Method Statement and ITP for Intumescent Mastic Firestopping at Service Penetrations – Method Statement
AI-assisted method statement with matching ITP, PDF download, and Excel export.
More than a static template
Unlike a downloadable Word or PDF template, this method statement is an AI-assisted editable starting point connected directly to a matching Inspection and Test Plan. Every section is structured, project-adaptable, and ready to export.
- AI-assisted drafting — Customize every section with AI for your specific project scope.
- Linked ITP — A matching inspection and test plan is generated alongside the method statement.
- Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
- Editable starting point, not a final document — Review, verify, and adjust all content against your project requirements before use.
Static template vs. Quollnet workflow
| Feature | Static template | Quollnet |
|---|---|---|
| Project-specific content | Manual fill-in required | AI-assisted customization |
| Linked ITP | Separate document, no link | Matching ITP included |
| Export formats | Usually PDF only | PDF and Excel |
| Structured sections | Free-form layout | 13 standardized sections |
| Saved to your account | Local file only | Cloud-saved, reusable |
| Content accuracy | You verify everything | AI-assisted, you still verify |
| Cost | Often free but time-intensive | Free to customize and download |
What you can customize
When you save this method statement to your account, every section becomes editable. The following 13 sections are included:
- Scope — Defines the activity and its boundaries.
- References — Standards, specifications, and drawings.
- Responsibilities — Roles and accountabilities.
- Resources — Labour, plant, and equipment summary.
- Materials — Materials and compliance requirements.
- Equipment — Tools and equipment details.
- Prerequisites — Hold points and pre-conditions.
- Method sequence — Step-by-step construction sequence.
- Safety controls — HSE risk controls and PPE.
- Environmental controls — Environmental mitigation measures.
- QA/QC — Quality inspection and test requirements.
- ITP — Inspection and Test Plan table (has its own page).
- Attachments — Referenced drawings and documentation.
Why this method statement is used
This method statement is used to define and communicate the approved procedure for carrying out method statement and itp for intumescent mastic firestopping at service penetrations on site. It ensures the work is planned in advance, the correct resources and controls are in place, and all personnel understand responsibilities, sequence, quality requirements, and safety controls before work begins. It aligns site execution with the documented scope and acceptance expectations.
Who uses this method statement
This method statement is used by contractors, site supervisors, project engineers, QA/QC engineers, HSE officers, consultants, and client representatives. It serves as a shared reference for planning, execution, supervision, inspection, and approval of the activity on site.
When it is prepared and submitted
The method statement is prepared before the work activity starts and submitted as part of the pre-construction documentation package for review and approval.
Who reviews or approves it
The method statement is usually submitted to the client representative, consultant, resident engineer, or project management consultant for review and approval before the work commences.
Important approval note
This method statement is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all content must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.
For example: if your specification requires a departure from a referenced standard, that departure must be documented and approved separately — this method statement will not capture that automatically. Always verify against your applicable drawings, specifications, and regulatory requirements.
Method statement content
Scope and Limits of Application
Included work
Install intumescent mastic in the annular space between approved building services and fire-resisting wall or floor assemblies. This method covers system selection, material receipt, pre-installation survey, surface preparation, backing installation, mastic application, tooling, protection, inspection, repair and handover. It applies to pipes, conduits, cables and other services only where the exact configuration is covered by an approved firestop system.
Limits of application
The fire rating applies to the complete penetration system, not to the mastic alone. A product data sheet or cartridge fire rating does not authorize installation. The approved system must cover the barrier construction and thickness, service type and size, insulation, sleeve, opening dimensions, seal depth, backing, treated faces, supports and any required wrap strips, collars or other components. Where those components are required, install them in the position and sequence specified by the system. Do not substitute additional mastic for a required component.
This method does not cover linear joints, fire or smoke damper perimeter assemblies, or membrane-only penetrations. Do not proceed with unlisted configurations, changes to the barrier, or enlargement of openings under this method. Obtain a revised approved system or a project-authorized, regulator-accepted technical assessment before proceeding where the tested or listed detail does not cover actual conditions.
Standards and Governing Documents
| Document Type | Reference / Number | Revision | Notes |
|---|---|---|---|
| Contract and regulatory documents | Adopted building and fire codes, project fire strategy, firestop specification, approved drawings and penetration schedule | Current approved issue for the work | Raise discrepancies before installation; do not select whichever requirement is easier to meet. |
| Test standards and system listing | ASTM E814 or UL 1479, as applicable to the approved system | Edition applicable to the accepted listing and governing code | Verify F rating and T rating where required, and L or W ratings where specified and documented. Do not assume these ratings from the product name. |
| Test and classification standards | EN 1366-3 and EN 13501-2, or their applicable national adoptions | Edition applicable to the accepted classification evidence | Verify E and EI performance as specified, applicable field of application and, where relevant, pipe end configuration. Do not treat European and ASTM/UL ratings as interchangeable. |
| Field inspection practice | ASTM E2174 | Contractually or legally applicable edition | Use the adopted edition for the prescribed inspection method, sampling and reporting. Contractor checks do not replace required independent inspection. |
| Approved technical submittals | System listing or classification report with applicable installation detail, product technical data sheet, safety data sheet and written compatibility documentation | Approved issue matched to products supplied | Resolve any conflict between system geometry and manufacturer installation instructions before work. A product instruction cannot expand a listing's scope. |
Responsibilities and Release Authority
| Role | Responsibility | Name / Party |
|---|---|---|
| Construction manager | Main contractor | |
| Fire protection designer or designated design authority | Design team | |
| MEP coordinator | MEP contractor | |
| Firestop supervisor and trained installers | Specialist firestop contractor | |
| QA/QC inspector | Main contractor | |
| Site HSE representative and area supervisor | Main contractor and facility operator, as applicable | |
| Engineer, independent firestop inspector or authority representative | As designated by the approved ITP and applicable code |
Personnel and Workface Resources
| Resource Type | Description | Quantity | Remarks |
|---|---|---|---|
| Installation crew and supervision | Provide trained personnel for each active workface, including access to both sides where the detail requires inspection or installation from both sides. | To suit workfront and access plan | |
| QA/QC coverage, inspector attendance and coordinated access | Schedule inspection before backing or components are covered and before walls, ceilings or shafts are closed. | Per approved inspection program |
Approved Materials and Compatibility
| Material | Specification / Grade | Quantity | Remarks |
|---|---|---|---|
| Intumescent firestop mastic | Exact manufacturer and product named in the approved system; within shelf life and stored within the manufacturer's limits. | Estimate from the approved seal geometry and product yield; reconcile against actual openings. | |
| Backing or forming material; wrap strips, collars or fixings where required | Approved type, density, thickness, orientation and compression for backing; approved size, configuration and fastening for ancillary components. | Per approved detail | |
| Cleaner, primer, tooling aid or other contact material | Use only materials permitted by the approved system and firestop manufacturer and confirmed compatible by the pipe or other contact-surface manufacturer as applicable. Compatibility approval does not replace firestop system approval. | As authorized |
Installation and Measuring Equipment
| Equipment | Capacity / Type | Quantity | Inspection Required |
|---|---|---|---|
| Compatible cartridge gun, nozzles, tooling spatulas and backing cutters | Matched to product packaging and approved seal geometry | Per active crew | Pre-use condition check |
| Rule, caliper, depth gauge, lighting, camera and condition meters as required | For ordinary annular gaps, use a gauge with 1 mm graduations as a practical benchmark [Verify per project specifications]; use finer resolution where needed to verify the approved limits. | Available at each active inspection front | Verify condition, zero and calibration or verification status as applicable |
| Inspected access platform, barriers, secured covers and suitable vacuum for approved cleaning | Matched to work height, imposed loads and dust assessment | As required by workface assessment | Pre-use and after relocation or alteration as applicable |
Prerequisites and Work Release
- Approve the fire strategy, penetration schedule, system details, material submittal, method statement, ITP and task risk assessment. Agree inspection notices, attendance and hold-point release authority before mobilization.
- Assign a unique ID to each penetration. Issue a workface detail or schedule showing the barrier construction, thickness and rating; opening limits; service and sleeve configuration; allowable minimum and maximum local annular gap; required mastic depth on each designated face and its datum; backing properties and setback; ancillary components; support requirements; and inspection criteria.
- Confirm that the barrier is complete at the penetration, including any required opening framing or lining. Services must be installed, independently supported and at their final position. Resolve commissioning, thermal movement and service operating conditions before sealing. Do not trap an unapproved insulation jacket, tape, sleeve coating or protective film in the bond line.
- Verify access, lighting, safe platform and inspection visibility. Keep both faces accessible where required. Review the manufacturer's limits for air and substrate temperature, moisture, tooling and cure. Plan to maintain these conditions through the specified protection period.
- In occupied or operational areas, coordinate penetrations through active compartment boundaries with the facility operator. Approve impairment controls and restoration timing before work. Temporary protection must be authorized for the affected opening and is not accepted as the final seal. [Verify per project HSE plan and local regulations]
Installation Method Sequence
| Step | Activity | Description | Responsibility | Inspection / Hold Point |
|---|---|---|---|---|
| 01 | Confirm system and stage materials | Match the penetration ID to the approved system before opening any product. Check the actual pipe polymer or metal, outside diameter, wall class or thickness where relevant, insulation and sleeves, and verify contact compatibility. Record product batch and expiry; quarantine damaged, expired or improperly stored material. | Firestop supervisor and QA/QC inspector | Document and material verification |
| 02 | Survey and measure opening | Verify barrier type, thickness, orientation, sleeve and service position and support. For a regular circular annulus, take readings at four quadrants as a baseline [Verify per project specifications] and at any tighter or wider point. For irregular or multi-service openings, measure corners, closest approaches, widest gaps and service-to-service spacing where controlled. Measure at the relevant seal plane on each required face and record the actual minimum and maximum; do not average away eccentricity. Check any distinct interface created by a sleeve. | Installer and firestop supervisor | Dimensional and visual survey |
| 03 | Prepare bond surfaces | Remove loose particles, dust, grease and bond-inhibiting contaminants from the barrier and contacting service or sleeve surfaces using permitted methods. Avoid damaging pipes, jackets, coatings and barrier edges. Repair defects only to an approved detail. Verify allowable surface moisture and temperature. Apply an approved primer only where required; observe its stated open or drying time. | Installer and firestop supervisor | Visual check and condition measurements where specified |
| 04 | Install backing and concealed components | Fit only the specified backing and components, in the orientation and sequence shown. For mineral wool, confirm the supplied density, installed thickness and prescribed compression using the system's stated basis. Pack continuously and keep the backing stable. Measure setback from the specified datum at the critical points on each required face, allowing for the finished surface profile so that the required seal depth is maintained after tooling. | Installer and QA/QC inspector | Pre-fill verification; witness as scheduled |
| 05 | Place and tool intumescent mastic | Place a continuous bead from the back of the seal zone toward the face, starting against the backing or at the specified placement datum. Keep the nozzle in the advancing material where access permits and fill behind the penetrant and into corners without bridging or dislodging the backing. Before skin formation, tool the mastic firmly against both bond surfaces to achieve continuous contact and the specified finish. Treat each face and interface shown in the detail; fit surface-mounted components at the specified stage. | Installer and firestop supervisor | In-process placement, profile and depth check |
| 06 | Protect seal and verify final condition | Record application time and relevant conditions. Protect against water, cleaning, dust, impact and service movement for the manufacturer's required period. Observe the applicable cure milestone before exposure, coating, service loading or concealment where specified; skin formation is not proof of full-depth cure. Inspect all required faces, fixings and finish after the applicable inspection interval. Apply the specified identification label adjacent to the seal without obscuring the inspection surface. | Firestop supervisor and QA/QC inspector | Final inspection and cure/protection review |
| 07 | Repair, reinspect and release | Tag rejected seals and block concealment. Remove defective material to the extent required by the approved repair procedure, without damaging the barrier or service; restore the complete approved detail and repeat affected inspections. Do not cover a deficient depth or failed bond with a superficial skim. Submit final records and obtain signed release before concealment. | Firestop supervisor, QA/QC inspector and designated release authority | Hold before concealment |
Task-Specific Health and Safety Controls
- Elevated access, shaft edges and open floor penetrations — falls and falling objects. Use a verified work platform and do not stand on services, ceilings or temporary covers. Provide guardrails, toe boards and secured, load-rated covers where applicable; maintain exclusion below while covers are lifted or work is overhead. Wear helmet, safety footwear and eye protection; use fall restraint or arrest only under an approved plan with suitable anchors and rescue provision. The supervisor verifies platform inspection, opening protection and below-area isolation before work and after relocation. [Verify per project HSE plan and local regulations]
- Live electrical services, hot pipes or pressurized lines — shock, burns or release of contents. Have MEP personnel positively identify the services and verify safe condition; prohibit work on exposed live parts and do not loosen supports, cut sleeves or disturb service joints. Isolate, lock out, verify the safe state and cool where required. Use barriers and keep unauthorized personnel out. Wear task-assessed gloves, eye protection and safety footwear; PPE is not a substitute for isolation. The authorized person releases work under the applicable permit and confirms reinstatement. [Verify per project HSE plan and local regulations]
- Mastic, primer or cleaner exposure — skin or eye injury and inhalation irritation. Review the SDS, minimize open containers, use local extraction or adequate mechanical ventilation where required, and prohibit unauthorized solvents. Use segregated preparation areas, splash control and accessible eyewash. Wear SDS-compatible gloves and splash eye protection; respiratory protection, if required by the assessment, must be selected and fit-tested. The supervisor checks SDS, ventilation and controls before use; no entry into a space classified as confined under this method without a separate approved entry procedure, permit and rescue arrangement. [Verify per project HSE plan and local regulations]
- Sharp edges, tools and mineral wool — cuts and fiber irritation. Use guarded cutters and cut on a stable surface; protect against sharp sleeve edges without modifying the listed bond line. Contain offcuts and restrict access to the cutting area. Wear cut-resistant gloves for cutting, suitable handling gloves and sleeves for wool, and safety glasses; add respiratory protection if required by the assessment. Inspect tools before use and supervise backing preparation. Do not grind, drill or dry-sweep under this method. If suspect hazardous legacy material is found, stop, isolate the area and obtain specialist clearance. [Verify per project HSE plan and local regulations]
- Open compartment boundary during works — fire and smoke spread. Limit the number and duration of open penetrations and maintain escape routes. Use authorized temporary fire protection or other approved interim measures, including fire watch where required, until the boundary is restored. Restrict access around open work and use normal site PPE for installation; PPE does not mitigate loss of compartmentation. The facility operator or permit issuer tracks openings and verifies restoration before closing the impairment permit. [Verify per project HSE plan and local regulations]
Task-Specific Environmental Controls
- Uncured sealant, primer and cleaner spills — contamination of drains and finishes. Use drip trays or protected surfaces and keep drain protection and spill materials at the point of use. Close containers between uses; contain and collect spills without washing them into drains. Wear SDS-compatible gloves and splash protection. The supervisor checks containment at setup and after spills; classify and report releases as required. [Verify per project HSE plan and local regulations]
- Mineral wool fibers and preparation dust — migration to occupied areas or air intakes. Cut backing at a controlled station using low-dust hand methods; capture debris with a suitable filtered vacuum rather than sweeping or blowing it. Segregate work from occupants and protect adjacent areas without obstructing required ventilation or egress. Wear gloves, sleeves and eye protection and respiratory protection where the exposure assessment requires it. Check barriers and housekeeping at each shift end. [Verify per project HSE plan and local regulations]
- Waste cartridges, solvent wipes and backing offcuts — leakage or improper disposal. Segregate clean offcuts, packaging and contaminated wastes in labeled, closed containers as appropriate. Do not combine incompatible waste streams or discharge liquid wastes to drainage. Wear handling gloves and eye protection during waste transfer. The supervisor verifies collection and records transfer through the approved waste route. [Verify per project HSE plan and local regulations]
Quality Assurance, Measurements and Traceability
Inspection coverage
Use 100% installer checks for system match, geometry, backing before coverage, application and final visual condition as the baseline [Verify per project specifications]. Contractor QA/QC independently reviews the register and checks work in accordance with the approved ITP. Statutory or contract independent inspections, including sampling and escalation of failed samples, follow the adopted standard or approved inspection program. Agree any representative first installation by system or materially different configuration before repetitive work.
Measuring depth and checking adhesion
Record actual local annular widths and the finished seal depth or documented means of verifying it, in mm, by face. Check critical positions, including changes in width, offsets, corners and tight access. Where reconstruction from setback and finish is permitted, use the same datum and account for recess, concavity and any backing displacement; a pre-fill setback reading alone does not prove finished depth. Use witnessed in-process measurement or another approved depth-verification method where backing or profile cannot be reliably verified from the finished face. Verify whether the system specifies installed or cured depth, and use the corresponding method. Do not infer depth from cartridge usage, surface appearance or a generic width-to-depth rule.
Inspect continuous contact at each bond line and check for gaps, pull-away, cracking, sagging and pinholes. This is a workmanship check, not proof of bond strength. Do not perform an improvised pull or probe test on a completed seal. When invasive checks are required by the approved inspection plan, have the authorized inspector select and document the sample; restore the tested area under an approved repair method and reinspect it before release.
Records and stop-work rules
Record penetration ID and location, barrier and service description, required rating, approved system and revision, actual dimensions per face, backing and ancillary components, batch and expiry, installer, inspection dates, application conditions where relevant, photographs and disposition. Reference measurement scale and face in depth photographs. If evidence for a concealed feature is missing, keep the release on hold until the designated authority accepts a verification plan; reopen when required. Do not change components, geometry or service configuration after acceptance without formal review and reinspection.
Attachments and Handover Deliverables
Compile the following controlled attachments for the project issue and record their references and revisions in the transmittal:
- Approved fire strategy extracts, barrier drawings, penetration schedule and installation details, including approved departures or technical assessments, if any.
- System listings or test and classification evidence with applicable field of application, product technical and safety data, and written contact-material compatibility evidence.
- Installer competency records, task risk assessment, access checks and applicable permits and impairment records.
- Material receiving and batch records, workface checklists, marked-up drawings, photographs, independent inspection reports and approved ITP releases.
- As-built penetration register, label schedule, nonconformance and repair closeouts, and owner instructions for inspecting, maintaining or altering seals without compromising the compartment barrier.
This content is a read-only public reference. Download or customize to get an editable version.
ITP preview
The first inspection activities from the linked ITP for Method Statement and ITP for Intumescent Mastic Firestopping at Service Penetrations:
| Activity | Inspection / Test | Acceptance Criteria | Responsibility | Record |
|---|---|---|---|---|
| System approval before installation | Review fire ratings, assembly and service limits, compatibility evidence and complete system details against the schedule and actual conditions. | Approved evidence covers all intended interfaces, ratings and components; no unresolved substitutions or deviations. | Design authority reviews; designated authority releases. | Approved technical submittal, compatibility evidence and schedule |
| Material receipt and release for use | Check labels, batch, expiry, packaging, storage records and ancillary component identification. | Products match the approved submittal, are undamaged and in date, and have been stored within manufacturer limits. | Storekeeper and firestop supervisor check; QA/QC reviews. | Material receiving and batch register |
| Opening, service and surface readiness | Check barrier thickness/type, support, actual local gaps and spacing, sleeve, insulation, bond surfaces, primer and application limits. | Actual dimensions and configuration comply with the approved system at all checked locations; approved surface preparation is complete. | Installer measures; supervisor verifies; QA/QC and designated inspector witness. | Survey and pre-installation checklist |
Showing 3 of 6 inspection activities. View full ITP →
Related Inspection and Test Plan
An Inspection and Test Plan (ITP) is available for Method Statement and ITP for Intumescent Mastic Firestopping at Service Penetrations. The ITP defines the inspection activities, acceptance criteria, hold and witness points, responsible parties, and records required to verify the work described in this method statement.
View the Method Statement and ITP for Intumescent Mastic Firestopping at Service Penetrations ITP →