Method Statement and ITP for Contiguous Bored Pile Shoring Walls – Method Statement
Method Statement and ITP for Contiguous Bored Pile Shoring Walls method statement and inspection test plan example.

Method Statement and ITP for Contiguous Bored Pile Shoring Walls – Method Statement

AI-assisted method statement with matching ITP, PDF download, and Excel export.

Published 28 Nov 2026 Rev. 00 5 views
About this method statement: This method explains how to drill contiguous shoring piles without damaging recently placed concrete, orient the cages, and place concrete through a tremie. It shows when to build the capping beam, open excavation stages, install shotcrete infill and check readiness for a deeper cut.

More than a static template

Unlike a downloadable Word or PDF template, this method statement is an AI-assisted editable starting point connected directly to a matching Inspection and Test Plan. Every section is structured, project-adaptable, and ready to export.

  • AI-assisted drafting — Customize every section with AI for your specific project scope.
  • Linked ITP — A matching inspection and test plan is generated alongside the method statement.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review, verify, and adjust all content against your project requirements before use.

Static template vs. Quollnet workflow

FeatureStatic templateQuollnet
Project-specific contentManual fill-in requiredAI-assisted customization
Linked ITPSeparate document, no linkMatching ITP included
Export formatsUsually PDF onlyPDF and Excel
Structured sectionsFree-form layout13 standardized sections
Saved to your accountLocal file onlyCloud-saved, reusable
Content accuracyYou verify everythingAI-assisted, you still verify
CostOften free but time-intensiveFree to customize and download

What you can customize

When you save this method statement to your account, every section becomes editable. The following 13 sections are included:

  • Scope — Defines the activity and its boundaries.
  • References — Standards, specifications, and drawings.
  • Responsibilities — Roles and accountabilities.
  • Resources — Labour, plant, and equipment summary.
  • Materials — Materials and compliance requirements.
  • Equipment — Tools and equipment details.
  • Prerequisites — Hold points and pre-conditions.
  • Method sequence — Step-by-step construction sequence.
  • Safety controls — HSE risk controls and PPE.
  • Environmental controls — Environmental mitigation measures.
  • QA/QC — Quality inspection and test requirements.
  • ITP — Inspection and Test Plan table (has its own page).
  • Attachments — Referenced drawings and documentation.

Why this method statement is used

This method statement is used to define and communicate the approved procedure for carrying out method statement and itp for contiguous bored pile shoring walls on site. It ensures the work is planned in advance, the correct resources and controls are in place, and all personnel understand responsibilities, sequence, quality requirements, and safety controls before work begins. It aligns site execution with the documented scope and acceptance expectations.

Who uses this method statement

This method statement is used by contractors, site supervisors, project engineers, QA/QC engineers, HSE officers, consultants, and client representatives. It serves as a shared reference for planning, execution, supervision, inspection, and approval of the activity on site.

When it is prepared and submitted

The method statement is prepared before the work activity starts and submitted as part of the pre-construction documentation package for review and approval.

Who reviews or approves it

The method statement is usually submitted to the client representative, consultant, resident engineer, or project management consultant for review and approval before the work commences.

Important approval note

This method statement is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all content must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

For example: if your specification requires a departure from a referenced standard, that departure must be documented and approved separately — this method statement will not capture that automatically. Always verify against your applicable drawings, specifications, and regulatory requirements.

Method statement content

Scope and Design Boundaries

This method covers construction of a contiguous bored pile wall for excavation support, from working platform acceptance through pile installation, capping beam construction, staged bulk excavation, inter-pile shotcrete infill, and handover. It applies to discrete, non-intersecting piles separated by design gaps. It does not authorize cutting into adjacent piles or treating the wall as a groundwater cutoff.

The approved temporary works design governs pile geometry and reinforcement, groundwater control, permissible surcharges, excavation stages, exposed face limits, support installation and loading, monitoring, and release criteria. Shotcrete infill retains material between piles only within the role assigned to it by the design; it does not replace a designed brace, anchor, or other restraint. Construct, test, load, and remove anchors or bracing under separate approved procedures, and coordinate their release points with this method. Do not change the sequence or substitute a dry, cased, or support-fluid drilling method in the field without the required review and approval.

Applicable Documents and Standards

Document TypeReference / NumberRevisionNotes
Project design and specifications Issued-for-construction shoring drawings; temporary works design and excavation sequence; geotechnical report and design groundwater levels; project specifications; utility and monitoring plans. Current approved revisions Refer conflicts to the designer and contract administrator before the affected work; do not combine incompatible acceptance regimes.
Geotechnical design and execution standards BS EN 1536, Execution of special geotechnical work — Bored piles; EN 1997 (Eurocode 7) and applicable National Annex where adopted. Contract-adopted editions Use execution classes, tolerances and supplementary provisions specified by the contract.
Concrete standards EN 206; EN 13670; EN 12350-1 and -2; EN 12390-2 and -3. Where an ASTM regime is specified, use the applicable ASTM C94/C94M, C172/C172M, C143/C143M, C31/C31M and C39/C39M. Contract-adopted editions Apply the approved test method for the specified consistence class. Do not interchange cube and cylinder criteria.
Sprayed concrete standards EN 14487-1 and -2; EN 14488-1 and -6, where adopted by the contract. Contract-adopted editions Use the approved project test regime for early strength, compressive strength, and any specified bond or toughness.
Temporary works and monitoring BS 5975 series where adopted; ISO 18674 series, applicable parts for the specified monitoring instruments. Contract-adopted editions Use the approved trigger-action-response plan and the contract's designated release authorities.

Roles and Release Authority

RoleResponsibilityName / Party
Construction manager Obtain required approvals before mobilization; coordinate piling, civils, excavation, and specialist support subcontractors. Principal contractor
Temporary works designer and coordinator Confirm the green-concrete exclusion rules, stage geometry and support readiness; assess movement, ground loss, unexpected water, and pile defects before authorizing affected work to continue. Design team and principal contractor, respectively
Specialist supervisors Piling supervisor controls bore and pour operations; civils and shotcrete supervisors control beam, excavation, and face work within the released stage. Piling, civils, and shotcrete contractors
Surveyor, monitoring lead, QA/QC engineer, laboratory, and Engineer Survey and monitoring personnel report readings and trigger breaches; QA/QC checks records; approved laboratory samples and tests; designated Engineer or delegated authority releases points assigned by the contract. Contractor, approved laboratory, and contract-designated reviewer

Personnel and Site Resources

Resource TypeDescriptionQuantityRemarks
Piling spread and lifting crew Rig operator, foreperson, banksman, drill hands, lift supervisor, slinger/signaller, concrete crew, and backup pump or delivery arrangements as required. One coordinated spread per active workfront; staffing per approved lift plan and work plan. Arrange sufficient concrete for continuous tremie placement, including contingency for overbreak and overpour.
Civils, excavation, and shotcrete crews Excavation crew, pile-head trimming crew, formwork and reinforcement crew, qualified nozzle operator, shotcrete pump operator, and standby support as required by the stage. Sized to complete protection and support within the specified exposure window. Do not open a panel unless labor, plant, material, and safe access are available to close it.
Verification and emergency support Survey, monitoring, QA/QC, approved testing laboratory, and emergency response coverage. Coverage matched to active workfronts, critical pours, and excavation stages. Provide an agreed communication route, emergency access, and after-hours monitoring response where specified.

Materials and Submittals

MaterialSpecification / GradeQuantityRemarks
Tremie concrete and capping beam concrete Separate approved mixes as required. Specify strength, exposure, maximum aggregate size, and pour-specific consistence. For a conventional slump-specified tremie mix, 180–220 mm is an indicative range [Verify per project specifications]; the approved mix trial and placement requirements govern.
Reinforcement, couplers, spacers, stiffeners, cast-ins and test ducts Approved grade and bar schedule, with cover, lifting details, orientation marks, and test provisions as applicable. Do not substitute bars or weld reinforcement unless approved.
Bore support consumables, wet-mix shotcrete, reinforcement and drainage components Approved support fluid only where required by the bore support plan. Shotcrete mix, accelerator, mesh or fibers, dowels, spacers, drain/filter components and curing materials per approved design and trials.

Plant and Inspection Equipment

EquipmentCapacity / TypeQuantityInspection Required
Rotary piling rig, drilling and cleanout tools, temporary casing and extractor; fluid mixing and treatment plant when specified Matched to pile diameter, length, ground conditions, casing loads, and certified platform bearing demand in actual configurations. Plant certification; daily plant, platform and exclusion checks; verify mast indication and drilling controls before use.
Crane, spreader, certified lifting accessories, watertight sectional tremie, hopper and supply plant Crane capacity verified for maximum load at actual radius including rigging; tremie diameter and length compatible with mix, cage clearance, bore depth and required embedment. Approved lift plan and inspection certificates; pre-use gear checks; verify pipe cleanliness, joint seals, lengths and initial seal arrangement before each pour.
Controlled pile-head breaker, excavator, formwork, concrete vibrator, shotcrete pump, nozzle, restrained pressure hoses, and access equipment Suitable for stage geometry, support clearances, specified mix and output, and working platform or floor loading limits. Daily checks; verify formwork design, access certification, pressure ratings, couplers, restraints, emergency stop and communication.
Total station and level, depth and concrete-level sounding tools, bore profile instrumentation as specified, fluid test kit if used, concrete test equipment, and wall/groundwater monitoring instruments Measurement range and resolution sufficient for specified tolerances and movement trigger levels. Current calibration or documented verification; control point closure and reliable baseline readings before disturbance.

Pre-start Approvals and Design Inputs

Design and execution release

  • Approve a numbered pile and guide layout showing toe and cutoff levels, spacing, minimum and maximum acceptable inter-pile gaps, cover, cage orientation, wall line, and any treatment at corners and discontinuities. Check the cumulative effect of positional and inclination tolerances on clear gaps and the excavation envelope at depth.
  • Approve a location-based drilling sequence with minimum separation, elapsed-time and/or verified early-strength criteria, limits on simultaneously open bores, and rules for casing extraction and other disturbing work next to recently cast piles. Record the evidence required for each neighboring-pile release. A generic waiting period is not a release criterion.
  • Approve bore support, minimum support head where fluid is used, permissible groundwater inflows, cleanout limits, bore-open time, bore checking method, concrete supply contingency, interruption response, and the tremie plan. Confirm trial piles or demonstration pours where specified.
  • Approve a dimensioned excavation and restraint schedule: bench and lift levels, panel widths, unsupported height and exposure times, berms, strut or anchor installation and load transfer, allowable surcharges, beam and shotcrete release strengths, drainage details, and contingency stabilization measures. Fix the required strengths, verification methods, and timing before excavation starts.

Site readiness

  • Obtain permits to drill, excavate, lift and discharge as applicable. Verify utilities through records, locating and approved non-destructive exposure as necessary; resolve any unexplained indication before drilling. Mark services, boundaries, adjacent foundations, overhead clearance limits, and no-load zones.
  • Accept the working platform for the actual plant, track or outrigger pressures, slopes, drainage and stand-off distances. Survey control and working levels; take baseline readings of the wall alignment, groundwater and adjacent assets as required by the monitoring plan. Brief the trigger-action-response plan, notification chain, emergency access, and stop-work authority. [Verify per project HSE plan and local regulations]

Construction Method and Sequence

StepActivityDescriptionResponsibilityInspection / Hold Point
01 Set out wall and prepare workfront Verify platform certification, exclusion zones, underground clearance and survey datum. Set out every numbered pile and record the guide casing or guide frame position before drilling. Use offset references that remain visible after rig positioning. Install guide works where specified, and check line, level and clearances before use. Site engineer, surveyor and piling supervisor Pre-start hold and per-pile set-out check.
02 Sequence drilling to protect recently cast piles Start at the released location and drill nonadjacent piles in the approved skip pattern. Alternating piles may be used only where the resulting spacing meets the design restriction. Log actual pour completion times and any required early-strength evidence. Before drilling an intervening pile or performing nearby casing extraction or other disturbing operations, check all affected piles against the approved distance and age or strength rules. If a bore approaches a neighboring pile, the ground is lost, or unexpected fresh cementitious material is recovered, stop disturbing work, maintain bore stability, and refer to the temporary works designer. Piling supervisor and temporary works coordinator Verify each pile release before tooling enters the ground.
03 Drill, stabilize and check the bore Align the rig and verify initial tool entry. Install casing to the approved depth and advance with the designated tools; maintain the approved positive support head for fluid-supported bores. Log depth, strata, returns, groundwater, losses, casing depth, inclination checks and obstructions. Confirm toe level and founding criteria; clean with the approved tool. Check depth, bore geometry, bottom sediment and, where used, support-fluid properties at specified sample locations before cage insertion. Recheck bottom or fluid condition if there is a delay or evidence of contamination or instability before pouring. Piling supervisor and QA/QC engineer Per-bore verification of toe, geometry, stability and cleanliness; fluid tests only when applicable.
04 Lift, orient and secure reinforcement cage Check cage identification, bars, links, splices, stiffeners, spacers, cast-ins and specified test tubes before lifting. Mark the excavation face and reference axis at the cage head; transfer the corresponding sight line to casing or a stable survey reference. Lift from approved points, lower without forcing, and make any approved segment splices at a supported work level. Measure final azimuth against the drawing, confirm top elevation and projection into the beam, and hold the cage on an approved support with positive anti-rotation and anti-float restraint. Verify the tremie path and recheck cage position during casing withdrawal and after the pour. Lift supervisor, surveyor, piling supervisor and QA/QC engineer Check each cage before lowering and again before concrete placement; record final top level and orientation.
05 Place pile concrete by tremie and extract casing Confirm concrete supply, bore and cage release, clean sealed tremie and measured pipe toe elevation. Lower the tremie centrally to the approved starting clearance near the cleaned base. In a fluid-filled bore, use the approved initial seal or separator and charge with sufficient concrete to displace fluid from the pipe and establish embedment before lifting. In a verified dry bore, use the approved dry-start tremie arrangement; do not introduce support fluid merely to start the pour. Place continuously. Sound the concrete surface at each truck and before every pipe cut; keep a running plot of concrete level and quantity. Lift and shorten the tremie only after confirming the planned outlet elevation will retain required embedment. Remove temporary casing progressively as specified, keeping a positive concrete head against surrounding fluid or ground pressures, and checking for cage lift and concrete level drop. Finish at the specified overpour level above cutoff; protect the head. Piling supervisor, concrete team and QA/QC engineer Continuous pour observation; record level, outlet elevation, embedment, casing movement, delivered volume and interruptions.
06 Expose, trim and accept pile heads After sufficient pile strength is evidenced, open only the approved shallow access or capping beam trench. Survey cutoff. Remove contaminated overpour with controlled tools to sound concrete without fracturing the retained head, damaging projecting bars or compromising cover. Verify head geometry and bar embedment/projection. Carry out specified pile tests when access, concrete age and the chosen method permit. Report defects or out-of-tolerance geometry and obtain written disposition before concealment or structural reliance. Civils supervisor, surveyor and QA/QC engineer Check every pile head before beam construction and coordinate specified pile testing.
07 Construct and cure capping beam Prepare pile heads and bearing surfaces as detailed. Erect forms and fix beam reinforcement, laps and starter connections; check support interfaces, inserts, grout pockets, cover, line, level, dimensions and construction joints before pouring. Place the beam concrete in the approved sequence, compact without displacing bars or embedded items, finish to level and cure. Strip forms only at the specified strength or approved condition. Obtain verified load-release strength and acceptance of required connections before the first bulk excavation stage. Civils supervisor, QA/QC engineer and temporary works coordinator Pre-pour hold, placement witness, and separate release before structural reliance.
08 Excavate each released stage and prepare inter-pile panels Verify monitoring readings and required restraint before starting. Excavate in designated lifts and short panels, keeping plant away from the wall and leaving berms where required. Survey bench and formation levels and log the time of first exposure. Use controlled trimming to remove loose material without undercutting piles or stripping stable ground behind the gaps. Inspect exposed geometry, seepage, ravelling, overbreak and pile damage. Fit the designed drains and filters, and set out reinforcement. Stop if ground cannot stand for the approved exposure time, clear gaps exceed design assumptions, water carries soil, or a trigger is reached; isolate the area and obtain a designed response before re-entry. Excavation supervisor, geotechnical representative and temporary works coordinator Stage-start hold; survey each lift and inspect every exposed panel promptly.
09 Install and inspect shotcrete reinforcement and drainage Confirm pile face and gap condition, clean accessible contact surfaces, and condition exposed substrate as specified without eroding soil. Install only approved dowels, mesh or specified fiber reinforcement, laps, ties and spacers. Locate existing pile reinforcement before drilling approved dowel holes and avoid cutting bars. Install filters, weeps and drains at designated positions and protect outlets from rebound. Set thickness pins or other approved depth guides and check clearances for encapsulation before spraying. Shotcrete supervisor and QA/QC engineer Inspect every panel before concealment.
10 Spray, cure and verify infill Use approved wet-mix shotcrete, trained nozzle operator and trial-established settings. Apply to vertical panels generally from the bottom up with nozzle directed as nearly normal to the receiving surface as practicable; adjust the angle around bars to fill behind reinforcement. Build thickness in approved passes, remove rebound and loose overspray before covering, and never reuse rebound. Preserve drain outlets. Cure and protect the surface from washout, drying and impact. Check placed thickness, continuity, cracking, debonding and strength, using approved panels, cores or other specified methods. Repair defects to an approved detail before release. Shotcrete supervisor, QA/QC engineer and testing laboratory Observe placement; thickness and visual checks for each panel; strength sampling by approved lot.
11 Release next stage and hand over wall Review as-built lift levels, shotcrete condition and strength, drainage, support installation and testing, preload or lock-off where designed, and monitoring trends. Obtain written authorization before each deeper cut or loading change. Repeat the excavation/infill cycle in the approved sequence. At final level, check retained berms or restraints, wall geometry, drainage and defects; transfer inspection and monitoring duties for the remaining service period. Temporary works coordinator, construction manager and designated Engineer Hold at each stage release and final handover.

Task-Specific Health and Safety Controls

Apply project base PPE (helmet, high-visibility clothing and safety footwear) plus the task PPE below. Permits, separation distances, exposure limits, rescue procedures and inspection frequencies shall be confirmed [Verify per project HSE plan and local regulations].

  • Underground and overhead services — strike, electrocution, gas release or flooding. Reconcile records with detection and approved non-destructive exposure; display actual locations and clearance limits. Use a banksman at plant approaches and restrict mechanical work near unresolved crossings. PPE: Base PPE and task-specific eye, hand and utility-owner-rated protection where specified. Collective protection: Physically marked stand-offs, barriers and height limits; isolate or protect services where required. Verification: Permit-to-drill or dig, utility owner clearance where required, and supervisor revalidation when obstructions or marks change.
  • Rig or crane instability — overturn, load drop or crushing. Operate only on the accepted working platform for the actual plant and travel configuration; check slope, soft zones, platform edges and crane setup. PPE: Base PPE; gloves for gear handling. Collective protection: Barricaded edge offsets, separate rig routes, engineered mats or platform repairs, exclusion of personnel from the overturn and lifting zone. Verification: Platform acceptance and daily checks, reinspection after heavy rain, excavation or trafficking damage, and a lift-supervisor check of setup before lifts.
  • Cage lifting, rotating plant and casing extraction — caught-between injuries or suspended-load fatality. Use a designed lift arrangement and controlled upending; signal from safe positions and use tag lines only if they can be controlled without entanglement. Isolate plant before intervention and keep hands away from casing joints. PPE: Base PPE, eye protection and suitable gloves for stationary handling; no loose items near rotating plant. Collective protection: No person under a suspended cage; segregate swing and slewing zones, and use approved cage support for splicing. Verification: Lift plan, pre-use gear inspection, operator authorization and continuous banksman or lift supervision.
  • Open bores, trenches and deep excavation — falls, engulfment and ground collapse. Close unattended bores with rated secured covers or isolate them with rigid barriers; do not enter a bore. Limit excavation and exposure to the released stage; inspect ground and support after rain, impact, or changed conditions. PPE: Base PPE; fall restraint only where the approved plan requires it in addition to collective protection. Collective protection: Guardrails, engineered setbacks, safe access and egress, exclusion below unstable faces and separated plant routes. Verification: Excavation permit, competent-person shift inspections, monitoring checks, documented rescue plan and working communication; no improvised entry for rescue.
  • Unstable panel, unexpected inflow or support movement — sudden face failure or flooding. Stop, withdraw and notify when movement triggers are reached, seepage carries soil, support changes, or soil ravels faster than the approved exposure limit. Do not send personnel forward to clear or spray an unstable panel. PPE: Base PPE; no PPE makes an unstable face safe to enter. Collective protection: Evacuate and barricade affected levels, maintain emergency access, and implement only preplanned or designer-approved stabilization. Verification: Stage controller confirms the restart release and monitoring actions in writing.
  • Tremie handling, pumped concrete and wet cement — line ejection, splash, pinch injury and chemical burns. Inspect pipe and couplings, secure lines, prohibit access beneath suspended pipe, and isolate and depressurize before breaking connections. PPE: Alkali-resistant gloves and boots, long sleeves, goggles and a face shield where splash is possible. Collective protection: Hose restraints as applicable, guarded hopper, controlled discharge area and eyewash/wash water. Verification: Supervisor checks setup before each pour; pump operator controls isolation and restart.
  • Pile-head trimming and drilling — silica, flying debris, noise and hand-arm vibration. Prefer controlled mechanical trimming; use wet suppression or suitable on-tool extraction, and track exposure for handheld tools. PPE: Eye/face and hearing protection, suitable fit-tested respiratory protection and gloves selected for the task. Collective protection: Debris screens, restricted access and plant/person separation. Verification: Task briefing, guarding checks, and exposure assessment and monitoring as required.
  • Shotcrete and accelerator — hose whip, high-pressure impact, rebound, dust and chemical exposure. Inspect rated hoses, locking devices and restraints; communicate pump start/stop and isolate and depressurize before clearing blockages. Use controlled dosing; maintain a safe position outside the rebound stream and ventilate enclosed work areas. PPE: Face/eye protection, gloves and impervious clothing as specified by the safety data sheet, hearing protection and suitable fit-tested respiratory protection. Collective protection: Exclusion around nozzle/line, screens where practical, ventilation or extraction and emergency eyewash. Verification: Supervisor signs pre-spray checks and confirms pressure isolation, crew competence and exposure controls.

Task-Specific Environmental Controls

Confirm discharge approvals, local thresholds, monitoring points, working hours and reporting obligations [Verify per project HSE plan and local regulations]. Use base PPE plus the task-specific protection below.

  • Bore fluid, concrete washout and shotcrete rebound — drain blockage, high-pH contamination and harm to soil or water. Collect bore returns in designated tanks when fluid is used; collect concrete washout and rebound on lined trays or in sealed skips. Do not discharge slurry or wash water to ground or drains. PPE: Alkali-resistant gloves, boots and splash protection. Collective protection: Secondary containment, drain isolation and designated hardstand. Verification: Environmental lead checks containment at shift start and after spills or heavy rain; retain removal records.
  • Pumped groundwater and sediment-laden runoff — silting, uncontrolled drawdown and settlement. Use only the approved pumping limits and discharge route; route water through specified treatment and sample for applicable parameters such as turbidity and pH. Suspend the affected discharge if limits are exceeded and manage water safely under the contingency plan. PPE: Waterproof slip-resistant boots, gloves and eye protection near treatment plant. Collective protection: Bunds, sealed hoses, segregated clean and dirty drainage and backup containment. Verification: Inspect discharge and log pumping and groundwater readings at permit/design frequencies; invoke the monitoring response for abnormal drawdown or soil-bearing flows.
  • Spoil or suspect contaminated ground — off-site tracking, exposure and unlawful disposal. Segregate suspect spoil, suspend routine handling pending classification, cover loads and use approved carriers and facilities. PPE: Gloves and boots suitable for the material; additional chemical or respiratory protection per assessment. Collective protection: Lined segregated storage, covers and managed wheel cleaning. Verification: Inspect loads and stockpiles, document characterization and waste transfers.
  • Dust, noise and vibration — exposure, nuisance and adverse effects on nearby assets. Use controlled cutting, localized extraction or dampening; keep haul routes clean and schedule disruptive work within approved hours. Use low-impact methods where the design or receptor limits require them. PPE: Fit-tested respiratory protection and hearing protection as required by exposure assessment. Collective protection: Barriers, screened work areas, sensitive-receptor setbacks and monitoring. Verification: Record complaints and measurements specified in the monitoring plan; stop or change the generating activity at the applicable action level.
  • Fuel or hydraulic release — soil and groundwater contamination. Inspect hoses and couplings, refuel within the designated contained area, and isolate leaking equipment. PPE: Hydrocarbon-resistant gloves and splash protection when handling fuel or spill residues. Collective protection: Bunded storage, drip trays, spill kits and drain covers. Verification: Pre-use plant inspection, supervised refueling and prompt notification, cleanup and disposal records.

Quality Assurance, Testing and Nonconformance

Acceptance and lot controls

  • Maintain a traceable register by pile ID, truck, cage mark, concrete batch and specimen set. Use corresponding registers by beam pour and shotcrete stage/panel. Record coordinates and elevations against the approved datum, actual dates and times, measured results, equipment IDs and inspector sign-off.
  • Apply approved frequencies. Where the contract is silent, submit for approval: check each cage, bore and pile pour; check tremie concrete consistence at each truck; take at least one compressive-strength sample set per pile pour and per beam pour, with additional sets for specified lot volumes and early release [Verify per project specifications]. A set shall contain the specimens needed for the specified test ages and methods. Verify shotcrete thickness and visual condition on every panel; use approved trial panels and at least one production strength sample set per spraying shift and mix as a proposed starting frequency [Verify per project specifications]. Identify and sample distinct lots after significant mix, nozzle operator or process changes as required by the accepted quality plan.
  • For fluid-supported bores, test density, viscosity, sand content and other specified properties using the approved sampling plan, including the required bottom-zone sample before concreting. Do not apply generic bentonite limits to polymer systems. Carry out integrity or other pile testing at the approved frequency, with suitable access and test age. A satisfactory test does not waive an unresolved pour or geometry deviation.
  • For early loading, use the project-approved method that demonstrates the required in-place strength, such as representative field-cured specimens or a calibrated maturity method appropriate to the mix. Do not treat routine standard-cured 28-day compliance results as an early-stage release. Use approved shotcrete early-age measurements where initial support capacity is needed before routine strength results become available.

Release and deviations

  • H — Hold: Do not proceed without a documented release by the authority assigned in the approved ITP. W — Witness: Give the contract notice; proceed without attendance only where the agreed notice and waiver rules permit. R — Review: Submit records for review. As-built and monitoring submissions do not themselves constitute a release.
  • Record and isolate deviations such as pile convergence, cage misorientation, excess sediment, an abnormal concrete volume trend, loss of tremie seal, low or unsound head, unexpected water, over-excavation, or thin or poorly bonded infill. Stop the affected work, make the location safe, raise a nonconformance, and obtain written technical disposition. Verify corrective work and close the report before concealment or structural reliance unless a signed design disposition explicitly allows otherwise.
  • Read instruments at the design baseline, stage and event intervals. Compare both magnitude and rate of change with the trigger-action-response plan; take additional readings and stop or impose restrictions at the prescribed triggers. Resume only after the designated authority accepts the assessment and issues written release.

Attachments and Controlled Forms

Include the following controlled documents in the construction issue package. Cross-reference current drawing and form numbers in the project document register.

  • Approved pile layout, sequence and green-concrete release matrix; temporary works design; guide and cage orientation details; capping beam and shotcrete details; excavation and restraint stage drawings.
  • Geotechnical information, utility clearances, working platform certificate and load plans; pile cage and casing lift plans; excavation and drainage permits where applicable.
  • Approved bore support, tremie pour and interruption plans; concrete and shotcrete mix approvals; shotcrete trials; materials certifications and plant/test calibration records.
  • Pile set-out and drilling release forms; bore, fluid, cage and pour records; pile integrity testing plan where specified; pile-head and capping beam checklists.
  • Excavation stage permits, restraints testing/lock-off forms, panel exposure and pre-spray sheets, shotcrete core or panel test forms, thickness records, and written stage release forms.
  • Instrumentation and monitoring plan with trigger-action-response levels, emergency and rescue plan, risk assessments, environmental permits, nonconformance register, final as-built drawings and handover checklist.

This content is a read-only public reference. Download or customize to get an editable version.

ITP preview

The first inspection activities from the linked ITP for Method Statement and ITP for Contiguous Bored Pile Shoring Walls:

ActivityInspection / TestAcceptance CriteriaResponsibilityRecord
Workfront, design and sequencing readinessReview platform sign-off, utility clearance, design drawings, pile program, concrete and shotcrete submissions, monitoring baselines and emergency arrangements.Approvals current; platform limits and utility clearance match plant and workfront; green-concrete and excavation rules are documented.Contractor, temporary works coordinator and designated EngineerPre-start checklist, permits, baseline readings and written release
Pile position and adjacent-pile releaseCheck pile ID, position, guide, approved skip sequence and actual neighboring-pile age or required strength evidence.Set-out within approved tolerance; spacing and green-concrete requirements satisfied for all affected piles.Surveyor and piling supervisor; release by designated temporary works authoritySet-out results and dated drilling release register
Bore completion before cage insertionCheck depth, strata/founding criteria, bore geometry, stability, bottom sediment and support fluid where used; recheck after delays or changed conditions.Approved toe, geometry, base cleanliness and fluid envelope met; no unresolved bore instability.Piling supervisor and QA/QC engineer; release by designated inspectorBore completion sheet, cleanout results and applicable fluid tests

Showing 3 of 11 inspection activities. View full ITP →

Related Inspection and Test Plan

An Inspection and Test Plan (ITP) is available for Method Statement and ITP for Contiguous Bored Pile Shoring Walls. The ITP defines the inspection activities, acceptance criteria, hold and witness points, responsible parties, and records required to verify the work described in this method statement.

View the Method Statement and ITP for Contiguous Bored Pile Shoring Walls ITP →

Frequently asked questions

Only after the approved separation and age or strength criteria are met for every affected pile. Use actual pour completion records and any required early-strength evidence; an alternating layout alone is not proof of release.

Mark the cage's excavation face and reference axis, compare them to the site survey reference after lowering, and record the installed angle and top elevation. Restrain the cage and recheck it during casing withdrawal and after concreting.

Establish the initial seal and embedment where placing under fluid, maintain continuous concrete supply, measure the concrete surface and pipe outlet elevation, and check embedment before each pipe cut. Follow the approved contingency if placement is interrupted or the seal is lost.

Not by default. Shotcrete infill retains material between piles as designed. Groundwater control, drainage and protection against soil migration require separate design measures.