifically engineered and approved.
- Verify actual service elevations and reserved space for insulation, cable installation and bend radii, pipe gradients and maintenance, ceiling access panels, and full VCD handle or actuator movement and removal. Record route or elevation changes on approved coordinated drawings before fabrication or installation.
- Agree release boundaries, inspection notices and leakage test requirements. Confirm whether testing is required; if so, record the defined test sections, sampling or coverage, pressure and polarity, leakage class or allowable rate, area calculation basis, and treatment of dampers and equipment in the test boundary.
- Establish safe access, lighting, temporary storage, lifting arrangements, protection of adjacent services and emergency arrangements. Check that mastic application and cure conditions can be maintained. Keep duct ends capped until assembly.
Installation Sequence
| Step | Activity | Description | Responsibility | Inspection / Hold Point |
|---|---|---|---|---|
| 01 | Receive and stage materials | Check labels and delivery records against approved submittals. Check each delivery lot for correct diameters, material and coating identification, damage, out-of-round ends, damaged gaskets and damper operation. Store off the floor in a dry area on supports that prevent rolling or distortion. Cap open ends and segregate rejected items. | Storekeeper / HVAC Supervisor / QA/QC | Delivery lot inspection |
| 02 | Set out duct route, supports and access | Transfer grid and elevation datums to the workfront and mark duct centerline, support centers, fittings and VCD tags. Survey crossings against actual tray and pipe locations; include insulation thickness, support hardware, tray cable access, drainage gradients, VCD movement and ceiling panel alignment. Stop at unresolved conflicts and obtain an approved revision before altering the route. | Mechanical Site Engineer / MEP Coordinator | Check each run and crossing against coordinated drawings |
| 03 | Install anchors, hanger rods and ring brackets | Scan and clear each proposed anchor position. Drill to the approved diameter and depth, clean holes and install anchors to the product instructions; verify embedment, edge distance, spacing and torque where applicable. If bonded anchors are approved, observe the documented cure time before loading. Install rods, specified locking hardware and correctly sized rings. Set elevations and provide additional supports or restraints at fittings and dampers where shown. Leave split rings ready to receive duct sections. | HVAC Supervisor / Authorized Anchor Installer | Verify support layout and anchors before loading; proof test only to an approved test schedule |
| 04 | Prepare duct sections and coupling sleeves | Measure site cuts from the approved layout. Make square cuts, deburr and remove swarf inside and outside. Check roundness and dry-fit representative components before production. Clean joint surfaces with an approved product and allow them to dry. Mark the required insertion depth on each duct end or sleeve as appropriate. Prepare gaskets or pre-applied mastic only as required by the approved joint detail. | Duct Fitter / HVAC Supervisor | Check ends, mating fit and engagement marks |
| 05 | Lift, seat and align duct sections | Lift manageable sections and seat them into the installed ring brackets. Close the rings and secure the hardware as specified without ovalizing the duct. Keep temporary support until each section is stable on its intended permanent supports. Establish line and level, or approved fall, before completing rigid connections. Do not allow an incomplete joint or damper casing to carry an unsupported length. | HVAC Supervisor / Lift Team / Duct Fitters | Check seating, clearance and stability before releasing lift equipment |
| 06 | Engage and mechanically secure sleeve joints | Insert the sleeve to the required engagement on both sides and bring ends to the specified stop or gap. Confirm alignment without forcing or distorting the duct. Install the approved number and pattern of fasteners around the circumference. Check engagement marks and fasteners before they are obscured. Keep fasteners clear of gasket sealing zones, damper blades and moving parts as applicable. | Duct Fitter / HVAC Supervisor | Check each joint before final mastic coverage |
| 07 | Install volume control dampers as each run advances | Verify the tag, size, scheduled location and any marked airflow direction or shaft orientation. Set the damper so its handle or actuator faces the approved access opening and has full operating and service clearance. Apply approved support and connection details without distorting the casing. Keep screws and sealant clear of the blade path, spindle and linkage. Stroke each manual damper fully and check its position indicator and lock. Check actuated units by a manufacturer-permitted manual method or arrange a powered stroke with the controls trade before final acceptance. | HVAC Supervisor / Duct Fitter / Controls Contractor as applicable | Location, access and full travel for every VCD |
| 08 | Apply mastic and protect the cure | As joints and dampers are secured, apply mastic continuously around the full circumference of each connection requiring sealing, including damper casing interfaces. Seal fastener heads, penetrations and longitudinal seams where required by the approved seal class and detail. Apply at the approved width and thickness and embed reinforcement where required. Maintain product temperature and moisture limits; protect from dust, moisture and movement during cure. Do not bridge gaps beyond the approved product limit: correct the fit or use an approved repair detail. | Duct Fitter / HVAC Supervisor | Check product condition, substrate, recorded application conditions and coverage |
| 09 | Inspect completed work and rectify defects | After the required cure, inspect 100% of accessible joint circumferences, including tops and backs with a light and mirror or recorded close-up images. Check for pinholes, gaps, cracks, lifting, incomplete coverage and missed fasteners or penetrations where sealing is required. Verify supports, route, access and damper function. Remove and reapply defective mastic or repair the joint using an approved detail, then re-inspect after cure. | HVAC Supervisor / QA/QC Inspector | Full visual check before insulation or concealment |
| 10 | Test leakage where specified | After mastic cure, isolate the approved test section and fit restrained test blanks. Confirm test setup, area basis, instrument calibration and specified pressure and direction. Stabilize at test pressure and record measured leakage. Depressurize before repairs, re-cure disturbed seals and retest failed sections. Remove temporary blanks and restore system interfaces after acceptance. | Test Technician / QA/QC Inspector | Witness per approved ITP |
| 11 | Release for downstream trades and hand over | Obtain written inspection release before insulation or ceiling closure. Confirm repair closure, clean interiors, temporary blank removal, protection of exposed open ends, and visible damper tagging and access provisions. Issue verified as-built markups and hand over to insulation, controls and testing, adjusting and balancing teams as applicable. | Mechanical Site Engineer / QA/QC Inspector | Pre-concealment hold point |
Health and Safety Controls
- Access at height — falls or falling tools: Use a correctly configured mobile tower or elevating platform on verified bearing surfaces; lock tower wheels and do not climb rails or overreach. PPE: Safety helmet, slip-resistant safety footwear, and fall restraint or protection where the equipment instructions and risk assessment require it. Collective measure: Guardrails, toe boards, controlled access and a barricaded area below. Verification: Inspect before use and after relocation or alteration as applicable; authorized operation, permits and rescue provisions [Verify per project HSE plan and local regulations].
- Lifting and positioning round duct — dropped loads, crushing and pinch injuries: Verify weight and center of gravity; use a rated lift or approved rigging that restrains rolling. Keep hands out of sleeve and ring pinch points and do not release the lift before permanent supports are secure. PPE: Helmet, handling gloves and safety footwear. Collective measure: Barricade the lifting zone, prohibit work under suspended loads, and use chocks or cradles for staged duct. Verification: Supervisor checks equipment, lifting route, support readiness and assigned signaling before each lift; formal lift plan and permits where required [Verify per project HSE plan and local regulations].
- Overhead anchor drilling — service strike, structural damage, dust and flying debris: Review structural and service drawings, scan proposed holes with equipment suitable for the substrate, observe restricted zones and use a depth stop. Stop if scan results are inconclusive or actual conditions differ. Use on-tool extraction for concrete dust. PPE: Eye protection, hearing protection, and fitted respiratory protection where the exposure assessment requires it. Collective measure: Establish a controlled drilling zone and isolate affected services when required; do not drill into reinforcement, post-tensioning or concealed services. Verification: Supervisor checks permits, marked fixing locations and required isolations before drilling [Verify per project HSE plan and local regulations].
- Sheet-metal cutting and handling — lacerations and flying swarf: Cut on a stable bench, deburr immediately, and use cold-cutting tools suited to the work. PPE: Eye protection, cut-resistant gloves for handling, and sleeves; observe tool restrictions on glove use near rotating parts. Collective measure: Guard the bench or tool and screen adjacent workers from debris. Verification: Supervisor checks blade, guard and bench condition before work; abrasive cutting or other hot work is outside this method unless separately assessed and permitted.
- Mastic and cleaners — eye or skin contact, inhalation, or fire where products are flammable: Use approved products, apply with ventilation and keep lids closed when not in use. Keep ignition sources away where the safety data sheet requires it. PPE: Chemical-resistant gloves selected using the safety data sheet, eye protection and any assessed respiratory protection. Collective measure: Provide ventilation, spill kit and access to eyewash; restrict access if ventilation is inadequate. Verification: Supervisor checks product safety data sheet, storage, ventilation and any chemical or confined-space permits before use [Verify per project HSE plan and local regulations].
- Working beside electrical trays and existing services — electric shock, dropped objects and service damage: Coordinate work windows and clearances; do not rest tools, duct or platforms on services. Obtain verified isolation if safe clearance from exposed energized parts cannot be maintained. PPE: Task PPE and any electrical PPE specified by the authorized electrical team. Collective measure: Use barriers, approved screening and isolation by authorized personnel. Verification: Electrical representative confirms the interface and permit or isolation requirements [Verify per project HSE plan and local regulations].
- Leakage testing — released blanks or sudden air discharge: Use restrained blanks rated for the differential pressure and a controlled pressure source. Depressurize and confirm zero differential pressure before adjusting or removing components. PPE: Eye protection, helmet and safety footwear; hearing protection where assessed. Collective measure: Barricade test ends and keep personnel out of the line of discharge. Verification: Test lead checks blank restraint, instrument range and boundary before pressurizing; apply test permit where required [Verify per project HSE plan and local regulations].
Environmental Controls
- Drilling dust and metal swarf — contamination of ducts, equipment and occupied areas: Use on-tool dust extraction, collect swarf immediately, and cap open duct ends. Do not dry sweep or use compressed air to disperse dust. PPE: Eye protection, handling gloves and respiratory protection where assessed. Collective measure: Screen the work zone and protect adjacent air intakes, sensitive equipment and finished areas. Verification: Supervisor checks extraction and screens before work and housekeeping at each shift end [Verify per project HSE plan and local regulations].
- Mastic, cleaning products and contaminated waste — spills to drains, staining and emissions: Keep containers closed and in secondary containment, use drip trays when dispensing, and collect residues and used wipes in designated containers. Do not discharge residues or washings to drains. PPE: Safety-data-sheet-compatible gloves and eye protection. Collective measure: Protect nearby drains and provide a spill kit and ventilation. Verification: Check labels, containment and waste classification; record spills and disposal as required [Verify per project HSE plan and local regulations].
- Drilling and cutting noise — disturbance to occupants and adjacent trades: Prefabricate off-site where practicable, use maintained tools and schedule noisy work within approved hours. PPE: Hearing protection for personnel in designated zones. Collective measure: Separate the work zone or use acoustic screening where feasible. Verification: Supervisor checks work-hour restrictions and any required monitoring [Verify per project HSE plan and local regulations].
- Sharp steel offcuts and packaging — injuries, litter and avoidable landfill: Collect offcuts in rigid, designated scrap bins and separate clean cardboard and plastic. Handle contaminated packaging as required by its classification. PPE: Cut-resistant gloves and safety footwear. Collective measure: Locate bins away from escape routes and prevent loose offcuts from falling from platforms. Verification: Inspect bins and work areas at shift end and retain waste transfer records where required [Verify per project HSE plan and local regulations].
Quality Assurance and Quality Control
Inspection criteria and frequency
- Check every delivery lot against approved material data. Verify the route and elevation of every installed run and inspect every support and VCD. Record measured clearances at crossings and access constraints. Use the approved setting-out tolerances; do not accept an apparent fit that compromises clearance, duct cross-section, insulation or access.
- Before mastic obscures the connection, verify insertion on both sides of each sleeve from the engagement marks and check specified end gap, fastener type, count and distribution. Record anchor installation parameters as required by the approved anchor schedule. Where proof testing is required, use the structural engineer's approved sampling, test loads and acceptance criteria; torque verification is not a substitute for a proof-load test.
- After cure and before concealment, visually check 100% of the circumference of joints requiring sealing. Accept only continuous bonded coverage of the specified width and thickness with no visible open gaps, pinholes, cracks, lifting edges, missed locations or exposed reinforcement where full encapsulation is required. Verify wet-film thickness or other application measurements only where the approved product detail gives a criterion and method. A clean visual result does not establish pressure leakage compliance.
- Check every VCD for full unobstructed travel, correct position indication, secure lock or actuator linkage, and safe operation through the intended access opening. Record any outstanding powered checks and do not give final functional acceptance until required checks are complete.
- Where leakage testing is specified, record the section ID, construction and leakage class, test area where applicable, test pressure and polarity, measured leakage, allowable leakage, instrument IDs, and pass/fail decision. Accept only when measured leakage does not exceed the specified limit at the specified pressure. Do not substitute a generic pressure, test percentage or leakage class for missing contract criteria.
Release and nonconformance
- H — Hold: Do not proceed beyond the point without documented release by the designated authority. W — Witness: Give the specified notice; proceed without attendance only if the approved ITP expressly permits it. S — Surveillance: Contractor checks, with oversight as stated in the approved ITP.
- Identify nonconforming work by location and system, prevent concealment, agree corrective action, and re-inspect or retest. Attach objective evidence to the inspection request and obtain written pre-concealment release.
Attachments and Inspection Records
- Approved coordinated duct plans and sections, VCD schedule, reflected ceiling or access panel plan, and current clash register.
- Approved drawings for ring brackets, hangers, anchors, sleeves, joint sealing and damper installation; structural fixing approvals and anchor test schedule where applicable.
- Material submittals and traceability certificates; technical and safety data sheets; current installation instructions for duct, sleeves, mastic, anchors and VCDs.
- Task risk assessment, access and lifting plans, applicable permits, substrate scan records and workfront releases.
- Material inspection requests, support and anchor checklists, production joint checklists, sealant batch and cure logs, photographic records and VCD functional checklists.
- Where applicable: leakage test procedure and section sketches, calibration certificates, anchor proof test reports, leakage reports and retest records.
- Nonconformance and corrective action records, signed pre-concealment releases, verified as-built markups and handover records.
This content is a read-only public reference. Download or customize to get an editable version.
ITP preview
The first inspection activities from the linked ITP for Method Statement for Installation of Round Spiral Galvanized Steel Ductwork:
| Activity | Inspection / Test | Acceptance Criteria | Responsibility | Record |
|---|---|---|---|---|
| H — Workfront and setting-out release | Review current approvals and inspect each released workfront; check actual route, service conflicts, access and drilling restrictions. | Approved drawings and fixing details are available; clearances, elevations and access comply; conflicts are closed and required permits issued. | Mechanical Site Engineer and MEP Coordinator prepare; QA/QC verifies; designated Engineer releases. | Workfront release, coordinated drawings, setting-out sheet and permit references. |
| S — Material receipt | Inspect each delivery lot and check damper tags, duct and sleeve markings, certificates, and mastic batch and expiry. | Materials match approved submittals; mating ends and components are clean, compatible and free of damage that affects fit, sealing or use; mastic is within shelf life. | Storekeeper and QA/QC Inspector. | Material inspection request, delivery notes, certificates and batch register. |
| W — Anchors and ring bracket installation | Check each support location, bracket, rod and fixing; verify anchor parameters at installation and witness specified proof tests where required. | Approved support spacing, substrate, anchor type, embedment, edge distances and torque or cure are met. Brackets are secure and undistorted; specified proof tests pass before affected supports are loaded. | HVAC Supervisor installs and records; QA/QC verifies; Engineer witnesses as scheduled. | Anchor and hanger checklist, torque or cure logs, proof test reports where applicable. |
Showing 3 of 8 inspection activities. View full ITP →
Related Inspection and Test Plan
An Inspection and Test Plan (ITP) is available for Method Statement for Installation of Round Spiral Galvanized Steel Ductwork. The ITP defines the inspection activities, acceptance criteria, hold and witness points, responsible parties, and records required to verify the work described in this method statement.
View the Method Statement for Installation of Round Spiral Galvanized Steel Ductwork ITP →