G
Guest

Method Statement: Installation and Mechanical Commissioning of Submersible Sewage Pumps – Method Statement
Method Statement: Installation and Mechanical Commissioning of Submersible Sewage Pumps method statement and inspection test plan example.

Method Statement: Installation and Mechanical Commissioning of Submersible Sewage Pumps – Method Statement

AI-assisted method statement with matching ITP, PDF download, and Excel export.

Published 16 Nov 2026 Rev. 00 1 views
About this method statement: This method details installation and commissioning of submersible sewage pumps, including guide rail alignment, auto-coupling, discharge piping, float level settings, dry-run protection, and performance testing. It includes HSE controls and a full ITP.

More than a static template

Unlike a downloadable Word or PDF template, this method statement is an AI-assisted editable starting point connected directly to a matching Inspection and Test Plan. Every section is structured, project-adaptable, and ready to export.

  • AI-assisted drafting — Customize every section with AI for your specific project scope.
  • Linked ITP — A matching inspection and test plan is generated alongside the method statement.
  • Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
  • Editable starting point, not a final document — Review, verify, and adjust all content against your project requirements before use.

Static template vs. Quollnet workflow

FeatureStatic templateQuollnet
Project-specific contentManual fill-in requiredAI-assisted customization
Linked ITPSeparate document, no linkMatching ITP included
Export formatsUsually PDF onlyPDF and Excel
Structured sectionsFree-form layout13 standardized sections
Saved to your accountLocal file onlyCloud-saved, reusable
Content accuracyYou verify everythingAI-assisted, you still verify
CostOften free but time-intensiveFree to customize and download

What you can customize

When you save this method statement to your account, every section becomes editable. The following 13 sections are included:

  • Scope — Defines the activity and its boundaries.
  • References — Standards, specifications, and drawings.
  • Responsibilities — Roles and accountabilities.
  • Resources — Labour, plant, and equipment summary.
  • Materials — Materials and compliance requirements.
  • Equipment — Tools and equipment details.
  • Prerequisites — Hold points and pre-conditions.
  • Method sequence — Step-by-step construction sequence.
  • Safety controls — HSE risk controls and PPE.
  • Environmental controls — Environmental mitigation measures.
  • QA/QC — Quality inspection and test requirements.
  • ITP — Inspection and Test Plan table (has its own page).
  • Attachments — Referenced drawings and documentation.

Why this method statement is used

This method statement is used to define and communicate the approved procedure for carrying out method statement: installation and mechanical commissioning of submersible sewage pumps on site. It ensures the work is planned in advance, the correct resources and controls are in place, and all personnel understand responsibilities, sequence, quality requirements, and safety controls before work begins. It aligns site execution with the documented scope and acceptance expectations.

Who uses this method statement

This method statement is used by contractors, site supervisors, project engineers, QA/QC engineers, HSE officers, consultants, and client representatives. It serves as a shared reference for planning, execution, supervision, inspection, and approval of the activity on site.

When it is prepared and submitted

The method statement is prepared before the work activity starts and submitted as part of the pre-construction documentation package for review and approval.

Who reviews or approves it

The method statement is usually submitted to the client representative, consultant, resident engineer, or project management consultant for review and approval before the work commences.

Important approval note

This method statement is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all content must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.

For example: if your specification requires a departure from a referenced standard, that departure must be documented and approved separately — this method statement will not capture that automatically. Always verify against your applicable drawings, specifications, and regulatory requirements.

Method statement content

Scope

Scope of Works

  • Install submersible wastewater pumps complete with guide rail system, auto-coupling (duckfoot) base, lifting chains, discharge piping/valves, and electrical/control integration in an existing/new wet well.
  • Align and commission guide rails and auto-coupling to achieve repeatable, leak-tight seating.
  • Connect discharge pipework to manifold/rising main, including isolation and non-return valves, supports, and flexible joints as specified.
  • Install and set liquid level controls (float switches and/or level transmitter), configure control panel logic, and implement dry-run prevention.
  • Perform pre-energization checks, hydrostatic testing of discharge pipework (where applicable), wet functional tests, and pump performance logging against approved curves.
  • Deliver as-built documentation, calibration records, ITRs/WIRs, O&M and training. [Verify per project specifications]

References

Document TypeReference / NumberRevisionNotes
Standard ISO 9906
Standard IEC 60034 (Parts 1, 11) / IEEE 43 (IR guidance) [Verify project requirement]
Standard IEC 60364 series [or BS 7671 where applicable] [Verify local code]
Standard BS EN 1092-1 (PN) or ASME B16.5 (Class) [Project standard governs]
Standard EN 805 (water supply) – test method basis for rising mains [Adapt for wastewater service] [Verify test pressure and duration per spec]
Standard BS 7121-1; EN 13155; EN 1492 series [Verify local regulations]
Standard ISO 10816/20816 (applicable parts) [Field guidance] Measurement approach for submerged units to be agreed
Standard ATEX/IECEx [Verify hazardous area classification]

Responsibilities

RoleResponsibilityName / Party
PM Project Manager Contractor
Construction Construction Manager / Site Engineer Contractor
QC Mechanical QC Inspector Contractor
QC Electrical QC Inspector Contractor
Cx Commissioning Engineer Contractor
HSE HSE Officer Contractor
Engineer Engineer/Employer’s Representative Engineer

Resources

Resource TypeDescriptionQuantityRemarks
Manpower Mechanical supervisor + fitters 4
Manpower Electrical supervisor + electricians 3
Manpower Commissioning engineer + technician 2
Manpower Appointed person, rigger/slinger 2-3
Manpower Standby rescue team with tripod/winch 2

Materials

MaterialSpecification / GradeQuantityRemarks
Pump IP68 motor, 400/690V or as specified, duty per schedule As per BOQ
Auto-coupling Manufacturer matched set Per pump
Guide rails Diameter per OEM, straightness ≤1 mm/m Per well
Pipe PN10/PN16 typical [Verify] As per drawings
Valves BS EN 1074 / AWWA [Verify] Per line
Jointing
Controls As required
Electrical IEC 60364 compliant
Fixings

Equipment

EquipmentCapacity / TypeQuantityInspection Required
Crane 5–25 t typical [Verify] 1 LOLER/Third-party cert valid
Rigging 1–3 t 2–4 Pre-use check
Torque wrench 20–300 Nm (range) 2 Calibration
IR tester Up to 1000 V 1 Calibration
Electrical test 1 each Calibration
Gas detector 2 Calibration
Rescue 150 kg+ 1 Pre-use
Ventilation >500 m3/h typical 1–2 Pre-use
Hydrotest set Up to test pressure 1 Calibration
Flowmeter 1 Calibration

Prerequisites

Pre-Start Requirements

  • Approved shop drawings, pump datasheets, GA drawings, wiring diagrams, and control logic narrative.
  • Approved Method Statement and ITP; task risk assessment (TRA/JSA) briefed to all personnel.
  • Permits: Lifting, Confined Space Entry, Electrical LOTO, Hot Work (if any), Excavation (if external works), as applicable. [Verify per project HSE plan and local regulations]
  • Wet well structurally complete, cleaned, and free from debris; inflow isolated or bypassed; temporary plugs/blinds installed as required.
  • Benchmarks and reference levels established; start/stop/high alarm elevations confirmed with Engineer.
  • OEM installation manuals for pumps and guide rails available at site; FAT reports (if applicable) reviewed.
  • All instruments calibrated; torque charts available; anchors and grout with valid TDS; materials inspected and accepted.
  • Hazardous area classification confirmed (if applicable) and equipment compliance verified.
  • Power supply available and tested for voltage and fault level; control panel energized for testing after LOTO clearance.

Method Sequence

StepActivityDescriptionResponsibilityInspection / Hold Point
1 Site handover and permits Conduct pre-start meeting; issue permits (Lifting, Confined Space, LOTO). Toolbox talk and TRA briefing. Site Engineer / HSE Permit verification
2 Delivery inspection Verify pumps, rails, auto-couplings, valves, and materials against approved submittals. QC / Storekeeper Visual and dimensional
3 Wet well preparation Isolate flows; clean well; gas test; ventilate; install temporary barriers/edge protection. Site Engineer / HSE Gas test & atmosphere control
4 Set out base and fixings Mark base elbow and bracket positions; drill and install chemical anchors; grout as required. Mechanical Supervisor Pull-out capacity (if required)
5 Install auto-coupling base Position duckfoot on base; align to riser; tighten flange bolts to specified torque. Mechanical Supervisor Flange joint inspection
6 Install guide rails and brackets Fit upper guide bracket; plumb rails using spirit level/laser; secure with intermediate supports as needed. Mechanical Supervisor Dimensional survey
7 Trial lowering (dry) Rig pump with certified slings to lifting eye; slowly lower without seating to check unobstructed travel and cable routing. Rigger / Mechanical Supervisor Rigging inspection
8 Final seating Lower pump to engage auto-coupling; confirm full contact of mating faces; raise 200–300 mm and re-seat to confirm repeatability. Mechanical Supervisor / QC Seating verification
9 Discharge piping and valves Install riser/valves/supports. Apply gasket, align flanges, tighten in star pattern to specified torque. Mechanical Supervisor Piping inspection
10 Electrical cabling and terminations Route pump power/control cables; fit IP68 glands; terminate in JB/panel; identify cores; earth bonding. Electrical Supervisor Electrical inspection
11 Protection and settings Set overloads at 1.05× FLA (cold) unless OEM states otherwise; configure seal/thermal relays; VFD parameters (if any). Commissioning Engineer Panel settings review
12 Pre-energization tests IR test (stator to earth) at 500 VDC for LV motors; record polarization index if required; verify phase rotation at panel/JB; continuity and insulation on control circuits. Electrical QC Electrical tests
13 Hydrostatic test (if applicable) Isolate pump; pressurize discharge line to 1.5× design pressure or PN rating (lower of the two); hold 30 min. Mechanical Supervisor / QC Pressure test
14 Float switch installation and setting Install weights and set elevations: Stop (lowest), Start (duty), Assist (lead/lag), High-High Alarm. Secure to cable holders/ hooks. Commissioning Engineer Level setout check
15 Dry-run prevention test With clean water, run pump then lower level to Stop; verify trip/interlock: stop at Stop level; seal/thermal alarms; VFD dry-run logic if present. Commissioning Engineer / Electrical QC Functional test
16 Wet functional test (duty/assist) Fill well; verify Duty starts at Start; Assist starts at Assist setpoint; check non-return valve operation and discharge pressure. Commissioning Engineer Operational check
17 Performance logging Stabilize at duty point; record flow, discharge pressure, voltage/current per phase, PF, frequency/VFD speed, and vibration (if measurable). Commissioning Engineer / QA Performance verification
18 Demobilization and handover Remove temporary works; reinstate covers; submit as-builts, logs, ITRs, O&M; train operator. Site Engineer / Commissioning Engineer Document review

Health, Safety and Environment (HSE) – Safety Controls

Task-Specific Hazards and Controls

  • Hazard: Lifting over open wet well; pump drop
  • Likely consequence: Serious injury/fatality, equipment damage
  • Control: Appointed Person lift plan; exclusion zone; certified crane and slings; taglines; no personnel under load
  • Required PPE: Helmet with chin strap, gloves, safety boots, eye protection
  • Collective measure: Edge protection/guardrails around wet well; barricades and signage
  • Inspection/permit: BS 7121-compliant lift plan; pre-use inspection of lifting gear; Lifting Permit [Verify per project HSE plan and local regulations]

  • Hazard: Confined space entry (wet well)

  • Likely consequence: Asphyxiation/toxic exposure (H2S/CH4), drowning, entrapment
  • Control: Confined Space Permit; continuous gas monitoring (O2, H2S, CH4/LEL, CO); forced ventilation; standby rescue team with tripod/winch; harness and lifeline; communication plan; water level isolation/bypass
  • Required PPE: Full body harness, multi-gas detector, chemical-resistant gloves, boots, hard hat, eye protection
  • Collective measure: Rescue plan drilled; barriered access; intrinsically safe lighting where required
  • Inspection/permit: Permit with atmospheric readings; bump test records; rescue equipment inspection tags

  • Hazard: Electrical energization/LOTO failure

  • Likely consequence: Electric shock, arc flash, equipment damage
  • Control: LOTO procedure; verified de-energization before termination; use of RCDs; correct phase rotation verification; IP68 glands and strain relief
  • Required PPE: Electrically rated gloves, arc-rated face shield/clothing (as required), safety boots
  • Collective measure: Barriers around panels; insulated tools; lock boxes and tags
  • Inspection/permit: Electrical work permit; LOTO audit; instrument calibration certificates

  • Hazard: Exposure to sewage aerosols/biological agents

  • Likely consequence: Illness, infection
  • Control: Hygiene controls, vaccination status [Verify]; minimize agitation; use clean water for testing; decontaminate equipment after use
  • Required PPE: Nitrile/chemical gloves, coveralls, eye/face protection, boots
  • Collective measure: Handwash station; dedicated waste bags/containers
  • Inspection/permit: HSE inspection; COSHH assessment (if chemicals used)

  • Hazard: Pressurization during hydrotest

  • Likely consequence: Line/component rupture, projectile hazards
  • Control: Rated test equipment; calibrated gauges; test blinds; gradual pressurization; exclude personnel from line of fire
  • Required PPE: Helmet, gloves, eye protection, boots
  • Collective measure: Barriered test area; pressure relief
  • Inspection/permit: Hydrotest procedure approval; gauge calibration record

  • Hazard: Slips/trips at wet well area (wet surfaces, hoses, cables)

  • Likely consequence: Sprains/fractures
  • Control: Good housekeeping; cable management; anti-slip mats; adequate lighting (24 V where required)
  • Required PPE: Safety boots with slip-resistant sole
  • Collective measure: Route marking; tidy-up schedules
  • Inspection/permit: HSE walkdowns; lighting checks

  • Hazard: Noise and vibration from running pumps/blowers

  • Likely consequence: Hearing damage
  • Control: Limit exposure time; select low-noise equipment; maintain covers closed during operation
  • Required PPE: Hearing protection where >85 dB(A)
  • Collective measure: Noise mapping and signage
  • Inspection/permit: Noise monitoring records

  • Hazard: Hot works (if any bracket welding)

  • Likely consequence: Burns, fire, fumes
  • Control: Hot Work Permit; fire watch; fire blankets/extinguishers; gas-free verification in confined space
  • Required PPE: Welding mask, gloves, FR clothing
  • Collective measure: Spark containment; ventilation
  • Inspection/permit: Hot Work Permit; gas readings [Verify]

Environmental Controls

Environmental Risk Controls

  • Sewage and contaminated water management
  • Control: Bypass/containment; use clean water for testing; collect and dispose of contaminated residues via licensed contractor.
  • Inspection/permit: Method for disposal approved by Engineer; waste transfer notes.

  • Dechlorination (if using chlorinated potable water for testing)

  • Control: Neutralize before discharge using approved agent; verify residual chlorine < permissible limit.
  • Inspection/permit: Sampling per local standards [Verify].

  • Spill prevention

  • Control: Drip trays under flanged joints; spill kits at point-of-work; immediate clean-up.
  • Inspection/permit: HSE inspections; spill log.

  • Noise and working hours

  • Control: Comply with permitted hours; use silencers on blowers/pumps where feasible.
  • Inspection/permit: Community/noise compliance checks.

  • Waste segregation

  • Control: Segregate scrap metal, packaging, used gaskets, and consumables; dispose per waste plan.
  • Inspection/permit: Waste register; toolbox briefings.

QA/QC Requirements

Quality Assurance and Control

  • Submittals: Approved datasheets, pump curves, GA drawings, I/O lists, software/logic description, torque tables, anchor TDS, calibration certificates.
  • Calibration: All measuring equipment within validity; record serial numbers on ITRs.
  • Inspection Requests (WIR/ITR): Submitted 24–48 hours prior for hold/witness points per ITP.
  • Dimensional and Alignment Checks: Guide rail plumbness, spacing, and seating verification documented.
  • Bolting Control: Use calibrated torque wrenches; record torque values and sequence.
  • Electrical Tests: IR tests with ambient correction where required; rotation check; protection setting sheets signed.
  • Hydrostatic Test: Procedure approval; calibrated gauges; acceptance documented.
  • Functional/Performance Tests: Test sheets include water levels, setpoints, current/voltage, flow, head, alarms, and vibration (if measurable). Compare against ISO 9906 acceptance and nameplate FLA.
  • Non-Conformance: NCR raised for deviations; corrective actions recorded and re-tested.
  • Records/Handover: As-builts, redlines, O&M manuals, spares list, training records, ITRs, permits, calibration certificates, performance logs.

Attachments

Attachments / Appendices

  • Approved pump datasheets and curves (duty/assist/standby) with ISO 9906 acceptance grade.
  • OEM installation manuals for pumps, guide rails, and auto-couplings.
  • Control philosophy and cause & effect for level devices and alarms.
  • Torque tables for flanged joints and bracket fixings.
  • Anchor manufacturer TDS and installation guide; grout TDS.
  • Lift plan, rigging study, and certificates for lifting gear.
  • Calibration certificates for torque wrenches, pressure gauges, flowmeters, and electrical testers.
  • ITR/WIR templates: seating check sheet, torque log, level setting sheet, IR/rotation sheet, pressure test certificate, performance log.
  • As-built drawings and redlines showing final elevations and cable routing.

This content is a read-only public reference. Download or customize to get an editable version.

ITP preview

The first inspection activities from the linked ITP for Method Statement: Installation and Mechanical Commissioning of Submersible Sewage Pumps:

ActivityInspection / TestAcceptance CriteriaResponsibilityRecord
Material receiving inspectionCheck datasheets, nameplates, certificatesConforms to approved submittals; no damage/corrosionQC Inspector / Engineer (Witness)Material Inspection Report (MIR)
Anchor installationEmbedment depth/spacing; TDS complianceAs per manufacturer; curing per TDS [Verify]QC Inspector (Hold)Anchor ITR/Photos
Auto-coupling base installationLevelness; flange torqueFlatness within 1 mm; torque within specified rangeQC Inspector / Engineer (Witness)Torque Log; WIR

Showing 3 of 14 inspection activities. View full ITP →

Related Inspection and Test Plan

An Inspection and Test Plan (ITP) is available for Method Statement: Installation and Mechanical Commissioning of Submersible Sewage Pumps. The ITP defines the inspection activities, acceptance criteria, hold and witness points, responsible parties, and records required to verify the work described in this method statement.

View the Method Statement: Installation and Mechanical Commissioning of Submersible Sewage Pumps ITP →

Frequently asked questions

Performance is verified against the approved pump curve using ISO 9906 hydraulic acceptance (typically Grade 2B unless otherwise specified) and current not exceeding nameplate FLA.

Rails are installed plumb within ≤3 mm over full height, parallel per OEM ±2 mm, ensuring smooth travel and zero-gap seating at the duckfoot.

By simulating low water level during wet testing to confirm pump stop at the Stop level and correct operation of seal/thermal/VFD dry-run interlocks.

Insulation resistance testing at 500 VDC for LV motors, continuity, and phase rotation verification; settings for overload, seal, and thermal protections are checked and recorded.

Yes, if newly installed or modified. Test at 1.5× design pressure or PN rating (lower governs), hold 30 minutes with no leaks and minimal pressure loss [Verify per project specs].

Related resources