Ncr Form Template

Download a practical NCR form template used on construction projects. Includes key fields for QA/QC non-conformance description, specification references, corrective action, verification, and closure.

Ncr Form Template
Ncr Form Template
English version

NCR Form Template

Use this NCR (Non-Conformance Report) form template to record and close construction non-conformances consistently, with the minimum fields expected by most QA/QC systems.

Best use: site QA/QC teams, consultants, and contractors who need a clean NCR format with clear references and closure evidence.


Download NCR Form Template


ncr form nonconformance report
Screenshot of the NCR (Non-Conformance Report) form template used for construction QA/QC documentation and closure.

What this NCR form includes (fields)

Need the definition and workflow?ย Read NCR Meaning in Construction (when to issue an NCR, who fills each section, and how NCRs are closed).

A) NCR identification

  • Project / package / contract

  • NCR number (unique reference)

  • Date raised

  • Raised by (company + name)

  • Responsible party (main contractor / subcontractor)

B) Location & work description

  • Building / zone / gridline / level / chainage

  • Trade / discipline (civil, architectural, MEP, steel, etc.)

  • Activity / element (slab, column, waterproofing, cable pulling, etc.)

C) Non-conformance description (facts only)

  • What was found (measured/observed/test result)

  • Quantity/extent (how much area affected)

  • Evidence reference (photos, sketches, marked-up drawings)

D) Requirement references (the most important part)

  • Specification section / clause

  • Drawing number + revision

  • Approved shop drawing / method statement reference

  • ITP step / WIR reference (if applicable)

  • Standard/code reference (if applicable)

E) Immediate action / containment

  • Stop affected activity (Yes/No)

  • Quarantine material (Yes/No)

  • Protect from concealment (Yes/No)

  • Temporary measures implemented

F) Contractor response

  • Root cause (why it happened)

  • Corrective action (how it will be fixed)

  • Preventive action (how recurrence is prevented)

  • Target dates

G) Engineer / Consultant disposition

  • Accept as-is (with justification)

  • Repair

  • Remove and replace

  • Accept with concession / technical deviation (if allowed)

H) Verification & closure

  • Re-inspection date

  • Re-test results reference (if applicable)

  • Closure evidence attached (photos/reports)

  • Closed by + date + signature


How to fill an NCR (quick guidance)

  1. Write the non-conformance as a measurable fact (not an opinion).

  2. Always include at least one hard reference: spec clause or drawing number.

  3. Record containment actions immediately (stop/quarantine/protect).

  4. Require contractor response with root cause + corrective + preventive action.

  5. Close only after verification evidence is submitted and accepted.


Suggested numbering system (simple and scalable)

Use one consistent format, for example:
NCR-Discipline-Year-Sequential

  • NCR-CIV-2026-001

  • NCR-MEP-2026-014

If you manage multiple packages, add package code:

  • NCR-PKG1-CIV-2026-001


Common mistakes (avoid these)

  • No reference to specs/drawings (โ€œnot acceptableโ€ is not enough)

  • Closing without evidence

  • Using NCRs for minor snags (creates noise and weakens the system)

  • Not controlling the affected work/material (containment)


Related pages (published separately)

  • NCR Meaning in Construction

  • NCR Log Template (Register)

  • Observation vs NCR vs Snag vs Defect


Filled Example NCR (Concrete Works)

A) NCR identification

  • Project: ABC Residential Towers โ€“ Package 01

  • NCR No.: NCR-CIV-2026-003

  • Date raised: 06 Jan 2026

  • Raised by: Consultant QA/QC Engineer

  • Responsible party: Main Contractor / RC Subcontractor

B) Location & work description

  • Location: Tower A, Level 05, Grid B-4 to B-6

  • Discipline / Trade: Civil / Reinforced Concrete

  • Element / Activity: Reinforcement fixing for slab S5 prior to concrete pour

C) Non-conformance description (facts only)

During pre-pour inspection, the top reinforcement spacing in the slab strip at Grid B-4 to B-6 was measured at 250 mm c/c, whereas the approved drawing requires 200 mm c/c. The affected area is approximately 18 mยฒ.
Evidence: Photo refs NCR-CIV-2026-003-01 to 05 and marked-up sketch SK-NCR-003.

D) Requirement references

  • Structural drawing: S-105 Rev 04 (Top reinforcement spacing @ slab strip = 200 mm c/c)

  • Specification: Section 03 30 00 โ€“ Cast-in-Place Concrete, clause (reinforcement installation per drawings)

  • ITP: ITP-RC-01, Hold Point HP-03 (Pre-pour rebar inspection)

  • WIR: WIR-RC-05-147 (submitted for pre-pour inspection)

E) Immediate action / containment

  • Stop affected activity: YES (pour not permitted in affected zone)

  • Prevent concealment: YES (do not place concrete until clearance)

  • Quarantine material: N/A

  • Temporary measures: Affected area tagged and barricaded; foreman instructed not to proceed.

F) Contractor response (root cause + corrective + preventive)

  • Root cause: Fixing crew used an outdated rebar spacing note from an earlier revision and the supervisor did not verify against the latest approved drawing revision.

  • Corrective action: Remove and re-fix top reinforcement in the affected zone to 200 mm c/c as per S-105 Rev 04. Submit re-inspection request.

  • Preventive action: Toolbox talk for rebar crew; supervisor to verify drawing revision on site before start of fixing; drawing revision list to be posted in the rebar yard.

  • Target date: Corrective action completed by 07 Jan 2026; re-inspection on 07 Jan 2026.

G) Engineer / Consultant disposition

  • Disposition: Repair / Rectify

  • Notes: Works may proceed only after re-inspection and acceptance of corrected spacing. No concrete placement permitted in affected zone prior to clearance.

H) Verification & closure

  • Re-inspection date: 07 Jan 2026

  • Verification outcome: Spacing re-measured at 200 mm c/c; accepted.

  • Closure evidence: Photo refs NCR-CIV-2026-003-C1 to C3; updated marked-up sketch attached.

  • NCR status: CLOSED

  • Closed by: Consultant QA/QC Engineer โ€“ 07 Jan 2026

Lena Miller's photo
Lena Miller
Jan 08, 2026
4
11
1.79k+
2.05k+

Ncr Form Template

Frequently Asked Questions


FAQ

Q: What is an NCR form in construction?

A: An NCR (Non-Conformance Report) form is a QA/QC record used to document work or materials that donโ€™t meet project requirements, reference the applicable spec/drawing/ITP, and track corrective actions through verification and closure.

FAQ

Q: When should I use an NCR instead of a snag list?

A: Use an NCR for confirmed non-compliance (spec/drawing/ITP breach, failed test, rejected inspection). Use a snag/punch item for minor completion or finishing issues that donโ€™t require formal corrective action tracking.

FAQ

Q: Who fills the NCR form (issuer vs contractor)?

A: The issuer records the non-conformance description and references. The contractor proposes root cause plus corrective/preventive actions. The engineer/consultant confirms disposition and closes the NCR after verification.

FAQ

Q: Do NCR forms need signatures?

A: Many projects require sign-off (raised by, contractor acknowledgement, engineer disposition, closure verification). On digital workflows, names + roles + dates and a PDF export often replace handwritten signatures.

FAQ

Q: What references should be included in an NCR?

A: At minimum, cite the relevant drawing number/revision or specification clause. If applicable, add the ITP step/hold point, WIR number, approved shop drawing, and test report reference.

FAQ

Q: Is an NCR the same as a Corrective Action Request (CAR)?

A: Theyโ€™re related but not always the same. Many projects use an NCR for the non-compliance record and a CAR for the corrective action process (or for repeated/systemic issues). Some QA systems combine both into one form.

Related Checklists


Remediate Pile Defects Checklist: Grout or Core Repair
โœ… 26 items
Remediate pile defects with a disciplined, field-proven process focused on pressure grouting or core repair, verification, and closing nonconformance reports. This checklist guides supervisors, QC engineers, and contractors through practical pile repair steps without adding new tests, relying on the approved investigation and method statement. It helps decide between pressure grouting for internal voids or core repair for localized damage, manages materials and equipment, and controls grouting pressures, volumes, and curing. You will capture photo evidence, pressure/volume logs, batch certificates, and as-built sketches to demonstrate that defective piles are restored to intent per approved project specifications and authority requirements. The scope excludes new integrity or load testing; verification depends on process records, dimensional checks, and joint inspections. Outcomes include safe, durable repairs, traceable documentation, and timely NCR closure. Use this interactive checklist to tick off actions, add field comments, and export a QR-secured PDF/Excel package for review and archiving.
Compile pile dossier for handover: QA docs checklist
โœ… 24 items
Compile pile dossier for handover is your structured process for organizing and validating all pile-related documentation prior to client acceptance. This piling documentation checklist focuses on the pile QA dossier, ensuring verifiable records for installation, testing, calibrations, and as-built deliverables while explicitly excluding general foundation records such as pile caps or ground beams. By curating only pile-specific evidenceโ€”installation logs, static and dynamic load test reports, integrity test summaries, instrument calibration certificates, and NCR closuresโ€”you reduce disputes, avoid rework, and accelerate taking-over. The outcome is a clean, traceable package that demonstrates compliance per approved project specifications and authority requirements, with consistent file naming, signatures, and revision control. Practical acceptance cues, SI-based tolerances, and geo-referenced evidence help teams close gaps quickly and defend quality under audit. Use this interactive checklist to assign actions, capture photo and file attachments, add comments, and track digital sign-offs. Start ticking items, comment where needed, and export the dossier as PDF/Excel with an embedded QR code.
Repair Driven Pile Heads/Splices: Weld, QA and Coating
โœ… 22 items
Repair driven pile heads/splices is a focused jobsite process to restore integrity of driven steel pile heads and welded splices after driving. This checklist addresses pile head repair, pile splice welding, weld rectification, protective coating application, and QA records. It explicitly excludes driving logs and production data, concentrating instead on defect identification, alignment and fit-up, qualified welding, nondestructive testing, and corrosion protection. By following these steps, teams reduce structural risk from crack propagation, misalignment, and coating failure, while creating a defensible audit trail. Each instruction pairs a method or tool with acceptance evidenceโ€”measurements in millimetres, temperature readings, NDT reports, coating thicknesses, photos, material heat numbers, and signaturesโ€”per approved project specifications and authority requirements. Use this checklist to organize work zones, capture approvals, and prevent rework, ensuring consistent, traceable repairs that stand up to independent review. Start in interactive mode to tick tasks, add comments, and export PDF/Excel with a secure QR for field sign-off.
Inspect retaining wall footing reinforcement (horizontal)
โœ… 26 items
Inspect retaining wall footing reinforcement (horizontal) is a critical pre-pour task that validates the rebar layout against the approved drawings and schedules. This checklist focuses on horizontal reinforcement within the footing, including bar sizes, spacing, lap splices, bar cover, supports, and the dowels that connect the footing to the wall stem. It excludes concrete-related controls and tests, keeping the scope clearly on steel placement and documentation. By verifying the reinforcement schedule, confirming chairs and spacers, checking dowel alignment, and measuring laps with a tape or rebar gauge, you prevent under-reinforcement, bar corrosion from inadequate cover, and stem misalignment due to misplaced dowels. The outcome is a compliant installation ready for form closure and further inspections, backed by photo evidence, material identification, and sign-offs per approved project specifications and authority requirements. Use this interactive checklist in the field: tick each item, add comments for nonconformances, and export your record as PDF or Excel with a QR code for authentication.
Terminate waterproofing at pile heads: prime, fillet, seal
โœ… 22 items
Terminate waterproofing at pile heads is a focused activity ensuring clean, primed, filleted, sealed, and protected terminations at each pile interface. This checklist zeroes in on pile head waterproofing termination details, including primer selection, cove fillets, termination bars, and protective measures, while explicitly excluding installation of general membranes. Executed correctly, it prevents water ingress, freezeโ€“thaw damage, steel corrosion, and premature deterioration at the slabโ€“pile junction. You will confirm substrate condition, apply compatible primer, form a consistent fillet, install a robust sealant band or termination bar detail, and protect the termination from construction traffic and backfill. Outcomes include durable, inspectable terminations with photo evidence, logged batch numbers, and traceable approvals per approved project specifications and authority requirements. Use this interactive checklist on mobile or tablet: tick items as completed, leave comments for issues, attach photos for verification, and export your record as PDF/Excel with a secured QR for sign-off.

Related Articles


Ncr At Handover
โณ 5 min read
Open Ncrs At Taking-over / Dlp: What Happens At Handover And How To Escalate
Can taking-over happen with open NCRs? Learn when handover is allowed, when it must be blocked, how to document outstanding NCRs, and when to escalate to contractual notices (e.g., Notice to Correct) through common contract authorities.
Ncr Meaning Construction
โณ 3 min read
Ncr Meaning In Construction (qa/qc Non-conformance Report Guide)
NCR meaning in construction: an NCR (Non-Conformance Report) is a QA/QC record issued when work or materials donโ€™t meet project requirements. Learn when to issue an NCR, who issues it, and how itโ€™s closed.
Ncr Log Template E46
โณ 2 min read
Ncr Log Template (register & Ncr Tracker) โ€“ Excel/pdf Download
Download an NCR log template (NCR register) to track non-conformance reports by ID, date, status, location, references, actions, and closure. Includes an empty template and a filled example in Excel and PDF.
Request For Inspection For Contractors
โณ 2 min read
Request For Inspection For Contractors
Download free professional Inspection Request Forms / templates for construction projects in Word, PDF and Excel formats. Perfect for contractors, consultants, and subcontractors, these templates ensure compliance and inspection processes. Free and customizable! You don't need to singup
Request For Quotation Rfq Form Template
โณ 3 min read
Rfq Form Template For Procurement | Free Download (pdf, Excel, Word)
Download a free, customizable Request for Quotation (RFQ) form template. Ideal for small tenders; available in PDF, Excel, Word formats to streamline procurement.