Method Statement for Installation, Inspection and Maintenance of Safety Nets Beneath Elevated Work Areas – Method Statement
AI-assisted method statement with matching ITP, PDF download, and Excel export.
More than a static template
Unlike a downloadable Word or PDF template, this method statement is an AI-assisted editable starting point connected directly to a matching Inspection and Test Plan. Every section is structured, project-adaptable, and ready to export.
- AI-assisted drafting — Customize every section with AI for your specific project scope.
- Linked ITP — A matching inspection and test plan is generated alongside the method statement.
- Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
- Editable starting point, not a final document — Review, verify, and adjust all content against your project requirements before use.
Static template vs. Quollnet workflow
| Feature | Static template | Quollnet |
|---|---|---|
| Project-specific content | Manual fill-in required | AI-assisted customization |
| Linked ITP | Separate document, no link | Matching ITP included |
| Export formats | Usually PDF only | PDF and Excel |
| Structured sections | Free-form layout | 13 standardized sections |
| Saved to your account | Local file only | Cloud-saved, reusable |
| Content accuracy | You verify everything | AI-assisted, you still verify |
| Cost | Often free but time-intensive | Free to customize and download |
What you can customize
When you save this method statement to your account, every section becomes editable. The following 13 sections are included:
- Scope — Defines the activity and its boundaries.
- References — Standards, specifications, and drawings.
- Responsibilities — Roles and accountabilities.
- Resources — Labour, plant, and equipment summary.
- Materials — Materials and compliance requirements.
- Equipment — Tools and equipment details.
- Prerequisites — Hold points and pre-conditions.
- Method sequence — Step-by-step construction sequence.
- Safety controls — HSE risk controls and PPE.
- Environmental controls — Environmental mitigation measures.
- QA/QC — Quality inspection and test requirements.
- ITP — Inspection and Test Plan table (has its own page).
- Attachments — Referenced drawings and documentation.
Why this method statement is used
This method statement is used to define and communicate the approved procedure for carrying out method statement for installation, inspection and maintenance of safety nets beneath elevated work areas on site. It ensures the work is planned in advance, the correct resources and controls are in place, and all personnel understand responsibilities, sequence, quality requirements, and safety controls before work begins. It aligns site execution with the documented scope and acceptance expectations.
Who uses this method statement
This method statement is used by contractors, site supervisors, project engineers, QA/QC engineers, HSE officers, consultants, and client representatives. It serves as a shared reference for planning, execution, supervision, inspection, and approval of the activity on site.
When it is prepared and submitted
The method statement is prepared before the work activity starts and submitted as part of the pre-construction documentation package for review and approval.
Who reviews or approves it
The method statement is usually submitted to the client representative, consultant, resident engineer, or project management consultant for review and approval before the work commences.
Important approval note
This method statement is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all content must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.
For example: if your specification requires a departure from a referenced standard, that departure must be documented and approved separately — this method statement will not capture that automatically. Always verify against your applicable drawings, specifications, and regulatory requirements.
Method statement content
Scope
Application
This method covers EN 1263 System S horizontal personnel fall-arrest nets with border ropes, installed below elevated construction work areas. It covers the net layout, supporting structure and anchorages, installation and joining, clearance verification, inspection, handover, maintenance, damage assessment and removal. Each handover applies only to the defined work zone, work levels and configuration recorded on the release.
Safety nets are collective fall-arrest protection. Retain required edge protection, safe access and measures to prevent falls. Personnel nets are not work platforms, debris nets or lifting devices. Do not add debris mesh or other attachments unless the compatible assembly and its additional loads have been approved. This method does not cover vertical nets, proprietary cantilever systems or nonstandard small-net configurations; those require a separately approved design and procedure.
Document administration: Project, issue date and submission details are held in the custom fields. Resolve the issue-date token to the current date in YYYY-MM-DD format before controlled issue. A method statement approval does not constitute release of an installed net.
References and Governing Documents
| Document Type | Reference / Number | Revision | Notes |
|---|---|---|---|
| Product standard | EN 1263-1, Temporary works equipment — Safety nets — Part 1: Safety requirements, test methods | Contract-adopted edition | Use the applicable national adoption where specified. |
| Installation standard | EN 1263-2, Temporary works equipment — Safety nets — Part 2: Safety requirements for the positioning limits | Contract-adopted edition | Apply the positioning requirements for the actual work geometry and net system. |
| Structural design standard | EN 1992-4, Eurocode 2 — Design of concrete structures — Part 4: Design of fastenings for use in concrete | Contract-adopted edition and applicable National Annex | Use with the product technical assessment and the governing structural design basis. Not applicable to beam clamps or steel member resistance. |
| Project and statutory documents | Contract specifications; approved temporary works design and anchor schedule; manufacturer instructions; project HSE plan; applicable regulations | Current approved revisions at point of use | Refer conflicts to the designer and contract administrator before installation. Do not substitute products or apply an alternative standard without approval. |
Responsibilities
| Role | Responsibility | Name / Party |
|---|---|---|
| Temporary Works Designer | Owns the temporary works design; obtains independent design checking as required by the project procedure. | Appointed design organization |
| Temporary Works Coordinator or appointed equivalent | Authorizes use, suspension and reinstatement under the project temporary works procedure. | Principal contractor |
| Safety Net Installation Supervisor | Stops work for deviations, damaged components, unsafe access or changed conditions. | Competent specialist installer |
| Competent Safety Net Inspector and QA/QC Engineer | Competent net inspector signs the technical inspection; QA/QC coordinates Client or Engineer attendance and verifies record completeness. | Appointed inspector and contractor QA/QC |
| HSE Lead and Overhead Construction Supervisor | HSE Lead verifies control readiness; Construction Supervisor controls work within the released limits and reports defects immediately. | Principal contractor and affected trade contractors |
Personnel and Site Resources
| Resource Type | Description | Quantity | Remarks |
|---|---|---|---|
| Installation crew | Trained safety-net riggers, access equipment operators and a supervisor capable of carrying out the approved rigging and joining sequence. | Per approved work and rescue plan; no lone installation or removal | Provide a ground attendant for MEWP emergency lowering when a MEWP is used. |
| Inspection and emergency personnel | Appointed inspector, named rescuers and first-aid coverage available for the work zone and shift. | Per appointment and site-specific rescue plan | Maintain access to the retrieval point and a reliable communication method; do not rely solely on emergency services. |
Materials and Components
| Material | Specification / Grade | Quantity | Remarks |
|---|---|---|---|
| System S personnel safety net | EN 1263-1; net class, mesh size, panel dimensions and identification per approved design. | Per approved net schedule | Quarantine unidentified, expired, unverified or damaged nets. |
| Tie ropes, coupling ropes, connectors and edge protection | Compatible with the EN 1263 system and the manufacturer's instructions; types, strengths and terminations per design. | Per approved details and joint lengths | Do not use makeshift ties, unverified connectors or knots not specified by the approved procedure. |
| Net anchor assemblies | Approved proprietary anchors, beam clamps or engineered attachments; product and substrate limits per approved design and installation instructions. | Per approved anchor schedule | Do not tie to guardrails, decking, services or unverified framing. Do not drill or weld to structural members without approval. |
Access, Installation and Inspection Equipment
| Equipment | Capacity / Type | Quantity | Inspection Required |
|---|---|---|---|
| MEWP or approved scaffold | Rated for actual reach, personnel, tools and material load. | Current statutory examination where applicable; pre-use checks or scaffold handover and inspection. | |
| Rigging aids, anchor installation tools and test instruments | Suitable for planned loads, installation settings and specified test ranges. | Pre-use condition checks, certification and calibration as applicable. | |
| Tape or laser distance meter, lighting, communications and rescue equipment | Measuring range and accuracy suitable for the layout; rescue kit rated for the planned use. | Pre-use functional and condition checks; calibration where required by the project. |
Prerequisites and Design Release
- Approved design: Issue a checked temporary works layout showing work limits and levels, each net ID and orientation, support and anchor IDs, spacing, design actions and load directions, joint details, edge coverage, initial sag, unloaded net profile and required deflected clearance. Verify stability of the support at the construction stage when the net will be used. Account for load transfer to adjacent fixings and the structure; do not approve a support solely on the strength rating of an individual connector.
- System S positioning benchmarks: Confirm that the panels are within the scope of EN 1263-2: net area at least 35 m² and shortest side at least 5 m. For the standard System S load arrangement, use anchor spacing below 2.5 m and check each point for a characteristic action of at least 6 kN at 45° for a maximum fall height of 6 m. These are design benchmarks, not field proof-test loads; confirm the action direction, combinations and any greater or more restrictive design requirements [Verify per project specifications].
- Fall height and edge coverage: Set the net as close as practicable below the working level. For the applicable EN 1263-2 geometry, the maximum fall height is 6 m and the reduced fall height limit in the 2 m perimeter zone is 3 m. For work areas with slope not exceeding 20°, minimum catching-width benchmarks are 2.0 m, 2.5 m and 3.0 m for applicable fall heights up to 1.0 m, 3.0 m and 6.0 m respectively [Verify per project specifications]. The designer shall show the actual measurement references and any special positioning requirements, including for slopes, corners, steps and openings. Do not apply the flat-area widths to steeper slopes without a design check.
- Deflection clearance: Verify clearance below and alongside the net against the approved deflection envelope, allowing for installed sag and dynamic deflection. Check beams, services, bracing, stacked materials, plant routes and any other obstruction. Do not substitute a nominal clearance or initial sag measurement for this check. Identify the protected clearance zone on the layout and keep it clear throughout use.
- Work controls: Accept the ITP and inspection notices, confirm permits and access arrangements, verify installer competence, and brief the site-specific rescue plan. Establish exclusion zones above and below the installation, control concurrent work and confirm weather limits. Confirm that MEWP emergency lowering or another approved recovery route is available before work at height [Verify per project HSE plan and local regulations].
Installation, Use, Maintenance and Removal Sequence
| Step | Activity | Description | Responsibility | Inspection / Hold Point |
|---|---|---|---|---|
| 01 | Set out work zones and control access | Walk down the installation with the supervisor. Mark work boundaries, anchor locations, access routes and the clearance zone. Stop conflicting work above and below the installation. Establish barriers and confirm rescue access before the crew is exposed to a fall. | Installation Supervisor and Construction Supervisor | Check actual structure, working levels, obstructions and means of access against the layout. |
| 02 | Receive, identify and lay out net components | Match each net and accessory to the approved schedule. Unfold on a clean surface and check mesh, border ropes, seams, labels, connectors and evidence of test validity. Assign each accepted net to its installation position. | Installation Supervisor and QA/QC | Visual and documentary check of each net and accessory. |
| 03 | Install and release anchorages | Verify member or substrate identity and condition. Where drilling is approved, confirm reinforcement, embedded services and no-drill zones before drilling. For post-installed anchors, record hole dimensions, embedment, cleaning, product batch, curing conditions and tightening settings as applicable. For clamps, verify member geometry, clamp fit, orientation, locking and specified tightening. Complete inspection and any specified testing before attaching nets. | Anchor Installer, Competent Inspector and Temporary Works Coordinator | Check every attachment; witness proof testing if specified. |
| 04 | Raise and secure panels | From independent protected access, raise each panel with approved handling equipment. Attach its border rope to the released anchors in the sequence shown on the rigging plan. Maintain control of free corners and secure the specified permanent ties before removing temporary handling lines. Fit chafe protection at approved contact points. | Competent Riggers under Installation Supervisor | Check each tie, termination, connector lock and potential abrasive contact. |
| 05 | Join panels and close perimeter gaps | Use the joint type shown on the approved layout. For laced joints, interconnect both panels continuously with compatible coupling rope, following the approved lacing pattern and end terminations. For an overlap joint, position and secure both panels to maintain the overlap throughout the joint. Inspect transitions at corners, columns, openings and changes in level. | Installation Supervisor and Competent Inspector | Inspect the full length of each joint; measure the narrowest overlap or largest laced-joint opening and check perimeter gaps. |
| 06 | Verify net geometry and clearance | Measure the installed net profile, unloaded sag, fall heights and catching widths against the approved drawing. Survey the nearest obstructions and verify clear space against the approved deflection envelope. Check each bay, changes in elevation and worst-case locations. | Competent Inspector with Site Engineer | Measure and record the controlling dimensions for each bay and interface. |
| 07 | Obtain written handover before overhead work | Complete the final walkdown, correct defects and verify that records correspond to the installed configuration. Sign the handover for each zone, show its status at agreed access points and brief the receiving work supervisor on limits, permitted stages, clearance and reporting. | Competent Inspector, Temporary Works Coordinator and Construction Supervisor | Hold point: verify technical sign-off and approvals identified in the ITP. |
| 08 | Inspect and maintain in service | Check each active zone before the shift and carry out recorded competent-person inspections at the specified interval. Check for debris, altered sag, loose or displaced ties, joint separation, chafing and new obstructions. Remove debris from independent protected access, with overhead work stopped in the affected area. Keep the clearance and rescue routes open. | Construction Supervisor and Competent Inspector | Pre-shift status and visual check; formal inspection at intervals not exceeding seven days as a benchmark, or sooner where required [Verify per project HSE plan and local regulations]. |
| 09 | Suspend use, assess damage and re-release | After a fall, significant object impact, severe weather, unauthorized modification, suspected chemical or heat exposure, or movement affecting anchors or geometry, stop work that relies on the affected system and isolate the zone. Activate rescue if needed. Inspect the affected and adjoining panels, connections, anchors and support load path before deciding on disposition. Quarantine affected equipment by ID. | Construction Supervisor, Competent Inspector and Temporary Works Designer | Check for cut or broken mesh, abrasion, loose stitches or knots, damaged border ropes, local stretching, glazing, discoloration, corrosion, loose fixings and structural deformation. |
| 10 | Remove, inspect and store | Obtain removal authorization after overhead fall exposure has ended or alternative protection is in place. Reinstate segregation. Lower panels in the approved removal sequence from independent protected access; control loose ropes and do not drop nets. Inspect and segregate components before storage. Remove or retain anchors and make good the substrate as instructed. | Temporary Works Coordinator and Installation Supervisor | Verify removal authorization, safe access, component condition and substrate closeout. |
Health and Safety Controls
Task risk controls
- Falls during installation, inspection or removal — fatal or serious injury: Work from guarded access wherever practicable; do not step on a net or rely on a partly installed system. Use an independently verified anchorage if personal restraint or arrest is required, with clearance and rescue assessed. PPE: Chinstrap helmet, safety footwear and task-appropriate harness and connector system where required. Collective protection: Guarded platforms, edge protection and closed approaches to exposed edges. Verification: Supervisor checks work-at-height permit, access handover and tie-off arrangements before each phase [Verify per project HSE plan and local regulations].
- MEWP overturn, crush or entrapment — fatal injury: Verify slab or ground support, working reach, travel route, platform load and manufacturer wind limits. Use a banksman where visibility or clearance is restricted. Do not position the platform where an operator can be trapped between controls and the structure without a reviewed control plan. PPE: Helmet, safety footwear and manufacturer- and task-required restraint. Collective protection: Guarded platform, segregation from vehicles and pedestrians, and emergency lowering access. Verification: Operator completes pre-use checks; ground attendant demonstrates familiarity with emergency controls [Verify per project HSE plan and local regulations].
- Dropped tools, anchors or net bundles — struck-by injury: Stop conflicting work, tether suitable hand tools, use secured tool containers and control raising and lowering of panels. Never work beneath suspended material. PPE: Helmet, gloves and safety footwear. Collective protection: Barricaded drop zone covering the handling footprint and credible drop area, with access control. Verification: Supervisor inspects boundaries and rigging before material movement and after any relocation.
- Unverified anchors, concealed services and sharp edges — electrocution, structural damage or failure during a fall: Use only scheduled supports and approved attachment details. Scan and obtain authorization for drilling where required; isolate affected services as necessary. Remove or shield sharp contact points without compromising anchorage. PPE: Eye protection, cut-resistant gloves for handling, and suitable hearing and respiratory protection for drilling as assessed. Collective protection: Drill-zone segregation, isolation and physical chafe protection. Verification: Confirm service clearance and no-drill zones; hold use of each anchor group until inspection and specified tests are accepted [Verify per project HSE plan and local regulations].
- Wind and uncontrolled movement — falls, entanglement or loss of control: Treat loose panels as wind-sensitive loads. Monitor gusts at the work location and stop if the equipment or approved task limit is reached, or earlier if control is lost. Secure partially rigged panels from protected access or lower them before leaving the area. PPE: Chinstrap helmet, suitable gloves and footwear. Collective protection: Maintain segregated handling and drop zones. Verification: Supervisor checks forecast, local conditions and restart readiness [Verify per project HSE plan and local regulations].
- Delayed recovery after a fall — worsening injury or suspension trauma: Stop operations, call the rescue team and secure the area. Recover the casualty by the preplanned means, such as a MEWP positioned to access the net from below, subject to the site-specific geometry. Do not cut the net or send personnel onto it as an improvised rescue. PPE: Rescuers use the specified helmet, fall protection and casualty handling equipment. Collective protection: Keep the rescue route clear and restrict access around the incident. Verification: Confirm named personnel, communications, first-aid response and rescue readiness before release; rehearse as required [Verify per project HSE plan and local regulations].
Environmental Controls
- Concrete drilling dust, where drilled anchors are approved — respirable silica exposure and dust migration: Use suitable on-tool extraction and controlled cleanup; do not dry sweep or use uncontrolled compressed air. Follow the anchor manufacturer's approved hole-cleaning sequence and control any dust generated by that sequence. PPE: Eye protection and suitable fit-tested respiratory protection where required by the exposure assessment. Collective protection: Segregate the drilling area and use extraction at source. Verification: Supervisor checks extraction and dust controls before drilling; monitor exposure where required [Verify per project HSE plan and local regulations].
- Resin, solvents or plant fluids — skin exposure and contamination of soil or drains: Where these products are used, store them upright in secondary containment, use drip trays where appropriate and segregate contaminated cartridges, wipes and absorbents. Use only manufacturer-approved net cleaning methods; do not discharge residues to drains. PPE: Product-compatible gloves and splash eye protection for handling. Collective protection: Bunded storage, spill kits and protected drains in exposed work areas. Verification: Check safety data sheets, storage and spill readiness; record spills and dispose of residues through the approved route [Verify per project HSE plan and local regulations].
- Drilling or powered access noise — worker exposure and disturbance to adjacent areas: Use suitable maintained equipment, limit simultaneous noisy operations and schedule drilling in permitted periods. PPE: Hearing protection as indicated by assessment. Collective protection: Delineate hearing protection zones or use barriers where practicable and compatible with safe access. Verification: Supervisor checks agreed working hours and verifies noise assessment or monitoring where warranted [Verify per project HSE plan and local regulations].
- Offcuts, packaging and rejected synthetic nets — windblown litter and unsafe reuse: Secure lightweight materials during handling, collect offcuts at source and label quarantined components. Segregate accepted recyclables, general waste and contaminated fractions; render condemned nets unusable before disposal in accordance with the asset procedure. PPE: Handling gloves and safety footwear. Collective protection: Lidded containers and a designated quarantine area. Verification: End-of-shift housekeeping checks and waste transfer records where required [Verify per project HSE plan and local regulations].
Quality Assurance and Quality Control
Inspection and traceability
- Link each net ID and test record to the installed bay; record each anchor ID, type, substrate or member, installation results and any proof-test results. Retain dated photographs of joints, critical interfaces and fixings before they become inaccessible.
- Check every net before use and confirm ongoing strength or ageing test evidence at intervals not exceeding 12 months for nets subject to periodic test-mesh testing, or earlier if required by the manufacturer or governing requirements [Verify per project specifications]. Match the tested sample to the net ID and assess the result against the applicable minimum energy-absorption requirement and manufacturer criteria. Do not remove a test mesh except in accordance with the manufacturer's instructions. Visual checks do not extend test validity.
- Inspect the full length of each joint and each perimeter transition. Measure each bay at its controlling geometry and closest obstruction. Record actual values and the drawing revision rather than marking quantitative checks only as pass or fail.
Inspection point rules
- H — Hold: No progression or use until the appointed release authority signs. Obtain Engineer or Client release as required by the accepted ITP.
- W — Witness: Give notice within the contract notice period and record attendance or permitted waiver. A missed witness inspection is not an automatic release; proceed only under the agreed ITP rules.
- R — Review: Verify records, traceability and current revision; record the review result. Inaccessible work must be inspected before concealment.
Defects and change control
Log nonconformities by zone, quarantine suspect equipment and suspend affected releases when protection is uncertain. Escalate design deviations to the Temporary Works Designer. Moving a panel, changing an anchor or joint, increasing the working elevation or introducing an obstruction beneath the net requires review before affected work resumes. Release requires verified corrective action, reinspection and updated drawings and records where applicable.
Attachments and Controlled Forms
Attach the following controlled documents and forms to the project issue; identify each by document number and revision.
- Approved temporary works calculations, design check where required, plan and sections, net and anchor schedules, joining details and deflection envelope.
- Manufacturer instructions, product conformity evidence, net identification and ageing-test register, anchor technical documentation and approved repair criteria.
- Approved task risk assessment, access and handling plan, work-at-height permits, emergency contacts and site-specific rescue plan with access route and retrieval point.
- Receiving, anchorage, installation, joint, geometry and clearance checklists; anchor test plan and test forms where specified; instrument calibration records.
- Inspection request and hold/witness release forms, signed zone handover and status register, and periodic inspection and maintenance forms.
- Incident, damage, quarantine, technical disposition and re-release forms; removal authorization and inventory closeout records.
This content is a read-only public reference. Download or customize to get an editable version.
ITP preview
The first inspection activities from the linked ITP for Method Statement for Installation, Inspection and Maintenance of Safety Nets Beneath Elevated Work Areas:
| Activity | Inspection / Test | Acceptance Criteria | Responsibility | Record |
|---|---|---|---|---|
| Design and installation readiness | Review design, independent check where required, product instructions, drawings, rescue plan and permits for each installation stage. | Current approved layout covers anchor and support capacity, join details, fall geometry, deflected clearance and construction sequence. Access and rescue are practicable and relevant permits are in place. | Temporary Works Designer and Coordinator; Engineer or Client where required | Approved design pack, check certificate where required and readiness release |
| Net and component receipt | Visually inspect each net and accessory; verify net label, approved classification, dimensions and current test evidence. | Traceable, compatible components conform to the approved schedule and are free from defects and undocumented repairs; test evidence is valid where applicable. | Installation Supervisor and QA/QC | Receiving checklist, net register and conformity/test evidence |
| Anchorage inspection and testing | Check each anchor and support condition. Verify installation parameters against the schedule; perform proof tests only at the approved sampling rate, loads and hold times where specified. | All anchors match the verified substrate and approved locations, spacing and details. Applicable torque and cure values are met. Required proof tests satisfy the design acceptance criteria for displacement and condition, and the anchor group is released. | Competent Inspector and Temporary Works Coordinator; tester and Engineer or Client as specified | Anchor log, calibration certificates, proof-test sheets and signed release |
Showing 3 of 9 inspection activities. View full ITP →
Related Inspection and Test Plan
An Inspection and Test Plan (ITP) is available for Method Statement for Installation, Inspection and Maintenance of Safety Nets Beneath Elevated Work Areas. The ITP defines the inspection activities, acceptance criteria, hold and witness points, responsible parties, and records required to verify the work described in this method statement.
View the Method Statement for Installation, Inspection and Maintenance of Safety Nets Beneath Elevated Work Areas ITP →