G
Guest

How To Create a Project Cash Flow For Contractors

Learn how to create a comprehensive cash flow for construction projects, including key contract conditions, subcontractor retention, work in excess of billing (WIEB), advance payments, and indirect costs. This step-by-step guide helps contractors manage project cash flows efficiently.

How To Create a Project Cash Flow For Contractors
How To Create a Project Cash Flow For Contractors
English version

How to Create a Project Cash Flow for Contractors

Managing cash flow is critical for contractors working on construction projects. An accurate project cash flow plan allows you to keep track of costs, plan for payments, and ensure that the project remains financially viable. This guide will help you understand how to create a project cash flow, incorporating key components like contract conditions, activity planning, indirect costs, and financial adjustments such as retention, work in excess of billing (WIEB), and advance payments.

1. Understanding Main Contract Conditions

The main contract contains several terms that directly affect cash flow. As a contractor, you must be aware of these conditions, as they will guide the timing and structure of your project’s inflows and outflows:

  • Time for Payment : The period between submitting a bill and receiving payment from the client (e.g., 30 or 60 days).
  • Retention : A percentage of each payment withheld by the client until certain milestones are met. This is usually released in two stages:
    • At Handover : A portion of the retention is released when the activity is completed.
    • At the End of Defect Liability Period (DLP) : The remainder is released after the DLP is complete, during which any defects must be corrected.
  • Advance Payment : Some contracts include an advance payment to the contractor at the start of the project. This advance is typically deducted from subsequent payments on a prorated basis.

2. Identify Financial Constants

Before starting cash flow calculations, you must define certain financial parameters:

  • Interest Rate or Desired Rate of Return (ROR) : This is the interest rate you will use when calculating the cumulative cash flow.

3. Planning Project Activities

Each project must be broken down into individual activities. For each activity, consider the following factors:

  • Start Date and Duration : When the activity will begin and how long it will last.
  • Work Period and No-Work Periods : Some activities may involve mobilization or manufacturing, where no site work is performed but costs are incurred.
  • Cost of Each Activity : Determine the total cost for each activity (e.g., excavation, foundation work, etc.).
  • Percent Subcontracted : Determine how much of the work is subcontracted. Subcontracted work is often subject to retention, WIEB, and advance payment adjustments.
  • Work in Excess of Billing (WIEB) : WIEB refers to work that has been completed but not billed yet. This will affect cash flows in subsequent billing cycles.

4. Managing Indirect Costs

Indirect costs refer to overhead costs that are not directly tied to specific activities but are necessary for the project's execution. These include:

  • Human Resources : Salaries for administrative personnel, site supervisors, etc.
  • Equipment : Costs for equipment rental, operation, and maintenance.
  • Temporary Mobilization : Setting up temporary infrastructure such as site offices.

To account for indirect costs in cash flow, you can create "fake activities" that spread the costs over their duration. For example, temporary site offices may incur costs throughout the entire project, while equipment may only be needed for certain phases.


cashflowpot screen01

Step-by-Step Cash Flow Process

A. Creating a Work Cash Flow for Each Activity

You can use mathematical formulas to better predict each activity work flow distribution: in this

For each activity, calculate the cash flow using the following steps:

  1. Start Date and Duration : Determine when the activity begins and how long it will last.
  2. Cost Spread : Divide the total cost of the activity by its duration to get the period cost. nb: this is an estimation that the cost is spread equally. This is not true in most cases. For this reason application such as CASHFLOWPOT.com can assist you in doing a more accurate curved spread.
    Monthly Activity Cost = Total Activity Cost / Duration (Months)
  3. Subcontracted Work : For subcontracted work, account for WIEB, retention, and advance payments in cash flow calculations.
  4. WIEB Adjustment : Work in excess of billing for subcontracted activities needs to be moved to the next period's cash flow:
    Work Cash Flow = (1 - WIEB) * Work of Previous Period + Work of Current Period * WIEB

B. Calculating the Outflow for Each Activity

Outflows include the cost of the activity, retention, and advance payment deductions. The formula for outflow is as follows:

Outflow = Activity Cost - Retention (for this period) - Advance Payment (if applicable)

Work in excess of billing (WIEB) should not be included in the outflow for the current period but carried over to the next billing period.

C. Total Work Cash Flow and Total Outflow

To get the total work cash flow and outflow for a given period, sum the cash flows and outflows from all activities:

Total Work Cash Flow = ∑ (Monthly Cash Flow for each activity)Total Outflow = ∑ (Monthly Outflow for each activity)

D. Generating the Project Inflow

Inflow represents the amount billed to the client, adjusted for WIEB, retention, and advance payment recovery:

Inflow = (1 - WIEB) * Work of Previous Period * % Subcontracted         + Work of Current Period * WIEB * % Subcontracted         + Work of Current Period * (1 - % Subcontracted)

After calculating inflow, deduct the retention and any recovery of advance payments.

E. Net Cash Flow and Cumulative Cash Flow

Calculate the net cash flow by subtracting outflows from inflows:

Net Cash Flow = Inflow - Total Outflow

To calculate cumulative cash flow, account for the interest rate or desired return on investment:

Cumulative Cash Flow = ∑ (Net Cash Flow * (1 + Interest Rate))

Application that will do all this for you


Get help with your cashflow web app

go to CASHFLOWPOT.com

Example of Cash Flow Calculation

Let's consider a project with the following conditions:

  • Foundation work starts in Month 1 and lasts 3 months, with a total cost of $200,000.
  • 80% of the foundation work is subcontracted, while 20% is done by the contractor directly. The subcontracted portion is subject to retention, WIEB, and advance payment.
  • Work in Excess of Billing (WIEB) is 10%, meaning 10% of the subcontracted work in Month 1 will be moved to Month 2 for billing.
  • Retention is 5%, with 50% released at the handover and 50% at the end of the Defect Liability Period (DLP).
  • An advance payment of $50,000 was given to the subcontractor, to be deducted on a prorated basis.

Month 1 Breakdown

1. Work Done in Month 1:

Total monthly cost: $66,667 ($200,000 / 3 months).

Subcontracted Portion (80%) :

66,667 * 0.8 = 53,334

Contractor Portion (20%) :

66,667 * 0.2 = 13,333

2. Work in Excess of Billing (WIEB):

10% of the subcontracted work will be billed in Month 2.

WIEB = 53,334 * 0.1 = 5,333

Billed Amount for Subcontracted Work in Month 1 :

53,334 - 5,333 = 48,001

3. Retention:

Retention for the subcontracted portion is 5%.

Retention = 48,001 * 0.05 = 2,400

4. Advance Payment Deduction:

The advance payment of $50,000 is spread evenly over 5 payments:

Advance Payment Deduction = 50,000 / 5 = 10,000

5. Outflow Calculation:

Subcontracted Outflow for Month 1 :

Outflow = 48,001 - 2,400 (Retention) - 10,000 (Advance Payment) = 35,601

Contractor's Outflow (not affected by WIEB or retention):

Outflow = 13,333

6. Total Outflow for Month 1:

Total Outflow :

Total Outflow = 35,601 (Subcontracted) + 13,333 (Contractor's Portion) = 48,934

The total outflow for Month 1 is $48,934.

Elie Saad's photo
Elie Saad
Dec 17, 2024
58
132
11.44k+
5.25k+

Related Checklists


Install CFA/Auger-Cast Piles: Speed, Pressure, Volume
✅ 24 items
Install CFA/auger-cast piles with disciplined control of auger speed, grout pressure, and placed volume. This field-ready guide focuses on continuous flight auger (CFA) production, also known as augercast piles, emphasizing parameter monitoring, pump flow management, and real-time logging against theoretical volume. You will find practical steps to calibrate sensors, regulate auger withdrawal rate, maintain positive head, and document outcomes. The scope covers setup, drilling, pumping, and reinforcement insertion only; post-install integrity testing methods are intentionally excluded and handled separately per approved project specifications and authority requirements. Following this checklist helps avoid necking, inclusions, and uncontrolled ground movement, while delivering the designed geometry and continuity of the pile shaft. Use it to brief crews, run shifts, and close out daily reports with defensible records. Switch to interactive mode to tick items, add comments and photos, and export results to PDF/Excel secured via a QR code.
Place Non-Shrink Grout Pads/Capping Checklist & QA Guide
✅ 28 items
Place non-shrink grout pads/capping is a focused activity that demands disciplined mix control, careful placement, thorough curing, and tight verification of flatness and level. This checklist supports supervisors and inspectors executing nonshrink grout capping and grout pad works while intentionally excluding bearing surface preparation, which must be completed and accepted beforehand. You will confirm batch tickets and water-to-powder ratios, verify flow spread and working time, and place grout to thickness while avoiding segregation and cold joints. Finishing uses straightedges and laser levels to achieve precise elevation and planarity, followed by moisture-retentive curing to lock in non-shrink performance. The outcome is predictable, dimensionally accurate pads/caps ready for subsequent installations, avoiding rocking supports, misalignment, premature cracking, or understrength issues. Use this interactive page to tick each step, add field comments and photos, and export a complete QA pack to PDF/Excel with a QR code that secures traceability and site acceptance.
Construction Tender Document Review Checklist
✅ 14 items
The construction tender document review is a critical process undertaken by contractors upon receiving a tender invitation. This phase involves a thorough examination of all documents associated with the tender to determine the feasibility and desirability of bidding on the project. The review includes evaluating project specifications, timelines, costs, and legal implications. This checklist ensures that contractors meticulously assess each component to make an informed bid decision, minimizing risks and enhancing the quality of the bid. Users can interact with the checklist by ticking off items, adding comments, and exporting the results as PDF or Excel, complete with a QR code for authenticity.
Audit temporary signage and wayfinding for compliance
✅ 20 items
Audit temporary signage and wayfinding for compliance is a focused field process that validates the placement, legibility, and maintenance of temporary notices, hazard boards, and traffic arrows against the approved logistics plan. This temporary wayfinding audit concentrates on construction and shutdown environments where routes, gates, and workfaces change frequently, minimizing confusion and collision risks. The checklist deliberately excludes permanent signs, concentrating only on movable, project-controlled signage for site signage compliance. You will verify mounting heights, spacing intervals, orientation, reflectivity, and night visibility, then capture geotagged photos and mark-ups tied to the latest plan revision. By aligning temporary signs with current routes and access points, crews and visitors navigate safely, deliveries arrive efficiently, and emergency paths remain clear. Use this practical, field-ready tool to standardize evidence, trigger corrective actions, and close out observations promptly. Start in interactive mode to tick items, add comments, assign actions, and export PDF/Excel with a QR-secured record.
HVAC Ductwork Rough-In Inspection Checklist
✅ 15 items
Inspecting HVAC ductwork rough-in before covering is a critical phase in construction, ensuring that all duct installations meet specified standards and are free from defects. This process involves checking the layout, alignment, and connections of ductwork systems in buildings to ensure efficient air flow and system functionality. This checklist focuses on pre-cover inspections, offering a step-by-step guide to verify the quality and compliance of duct installations. By using this interactive checklist, professionals can tick off completed tasks, add comments, and export their reports, ensuring a thorough and documented inspection process.

Related Articles


Construction Project Retention
⏳ 3 min read
Retention In Construction: Formulas, Bonds & Accounting Guide
Learn how construction retention works with clear formulas, bond types, accounting entries, and examples. Ensure cash flow and quality in your projects.
Master Construction Project Cashflow With Cashflowpot
⏳ 1 min read
Master Construction Project Cashflow With Cashflowpot
Learn how to optimize your construction project cash flow using CASHFLOWPOT in this easy-to-follow tutorial. From setting up new projects to adding activities and tracking cash flow, this guide will help you efficiently manage your finances. Plus, learn how to export your cash flow data to Excel for in-depth analysis. Ideal for both beginners and experienced construction managers.
Quollnet Cashflow
⏳ 2 min read
How To Use Quollnet To Predict Construction Project Cashflow
Quollnet project cashflow simulates real-life project work progress to generate cashflow projections. Enter project cost, advance payment, duration, retention, and more to forecast your cashflow.
Construction Cashflow Prediction
⏳ 7 min read
Construction Project Cash Flow Prediction
Learn how to accurately predict construction project cash flows using mathematical models such as polynomial and exponential curves. Discover essential adjustments, including advance payments, retention deductions, payment delays, and work-in-progress billing, to align predicted work with real cash outflows.
Advance Payment Construction Contracts
⏳ 5 min read
Advance Payment In Construction Contracts: Legal Provisions, Recovery Formulas, And Key Insights
Explore the essentials of advance payments in construction contracts, including their purpose, legal provisions, and applications in FIDIC, NEC, and JCT frameworks. This article covers recovery formulas, mobilization payments, price adjustment clauses, and strategies for managing contractor cash flow and project risks. A valuable guide for professionals navigating construction finance and legal contracts.