AIA Architect’s Supplemental Instruction (ASI) – Free Form and Usage Tips

Download our free AIA Architect’s Supplemental Instruction (ASI) form. Learn how to use it for minor changes with no cost/time impact, per AIA contracts.

Aia Architects Supplemental Instruction Form
Aia Architects Supplemental Instruction Form
English version

AIA Architect’s Supplemental Instruction (ASI) – Free Form & Usage Tips


Introduction

Under the AIA A201 – General Conditions of the Contract for Construction, an Architect’s Supplemental Instruction (ASI) allows the architect to authorize a minor change in the work that does not affect the contract sum or contract time.

Because ASIs apply only to zero-cost, zero-time changes, they are often used for clarifications, small adjustments, or minor corrections. If the contractor believes an ASI will have cost or time impact, it should be converted into a Construction Change Directive (CCD) or Change Order.

This mini guide focuses on the AIA ASI form available for free download from Quollnet, showing how to use it effectively in your projects.

Download the AIA ASI Form – PDF, Excel, WebP


Purpose of the ASI Form

The ASI form provides a standardized method for issuing instructions that:

  • Clarify design details without altering price or schedule.

  • Maintain a written record of minor adjustments.

  • Ensure all relevant parties (Owner, Contractor, Consultants) are notified.


When to Use an ASI

Examples of valid ASI situations:

  • Minor dimension adjustments.

  • Clarifications of finishes, colors, or materials.

  • Additional detail for an already approved design.

  • Correcting non-critical errors in drawings/specs.

If a proposed change affects cost or schedule — even slightly — it must not be issued as an ASI. Instead, use a CCD or Change Order.

For broader context on instructions in construction, see our Complete Guide to Site Instructions.


How to Fill the ASI Form

Header:

  • Project name & number.

  • Owner, Contractor, and Architect names.

  • ASI number and date.

Instruction Details:

  • Description of change/clarification.

  • Reference documents (drawings, specs, RFIs).

  • Reason for instruction.

Authorization Statement:

“This Supplemental Instruction authorizes a minor change in the Work not involving adjustment to the Contract Sum or extension of the Contract Time.”

Signatures & Distribution:

  • Architect’s signature and date.

  • Distribution list (Owner, Contractor, Consultants, File).


Best Practices for Using ASIs

  1. Confirm zero impact on cost and time before issuing.

  2. Describe changes clearly to avoid ambiguity.

  3. Include references to relevant drawings/specs.

  4. Maintain an ASI log to track all issued instructions.

  5. Ensure prompt distribution to all relevant parties.


Download the Form

Download AIA ASI Form – PDF
Download AIA ASI Form – Excel
Download AIA ASI Form – WebP


Related Reading

Elie Saad's photo
Elie Saad
Aug 10, 2025
0
44
697
1.49k+

Related Checklists


Floor Surface Preparation Inspection Checklist
✅ 15 items
Proper floor surface preparation is crucial for ensuring the longevity and quality of tile installations. Whether you're a professional tiler or a DIY enthusiast, this checklist will guide you through the essential steps to inspect and prepare floor surfaces before tiling. This will help prevent common issues such as tile cracking, adhesive failure, and uneven surfaces. By following this comprehensive checklist, you can ensure that your tiling project begins with a solid foundation, ultimately saving time and costs on potential repairs.
Site Handing Over Checklist for Employers and Contractors
✅ 12 items
The site handing over process marks a crucial transition from the employer to the contractor before the commencement of work. This phase ensures that all site conditions, documentation, and logistical arrangements are thoroughly checked and confirmed. The checklist covers essential aspects such as site access, boundary conditions, utilities, and safety measures to ensure a smooth transition. This step is vital for mitigating risks, ensuring compliance, and establishing a clear understanding of responsibilities. Our interactive checklist allows users to tick items, leave comments, and export reports as PDF or Excel, complete with a unique QR code for authenticity.
Substrate Inspection Checklist for Waterproofing
✅ 12 items
Ensuring the substrate is properly prepared and inspected is crucial before applying any waterproofing materials. This checklist guides construction professionals through a comprehensive inspection process to identify potential issues that could compromise the waterproofing application. By following this checklist, you will enhance the longevity and effectiveness of the waterproofing layer, prevent costly repairs, and ensure the structural integrity of the building. Whether you are a site manager or an inspector, these steps will help you perform a thorough evaluation of the substrate, ensuring it is ready for the next phase of construction.
Signage and Identification Installation Inspection Checklist
✅ 13 items
Inspecting signage and identification installations ensures that all signs are properly mounted, visible, and compliant with regulations. This process involves checking materials, placements, and adherence to safety standards. It is crucial for maintaining an organized and safe environment, especially in public or commercial spaces. The checklist includes inspecting various types of signs and their placements, ensuring they are free of damage, and verifying that they meet all relevant guidelines. Users can interact with this checklist online, make notes, and export their findings with a QR code for authentication.
Trigger/Action Response Plan: Holds, Thresholds, Escalation
✅ 24 items
Trigger/action response plan establishes clear thresholds, hold points, communications, and escalation paths across construction activities. This checklist guides teams to set control limits, build a notification matrix, and formalize an escalation protocol so responses are consistent when readings or events cross boundaries. It organizes trigger definitions, hold-point approvals, and message content without prescribing contractor remedies, keeping the plan focused on governance and decision-making. Coverage includes quality, safety, environmental, and schedule indicators per approved project specifications and authority requirements. Benefits include faster resolution, documented accountability, and fewer disputes because actions, roles, and timeframes are defined in advance. Use it during preconstruction or mobilization, then maintain it through change control as risks evolve. The plan reduces uncontrolled stoppages, near-miss escalation, and nonconformance sprawl by combining measured limits, decision authority, and reliable communication channels. Start in interactive mode to tick items, add project-specific comments, and export the approved plan as PDF/Excel with a QR-secured link for field access.

Related Articles


Fidic Site Instruction Form Download Usage
⏳ 3 min read
Fidic Site Instruction Form – Free Download And Usage Tips
Download our free FIDIC Site Instruction form. Learn how to use it in any FIDIC edition, track variations, and protect against disputes with proper records.
Site Instructions Construction Legal And Forms
⏳ 5 min read
Site Instructions In Construction: Legal Guide & Templates
Learn what site instructions (Engineer’s, Architect’s, PM’s Instructions, ASI, Work/Field Orders) mean legally in FIDIC, JCT, NEC & AIA, with free forms.
Site Clarification Rfi Free Templates Log Flowchart
⏳ 5 min read
Site Clarifications (rfis) — Definition, Legal & Free Templates
Learn what a site clarification (RFI) is, the legal line between clarification and instruction, and download free templates: RFI log (Excel/CSV), checklist, and flowchart.
Aia Construction Change Directive Form
⏳ 2 min read
Aia Construction Change Directive (ccd) – Free Form And Usage Tips
Download our free AIA Construction Change Directive (CCD) form. Learn how to use it for changes affecting cost/time when terms aren’t yet agreed.
Request For Quotation Rfq Form Template
⏳ 3 min read
Rfq Form Template For Procurement | Free Download (pdf, Excel, Word)
Download a free, customizable Request for Quotation (RFQ) form template. Ideal for small tenders; available in PDF, Excel, Word formats to streamline procurement.