G
Guest

Fidic Site Instruction Form Download Usage

Download our free FIDIC Site Instruction form. Learn how to use it in any FIDIC edition, track variations, and protect against disputes with proper records.

Fidic Site Instruction Form Download Usage
Fidic Site Instruction Form Download Usage
English version

FIDIC Site Instruction Form – Free Download and Usage Tips

Introduction
In any FIDIC contract, the Engineer has the authority to issue instructions to the contractor to ensure proper execution of the works. These Site Instructions are legally binding and must be complied with immediately, regardless of whether they come on an official form, in meeting minutes, or via marked-up drawings.

This mini guide focuses specifically on the FIDIC Site Instruction form we designed at Quollnet — a practical tool for documenting, tracking, and managing instructions in a way that aligns with FIDIC’s requirements and reduces the risk of disputes.

Download the FIDIC Site Instruction Form – PDF, Excel, WebP


About Clause Numbering

Note: In the FIDIC 1999 and 2017 Red Book editions, Engineer’s Instructions are addressed in Clause 3.3. In earlier FIDIC versions (such as the 1977 and 1987 editions), the numbering differs, but the underlying principle — the Engineer’s authority to issue instructions — is the same. Always check your specific contract edition for the correct clause reference.


Purpose of the Form

The form provides a standardized method to issue instructions, ensuring:

  • Clear, concise communication of the directive.

  • Proper contractual reference and supporting documentation.

  • Traceability through the Site Instruction Register.

  • A direct link between the instruction, related variations, and potential claims under Clause 20.


When to Use the FIDIC Site Instruction Form

While Engineer’s Instructions can be issued in many formats, the dedicated form should be used when you want a clear, auditable record. Common scenarios include:

  • Design clarifications or corrections.

  • Safety measures requiring immediate action.

  • Coordination changes between trades.

  • Appointment of nominated subcontractors.

  • Owner-requested changes for convenience.

  • Instructions due to unforeseen site conditions.

  • Remedial work following non-conformance reports.

For the broader legal context of when an instruction applies, see our Complete Guide to Site Instructions.


How to Fill the Form

The downloadable form includes the following sections:

Header:

  • Project name, number, address.

  • Contractor/Subcontractor details.

  • Employer and Engineer names.

  • Instruction number, revision, date.

Instruction Details:

  • Subject/title.

  • Description (clear and actionable).

  • Reason for the instruction.

  • Required action and completion date.

  • Reference documents (drawings, specs, correspondence).

  • Contract clause reference (per your edition).

Impact Assessment:

  • No cost/time impact expected.

  • Potential cost impact (contractor to submit quotation).

  • Potential time impact (contractor to submit revised program).

  • Other (specify).

Signatures:

  • Engineer/Consultant (before issue).

  • Contractor acknowledgment.

Mandatory Statement:

“This Site Instruction is issued under the clause of the Contract governing Engineer’s Instructions. The Contractor shall comply immediately. If the Contractor considers that the instruction will result in an adjustment to the Contract Price and/or Time for Completion, notice shall be given in accordance with the relevant claims clause.”


Best Practices for Using the Form

  1. Number sequentially to maintain a clear record.

  2. Reference the correct clause for your contract edition.

  3. Be specific — avoid vague terms like “as discussed.”

  4. Attach supporting documents with clear identifiers.

  5. Record the impact assessment truthfully.

  6. Log it in the Site Instruction Register immediately.

  7. Link related instructions to variations/claims.


Download the Form

Download FIDIC Site Instruction Form – PDF
Download FIDIC Site Instruction Form – Excel
Download FIDIC Site Instruction Form – WebP

fidic site instructions by quollnet


Related Reading

Elie Saad's photo
Elie Saad
Aug 10, 2025
0
51
849
2.53k+

Related Checklists


Retaining wall stem reinforcement (vertical) inspection
✅ 24 items
Retaining wall stem reinforcement (vertical) inspection confirms the vertical rebar is installed to the approved drawings before any concrete is placed. This focused checklist supports vertical rebar checking, retaining wall steel fix inspection, and bar spacing and cover checks on the stem only, excluding concreting. You will verify bar sizes and spacing, concrete cover using spacers and a covermeter/template, lap splice lengths or couplers, and detailing around openings and embedded items. By capturing measurements, photos, and approvals, you reduce risks of inadequate cover, misaligned bars, insufficient development, congestion at openings, and costly rework. The outcome is a compliant, durable stem that accepts formwork and subsequent concreting without clashes, while meeting the approved project specifications and authority requirements. Use this as a hold‑point inspection: measure, mark any corrections, and record evidence for quality assurance. Start the interactive mode to tick items, leave comments for the steel fixer, and export your completed record to PDF/Excel with a secured QR code.
Substrate Inspection Checklist for Waterproofing
✅ 12 items
Ensuring the substrate is properly prepared and inspected is crucial before applying any waterproofing materials. This checklist guides construction professionals through a comprehensive inspection process to identify potential issues that could compromise the waterproofing application. By following this checklist, you will enhance the longevity and effectiveness of the waterproofing layer, prevent costly repairs, and ensure the structural integrity of the building. Whether you are a site manager or an inspector, these steps will help you perform a thorough evaluation of the substrate, ensuring it is ready for the next phase of construction.
Carpentry and Joinery Installation Inspection Checklist
✅ 15 items
This Carpentry and Joinery Installation Inspection Checklist is designed to guide construction professionals in assessing the quality and accuracy of carpentry and joinery work on site. Whether you are a site manager, a quality assurance inspector, or a skilled tradesperson, this checklist provides a structured approach to ensuring installations meet industry standards and client specifications. It covers essential aspects such as materials, workmanship, safety, and compliance, helping you to identify and address potential issues before they escalate. Proper inspections not only enhance the durability and safety of the structures but also ensure customer satisfaction and project success.
Repair Driven Pile Heads/Splices: Weld, QA and Coating
✅ 22 items
Repair driven pile heads/splices is a focused jobsite process to restore integrity of driven steel pile heads and welded splices after driving. This checklist addresses pile head repair, pile splice welding, weld rectification, protective coating application, and QA records. It explicitly excludes driving logs and production data, concentrating instead on defect identification, alignment and fit-up, qualified welding, nondestructive testing, and corrosion protection. By following these steps, teams reduce structural risk from crack propagation, misalignment, and coating failure, while creating a defensible audit trail. Each instruction pairs a method or tool with acceptance evidence—measurements in millimetres, temperature readings, NDT reports, coating thicknesses, photos, material heat numbers, and signatures—per approved project specifications and authority requirements. Use this checklist to organize work zones, capture approvals, and prevent rework, ensuring consistent, traceable repairs that stand up to independent review. Start in interactive mode to tick tasks, add comments, and export PDF/Excel with a secure QR for field sign-off.
Site Survey and Layout Benchmark Inspection Checklist
✅ 15 items
The site survey and layout benchmark inspection is a crucial preparatory phase in construction projects. It involves verifying the accuracy of the site's initial survey and the placement of layout benchmarks before any physical work begins. This step ensures that the project aligns with design specifications and prevents costly errors and delays. This checklist provides a comprehensive guide to inspecting various aspects of site surveys and benchmarks, helping professionals ensure quality and compliance. Users can interact with this checklist online, ticking off items, adding comments, and exporting the report as a PDF or Excel file, complete with QR code authentication for traceability.

Related Articles


Site Instructions Construction Legal And Forms
⏳ 5 min read
Site Instructions In Construction: Legal Guide & Templates
Learn what site instructions (Engineer’s, Architect’s, PM’s Instructions, ASI, Work/Field Orders) mean legally in FIDIC, JCT, NEC & AIA, with free forms.
Aia Architects Supplemental Instruction Form
⏳ 2 min read
Aia Architect’s Supplemental Instruction (asi) – Free Form And Usage Tips
Download our free AIA Architect’s Supplemental Instruction (ASI) form. Learn how to use it for minor changes with no cost/time impact, per AIA contracts.
Site Clarification Rfi Free Templates Log Flowchart
⏳ 5 min read
Site Clarifications (rfis) — Definition, Legal & Free Templates
Learn what a site clarification (RFI) is, the legal line between clarification and instruction, and download free templates: RFI log (Excel/CSV), checklist, and flowchart.
Aia Construction Change Directive Form
⏳ 2 min read
Aia Construction Change Directive (ccd) – Free Form And Usage Tips
Download our free AIA Construction Change Directive (CCD) form. Learn how to use it for changes affecting cost/time when terms aren’t yet agreed.
Fidic Site Instruction Form Download Usage
⏳ 3 min read
Formulaire D'instruction De Chantier Fidic – Téléchargement Gratuit Et Conseils D'utilisation
Téléchargez notre formulaire d'instruction de chantier FIDIC gratuit. Apprenez à l'utiliser dans n'importe quelle édition FIDIC, suivez les variations et protégez-vous contre les litiges avec des enregistrements appropriés.