Inspection and Test Plan for Method Statement: Lean Concrete Sub‑Base (LCB/DLC) for Rigid Pavements
AI-assisted inspection and test plan connected to a method statement, with PDF and Excel export.
More than a static template
Unlike a downloadable Word or PDF template, this ITP is an AI-assisted editable starting point directly connected to its method statement. Every inspection activity, hold point, and acceptance criterion is structured and ready to adapt to your project.
- AI-assisted customization — Tailor inspection activities and acceptance criteria to your specific project scope.
- Linked method statement — This ITP is connected to the corresponding method statement describing the work sequence.
- Multiple export formats — Download as a formatted PDF or editable Excel spreadsheet.
- Editable starting point, not a final document — Review and verify all content against your project specifications and standards before use.
What you can customize
When you save this ITP to your account, every inspection row becomes editable. You can add, remove, or modify:
- Inspection activity — Description of what is being inspected.
- Inspection type — Hold point (H), Witness point (W), Review (R), or Monitor (M).
- Responsibility — Contractor, subcontractor, engineer, or client.
- Frequency — How often the inspection occurs.
- Acceptance criteria — Referenced standard or specification requirement.
- Records — Forms, test reports, or checklists required as evidence.
Why this ITP is used
To control and verify that lean concrete sub-base construction meets specified quality, geometry, finish, and strength requirements.
Who uses this inspection and test plan
QA/QC engineers, site engineers, laboratory staff, construction managers, and the Client/Engineer.
When this ITP is prepared and submitted
Implemented before, during, and after LCB placement—starting with material approvals through to final acceptance.
Who receives or approves this ITP
Engineer/Client Representative
Inspection scope
Covers materials approvals, batching, delivery checks, placement controls, vibration, levels, thickness, curing, bond breaker, and compressive strength testing.
Typical hold, witness, and review points
Pre-pour base/level check (Hold), bond breaker application (Hold/Witness), compressive strength sampling and testing (Witness), final acceptance (Hold).
Typical inspection records
Approved submittals, IRs, delivery tickets, fresh property logs, curing/bond-breaker application logs, strength test reports, thickness/level surveys, NCRs, acceptance certificate.
Important approval note
This ITP is an AI-assisted editable starting point, not a pre-approved document. Before use on any project, all inspection activities, hold points, and acceptance criteria must be reviewed and approved by the relevant parties (superintendent, principal contractor, or client representative) in accordance with your contract and project quality plan.
Always verify acceptance criteria against your applicable drawings, specifications, and regulatory requirements. Hold points must be confirmed with the relevant authority before work proceeds past that point.
Inspection and test plan
| Activity | Inspection / Test | Acceptance Criteria | Responsibility | Record |
|---|---|---|---|---|
| Materials approvals | COC/COA comply with referenced standards; approvals in place. | QA/QC Engineer | Approved submittals | |
| Batch plant calibration | Calibration current; tolerances within manufacturer/spec. | QA/QC Engineer | Calibration certificates | |
| Pre-pour base and level check | Base clean; moisture acceptable (no free water); levels within ±5 mm. | Site Engineer | Pre-pour IR, checklist | |
| Concrete delivery verification | Temp (ASTM C1064); Vebe/slump (BS EN 12350-3/ASTM C143); unit weight (ASTM C138) as scheduled | Temp 5–32°C; Vebe 10–20 s or slump ≤25 mm; delivery ≤90 min. | Lab Technician | Field test reports; tickets |
| Placement and screed vibration | Vibrator frequency check | 4,000–7,000 vpm [Verify]; uniform head; no segregation/honeycomb. | Paver Operator / QA/QC | Equipment log; site diary |
| Surface regularity and level | 3 m straightedge; level survey | Straightedge ≤10 mm; level ±10 mm. | Site Engineer / QA/QC | QC checklist; survey file |
| Thickness verification | Direct measure/cores | +10/−5 mm; average ≥ design. | QA/QC Engineer | Thickness report |
| Curing application | Visual, coverage confirmation | Uniform membrane at 0.4–0.5 L/m², no holidays. | Foreman / QA/QC | Curing log |
| Bond breaker installation (if specified) | Visual; film rate; overlap check | Emulsion 0.3–0.5 kg/m² continuous; or PE sheet 125–200 µm with 150 mm overlapped and taped. | Site Engineer / QA/QC | IR; application log; photos |
| Compressive strength testing | ASTM C31 (making/curing), ASTM C39 (testing) or EN 12390 | Average ≥ f'c; no individual <0.85 f'c [Verify]. | Lab Technician | Lab test reports |
| Final acceptance and release | Document review and walkdown | All ITP items closed; NCRs resolved; records complete. | Engineer / QA/QC | Acceptance certificate |
This table is a read-only public reference. Download the PDF or Excel version, or customize this ITP to edit it for your project.
Frequently asked questions
Related method statement
This Inspection and Test Plan is associated with the Method Statement: Lean Concrete Sub‑Base (LCB/DLC) for Rigid Pavements method statement, which describes the step-by-step construction sequence, resources, materials, equipment, safety controls, and environmental controls for this activity.
View the Method Statement: Lean Concrete Sub‑Base (LCB/DLC) for Rigid Pavements method statement →