Inspection and Test Plan for Method Statement and ITP for Contiguous Bored Pile Shoring Walls
AI-assisted inspection and test plan connected to a method statement, with PDF and Excel export.
More than a static template
Unlike a downloadable Word or PDF template, this ITP is an AI-assisted editable starting point directly connected to its method statement. Every inspection activity, hold point, and acceptance criterion is structured and ready to adapt to your project.
- AI-assisted customization — Tailor inspection activities and acceptance criteria to your specific project scope.
- Linked method statement — This ITP is connected to the corresponding method statement describing the work sequence.
- Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
- Editable starting point, not a final document — Review and verify all content against your project specifications and standards before use.
What you can customize
When you save this ITP to your account, every inspection row becomes editable. You can add, remove, or modify:
- Inspection activity — Description of what is being inspected.
- Inspection type — Hold point (H), Witness point (W), Review (R), or Monitor (M).
- Responsibility — Contractor, subcontractor, engineer, or client.
- Frequency — How often the inspection occurs.
- Acceptance criteria — Referenced standard or specification requirement.
- Records — Forms, test reports, or checklists required as evidence.
Why this ITP is used
To verify work against the shoring design and prevent a construction stage from starting before its stability and quality requirements are met.
Who uses this inspection and test plan
Piling, civils and shotcrete supervisors, surveyors, QA/QC engineers, laboratories, temporary works personnel and the contract-designated Engineer use it.
When this ITP is prepared and submitted
Use it from workfront release and pile set-out through beam construction, excavation and each infill stage, then again at final handover.
Who receives or approves this ITP
The contract-designated Engineer or client representative through document control, with temporary works coordinator review and designer input where required.
Inspection scope
Covers set-out and adjacent-pile release, bore and cage checks, concrete placement and testing, pile head and beam acceptance, excavation geometry, support readiness, shotcrete reinforcement, thickness and strength, and monitoring.
Typical hold, witness, and review points
Typical holds include drilling release, bore acceptance, pre-pour checks, pre-spray checks and excavation stage release. Common witness points include concrete and shotcrete placement, production sampling and lift checks.
Typical inspection records
Registers include set-out, bore and tremie logs, cage orientation surveys, batch and laboratory reports, stage permits, restraint and monitoring results, shotcrete panel checks, and final as-builts.
Important approval note
This ITP is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all inspection activities, hold points, and acceptance criteria must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.
Always verify acceptance criteria against your applicable drawings, specifications, and regulatory requirements. Hold points must be confirmed with the relevant authority before work proceeds past that point.
Inspection and test plan
| Activity | Inspection / Test | Acceptance Criteria | Responsibility | Record |
|---|---|---|---|---|
| Workfront, design and sequencing readiness | Review platform sign-off, utility clearance, design drawings, pile program, concrete and shotcrete submissions, monitoring baselines and emergency arrangements. | Approvals current; platform limits and utility clearance match plant and workfront; green-concrete and excavation rules are documented. | Contractor, temporary works coordinator and designated Engineer | Pre-start checklist, permits, baseline readings and written release |
| Pile position and adjacent-pile release | Check pile ID, position, guide, approved skip sequence and actual neighboring-pile age or required strength evidence. | Set-out within approved tolerance; spacing and green-concrete requirements satisfied for all affected piles. | Surveyor and piling supervisor; release by designated temporary works authority | Set-out results and dated drilling release register |
| Bore completion before cage insertion | Check depth, strata/founding criteria, bore geometry, stability, bottom sediment and support fluid where used; recheck after delays or changed conditions. | Approved toe, geometry, base cleanliness and fluid envelope met; no unresolved bore instability. | Piling supervisor and QA/QC engineer; release by designated inspector | Bore completion sheet, cleanout results and applicable fluid tests |
| Reinforcement cage and tremie readiness | Verify fabricated cage before lifting; check installed orientation, top level, restraints, projections, cover provisions, tremie integrity and clearance, and continuity of supply. | Cage and tremie match approved arrangement; required pre-pour bore rechecks satisfactory; sufficient concrete supply confirmed. | Piling supervisor, surveyor and QA/QC engineer; release by designated inspector | Cage inspection, orientation/elevation survey and pour release |
| Pile concrete placement and sampling | Verify batches and fresh properties; sample to approved frequency; track concrete rise, volume, embedment, casing extraction, cage movement and overpour. | Mix and tests match specification; approved placement limits maintained; anomalies recorded and formally resolved before pile acceptance. | Piling supervisor, QA/QC and testing laboratory; Engineer witnesses as designated | Tremie log, volume plot, delivery tickets and fresh/strength test reports |
| Pile testing, head trimming and as-built acceptance | Survey all trimmed heads; inspect soundness and starter projections; review specified integrity tests and any geometry or pour deviations. | Cutoff, wall geometry and connections acceptable; design disposition available for deviations; applicable test and release conditions satisfied. | QA/QC, surveyor, testing specialist and designated Engineer | Head survey, inspection, test reports and disposition register |
| Capping beam pre-pour and concrete placement | Check dimensions, line and level, reinforcement anchorage and cover, forms, joints, interfaces and embeds; verify concrete tests and curing. | Pre-pour checks meet design; accepted mix and agreed sampling used; curing and protection applied. | Civils supervisor, QA/QC, testing laboratory and designated inspector | Beam checklist, pour log, curing record and test reports |
| Excavation stage release and geometry | Review beam or earlier infill release strength, restraints and test/lock-off status where applicable, instrument readings and response status; survey excavation and time panel exposure. | Required strengths and support state verified; readings satisfy stage release criteria; excavation remains within permitted levels, widths, unsupported duration and surcharge limits. | Temporary works coordinator, excavation supervisor, monitoring lead and designated Engineer | Stage permit, support records, monitoring and excavation survey |
| Shotcrete face preparation and reinforcement | Check face stability, gap dimensions, seepage control, mesh or approved reinforcement, dowels, cover guides and drain/filter details. | Stable panel within design limits; reinforcement, thickness guides, interfaces and drainage match approved details. | Shotcrete supervisor, QA/QC and designated inspector | Panel checklist, measurements and photographs |
| Shotcrete placement and hardened acceptance | Observe trial-approved spray technique and curing; inspect every panel for thickness and defects; sample panels or cores to the approved frequency and test early or final strength as specified. | Specified thickness, strength, continuity, finish and drainage achieved; repairs verified; release strength demonstrated before deeper excavation. | Shotcrete supervisor, testing laboratory, QA/QC and designated Engineer | Application and curing logs, thickness map, panel/core reports and repair sign-off |
| Final shoring handover | Review final wall and excavation survey, pile and shotcrete records, drainage, remaining supports, nonconformance closeout and ongoing monitoring arrangements. | As-built wall accepted; defects closed or dispositioned; monitoring and restraint responsibilities formally transferred. | Construction manager, temporary works coordinator and designated Engineer | Signed handover and shoring quality dossier |
This table is a read-only public reference. Download the PDF or Excel version, or customize this ITP to edit it for your project.
Frequently asked questions
Related method statement
This Inspection and Test Plan is associated with the Method Statement and ITP for Contiguous Bored Pile Shoring Walls method statement, which describes the step-by-step construction sequence, resources, materials, equipment, safety controls, and environmental controls for this activity.
View the Method Statement and ITP for Contiguous Bored Pile Shoring Walls method statement →