G
Guest

Method Statement and ITP for Intumescent Mastic Firestopping at Service Penetrations inspection and test plan example.

Inspection and Test Plan for Method Statement and ITP for Intumescent Mastic Firestopping at Service Penetrations

AI-assisted inspection and test plan connected to a method statement, with PDF and Excel export.

Published 29 Nov 2026 Rev. 00 1 views
About this ITP: This ITP identifies what to check before, during and after intumescent mastic installation. It assigns responsibility for verifying concealed components, measuring seal geometry and releasing the work before enclosure.

More than a static template

Unlike a downloadable Word or PDF template, this ITP is an AI-assisted editable starting point directly connected to its method statement. Every inspection activity, hold point, and acceptance criterion is structured and ready to adapt to your project.

  • AI-assisted customization — Tailor inspection activities and acceptance criteria to your specific project scope.
  • Linked method statement — This ITP is connected to the corresponding method statement describing the work sequence.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review and verify all content against your project specifications and standards before use.

What you can customize

When you save this ITP to your account, every inspection row becomes editable. You can add, remove, or modify:

  • Inspection activity — Description of what is being inspected.
  • Inspection type — Hold point (H), Witness point (W), Review (R), or Monitor (M).
  • Responsibility — Contractor, subcontractor, engineer, or client.
  • Frequency — How often the inspection occurs.
  • Acceptance criteria — Referenced standard or specification requirement.
  • Records — Forms, test reports, or checklists required as evidence.

Why this ITP is used

It verifies that the installed penetration seal matches the approved firestop system and captures evidence of features that cannot be inspected after concealment.

Who uses this inspection and test plan

Specialist installers, contractor QA/QC staff, the designated release authority and independent firestop inspectors where appointed.

When this ITP is prepared and submitted

Use it from system approval and material receipt through installation, repair, final inspection and release before concealment.

Who receives or approves this ITP

Submit to the contractual approval authority, typically the Engineer or client representative, and to the independent inspector or authority having jurisdiction where required.

Inspection scope

Verify barrier and service configuration, local gap dimensions, contact-material compatibility, backing and ancillary components, finished seal depth and profile, identification, repairs and closeout evidence.

Typical hold, witness, and review points

Hold at system approval and before concealment. Witness opening readiness, backing and concealed components before filling, and selected in-process installation and depth checks. Apply additional statutory or contract hold points where required.

Typical inspection records

Approved system schedule, material and batch records, dimensional checks, dated photographs, inspection reports, penetration register, repair closeouts and signed release.

Important approval note

This ITP is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all inspection activities, hold points, and acceptance criteria must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

Always verify acceptance criteria against your applicable drawings, specifications, and regulatory requirements. Hold points must be confirmed with the relevant authority before work proceeds past that point.

Inspection and test plan

Activity Inspection / Test Acceptance Criteria Responsibility Record
System approval before installation Review fire ratings, assembly and service limits, compatibility evidence and complete system details against the schedule and actual conditions. Approved evidence covers all intended interfaces, ratings and components; no unresolved substitutions or deviations. Design authority reviews; designated authority releases. Approved technical submittal, compatibility evidence and schedule
Material receipt and release for use Check labels, batch, expiry, packaging, storage records and ancillary component identification. Products match the approved submittal, are undamaged and in date, and have been stored within manufacturer limits. Storekeeper and firestop supervisor check; QA/QC reviews. Material receiving and batch register
Opening, service and surface readiness Check barrier thickness/type, support, actual local gaps and spacing, sleeve, insulation, bond surfaces, primer and application limits. Actual dimensions and configuration comply with the approved system at all checked locations; approved surface preparation is complete. Installer measures; supervisor verifies; QA/QC and designated inspector witness. Survey and pre-installation checklist
Backing and other concealed components before mastic Verify backing material, thickness, compression and setback as applicable; check concealed wrap, fixings or other features against the listed arrangement. Specified components are stable and correctly positioned; available depth accounts for the required finished profile and datum. Installer and QA/QC; designated inspector witnesses per notice. Pre-fill inspection sheet, setback readings and photographs
Placement, tooling and seal depth Observe placement at selected workfaces; verify finished depth on required faces by the agreed method and examine accessible bond lines and profile. Seal depth, width and profile comply with the approved system; continuous contact without visible voids, skips or separation; required components present and undisturbed. Installer checks; QA/QC verifies; independent inspector tests where appointed. Installation checklist with measurements and applicable inspection or sample reports
Final acceptance and release before concealment Inspect finish and identification, review application/protection status, verify records and resolve defects or failed samples before release. System complete and undamaged; applicable cure and protection conditions for concealment verified; required reports and repairs accepted; signed release obtained. QA/QC submits; designated release authority signs; independent inspector reports as required. Final inspection request, signed release, updated register and closed nonconformance reports

This table is a read-only public reference. Download the PDF or Excel version, or customize this ITP to edit it for your project.

Frequently asked questions

Before the mastic covers it. Verify backing type, density where specified, required compression or thickness, setback and any concealed components against the approved detail.

No. Use accepted dimensional evidence from installation or an approved inspection method. A photograph alone generally shows only surface condition.

The designated release authority under the approved ITP signs the release after the required inspections, records and repair closeouts are accepted.

Related method statement

This Inspection and Test Plan is associated with the Method Statement and ITP for Intumescent Mastic Firestopping at Service Penetrations method statement, which describes the step-by-step construction sequence, resources, materials, equipment, safety controls, and environmental controls for this activity.

View the Method Statement and ITP for Intumescent Mastic Firestopping at Service Penetrations method statement →

Related resources